Bathroom · domestic · fixed price

Job 3951

Complete
Cloakroom and utility refit
For Alistair Millard, Bishopston. Chris Moss (small works) with Kate Lyons. On site 16 Jan to 22 Jan, handed over 1 Feb 2026.
Agreed price
£10,150
ex VAT
Final margin
28.3%
quoted 29.4%
100% of the work done8 m²
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Quoted margin29.4%£2,986 on £10,150
Final margin28.3%£2,872 profit
Invoiced so far£10,150of £10,150, £10,150 paid
Where the money went
PersonHoursLabour costDifference
CM
Chris Moss
Small works and snagging fitter, £30/h at cost
40 h
of 38.5 h estimated
£1,200
of £1,155
+£45
SK
Sam Kerridge
Labourer and driver, £22/h at cost
8 h
of 9.5 h estimated
£176
of £209
-£33
Rule of thumb: 6 h per m².
Cost week by week
£7,278 spent over 2 weeks, against a £7,164 estimate
LabourMaterialsSubcontract
Extras and variations · 0
Variations →
No extras on this job.
Timesheets · 48 h, £1,376 at cost
Timesheets →
Week ofPersonHoursCostStatus
19 Jan
Tap for the days
CMChris Moss32 h
4 days
£960.00
at £30/h
approved
from the paper sheets
12 Jan
Tap for the days
CMChris Moss8 h
1 day
£240.00
at £30/h
approved
from the paper sheets
12 Jan
Tap for the days
SKSam Kerridge8 h
1 day
£176.00
at £22/h
approved
from the paper sheets
Purchases · 4, £4,502
Purchases →
OrderWhatStatusNet
PO-5132
Brackwell Tiles, raised 15 Jan
Tiles and adhesiveDelivered 20 Jan, billed£667.29
PO-5130
Avonmere Builders Merchants, raised 13 Jan
Board and sundriesDelivered 16 Jan, billed£443.02
PO-5122
Linmouth Bathroom Supply, raised 6 Jan
Sanitaryware and brasswareDelivered 15 Jan, billed£2,261.19
PO-5106
Wrenfold Kitchen Supply, raised 27 Dec 2025
Utility unitsDelivered 16 Jan, billed£1,130.62
Subcontractor invoices · 4, £1,400
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3428
Jon Haskins Plumbing and Heating, 22 Jan
Plumbing, second fixPaid£525.00
SC-3429
Gary Pullen Electrical, 22 Jan
Electrics, second fixPaid£175.00
SC-3422
Jon Haskins Plumbing and Heating, 19 Jan
Plumbing, first fixPaid£525.00
SC-3418
Gary Pullen Electrical, 16 Jan
Electrics, first fixPaid£175.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2211
issued 29 Dec 2025
Deposit
1 line
Paid 10 Jan£2,537.50£3,045.00posted
INV-2223
issued 19 Jan
Progress
1 line
Paid 25 Jan£5,075.00£6,090.00posted
INV-2240
issued 2 Feb
Completion
1 line
Paid 15 Feb£2,537.50£3,045.00posted
Stages £10,150 + billed extras £0 = £10,150 on invoices. £10,150 sent, £10,150 paid.
AM
Alistair Millard
Alistair Millard · client since 17 Nov 2025
Site94 Hollybush Lane, Bishopston
Phone07700 900701
PortalLive: progress, extras, invoices
See what Alistair sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewChris Moss, small works
Booked26 Dec 2025
StartedFri 16 Jan
Handed over1 Feb 2026
Timeline
Handed over and closed
Kate · 1 Feb 15:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £525.00
Jon Haskins · 22 Jan 17:00
Gary Pullen Electrical: Electrics, second fix, £175.00
Gary Pullen · 22 Jan 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £525.00
Jon Haskins · 19 Jan 17:00
Gary Pullen Electrical: Electrics, first fix, £175.00
Gary Pullen · 16 Jan 17:00
First day on site: Chris, Sam
Site app · 16 Jan 07:30
Booked: £10,150 ex VAT
Owen · 26 Dec 2025 11:00