Bathroom with walk-in shower
For Victoria and Richard Upton, Saltford. Crew B with Kate Lyons. On site 14 May to 26 May, handed over 30 May 2026.
Agreed price
£12,350
ex VAT
Final margin
-3.9%
quoted 25.2%
100% of the work done24 m² tiled
Client's portal view
This job lost money
It finished £484.86 down. Tiling overran: labour took 184 h against 101 h estimated, and materials came to £5,313 against £4,200. Moved the radiator and added a towel rail (V-3981-1, £680) was agreed on a handshake and never billed. It ran before the site app: nothing flagged it until the job was closed.
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Extras captured on site
1 extra on this job
Every extra ↓
Quoted margin25.2%£3,108 on £12,350
Final margin-3.9%-£485 profit
Invoiced so far£12,350of £12,350, £12,350 paid
Where the money went
PersonHoursLabour costDifference
MT
Mike Tanner
Lead fitter and tiler, crew B, £34/h at cost
64 h
of 40.5 h estimated
£2,176
of £1,377
+£799
RH
Ryan Hale
Fitter, crew B, £30/h at cost
64 h
of 35.5 h estimated
£1,920
of £1,065
+£855
CW
Callum Webb
Apprentice fitter, crew B, £16/h at cost
56 h
of 25 h estimated
£896
of £400
+£496
True labour cost. The 25 bathrooms finished this year really took 4.5 h per m² tiled, against the old rule of 4.2. This job: 24 m² tiled, priced on 101 h. Rule of thumb: 4.2 h per m² tiled. New quotes now use the true rate →
Cost week by week
£12,835 spent over 3 weeks, against a £9,242 estimate
LabourMaterialsSubcontract
Extras and variations · 1
Variations →
Timesheets · 184 h, £4,992 at cost
Timesheets →
Week ofPersonHoursCostStatus
25 May
Tap for the days
CWCallum Webb8 h
1 day
£128.00
at £16/h
approved
from the paper sheets
25 May
Tap for the days
MTMike Tanner8 h
1 day
£272.00
at £34/h
approved
from the paper sheets
25 May
Tap for the days
RHRyan Hale8 h
1 day
£240.00
at £30/h
approved
from the paper sheets
18 May
Tap for the days
CWCallum Webb32 h
4 days
£512.00
at £16/h
approved
from the paper sheets
18 May
Tap for the days
MTMike Tanner40 h
5 days
£1,360.00
at £34/h
approved
from the paper sheets
18 May
Tap for the days
RHRyan Hale40 h
5 days
£1,200.00
at £30/h
approved
from the paper sheets
11 May
Tap for the days
CWCallum Webb16 h
2 days
£256.00
at £16/h
approved
from the paper sheets
11 May
Tap for the days
MTMike Tanner16 h
2 days
£544.00
at £34/h
approved
from the paper sheets
11 May
Tap for the days
RHRyan Hale16 h
2 days
£480.00
at £30/h
approved
from the paper sheets
Purchases · 5, £5,313
Purchases →
OrderWhatStatusNet
PO-5303
Brackwell Tiles, raised 14 May
Wall and floor tiles, adhesive, groutDelivered 19 May, billed£1,433.38
PO-5296
Voltmere Electrical Wholesale, raised 11 May
Lighting and extractorDelivered 14 May, billed£257.68
PO-5297
Avonmere Builders Merchants, raised 11 May
Board, tanking and sundriesDelivered 14 May, billed£680.89
PO-5293
Kestle Timber, raised 10 May
Timber and fixingsDelivered 14 May, billed£369.68
PO-5286
Linmouth Bathroom Supply, raised 4 May
Sanitaryware and brasswareDelivered 13 May, billed£2,571.23
Subcontractor invoices · 5, £2,530
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3587
Jon Haskins Plumbing and Heating, 26 May
Plumbing, second fixPaid£782.00
SC-3588
Gary Pullen Electrical, 26 May
Electrics, second fixPaid£230.00
SC-3582
Mark Dent Plastering, 19 May
Plastering, skim and making goodPaid£506.00
SC-3576
Jon Haskins Plumbing and Heating, 15 May
Plumbing, first fixPaid£782.00
SC-3577
Gary Pullen Electrical, 15 May
Electrics, first fixPaid£230.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2302
issued 17 Apr
Deposit
1 line
Paid 2 May£3,087.50£3,705.00posted
INV-2327
issued 20 May
Progress
1 line
Paid 26 May£6,175.00£7,410.00posted
INV-2335
issued 1 Jun
Completion
1 line
Paid 11 Jun£3,087.50£3,705.00posted
Stages £12,350 + billed extras £0 = £12,350 on invoices. £12,350 sent, £12,350 paid.
VR
Victoria and Richard Upton
Victoria Upton · client since 15 Mar 2026
Site26 Park Avenue, Saltford
Phone07700 900747
PortalLive: progress, extras, invoices
See what Victoria sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewCrew B: Mike, Ryan, Callum
Booked15 Apr 2026
StartedThu 14 May
Handed over30 May 2026
Timeline
Handed over and closed
Kate · 30 May 15:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £782.00
Jon Haskins · 26 May 17:00
Gary Pullen Electrical: Electrics, second fix, £230.00
Gary Pullen · 26 May 17:00
Mark Dent Plastering: Plastering, skim and making good, £506.00
Mark Dent · 19 May 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £782.00
Jon Haskins · 15 May 17:00
Gary Pullen Electrical: Electrics, first fix, £230.00
Gary Pullen · 15 May 17:00
First day on site: Callum, Mike, Ryan
Site app · 14 May 07:30
Booked: £12,350 ex VAT
Owen · 15 Apr 11:00