Kitchen · domestic · fixed price

Job 3984

Complete
Kitchen fit-out
For Catherine Keedwell, Clevedon. Crew A with Kate Lyons. On site 15 Jun to 22 Jun, handed over 29 Jun 2026.
Agreed price
£17,200
ex VAT
Final margin
20.5%
quoted 24.3%
100% of the work done11 cabinets
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Quoted margin24.3%£4,174 on £17,200
Final margin20.5%£3,532 profit
Invoiced so far£17,200of £17,200, £17,200 paid
Where the money went
PersonHoursLabour costDifference
SR
Steve Rowe
Lead fitter, crew A, £34/h at cost
48 h
of 44.5 h estimated
£1,632
of £1,513
+£119
LD
Liam Doyle
Joiner, crew A, £30/h at cost
48 h
of 44.5 h estimated
£1,440
of £1,335
+£105
JP
Josh Penrose
Apprentice joiner, crew A, £16/h at cost
40 h
of 28 h estimated
£640
of £448
+£192
RF
Rob Finch
Decorator, £28/h at cost
8 h
of 10 h estimated
£224
of £280
-£56
True labour cost. The 15 kitchens finished this year really took 12.95 h per cabinet, against the old rule of 11.5. This job: 11 cabinets, priced on 127 h. Rule of thumb: 11.5 h per cabinet. New quotes now use the true rate →
Cost week by week
£13,668 spent over 3 weeks, against a £13,026 estimate
LabourMaterialsSubcontract
Extras and variations · 0
Variations →
No extras on this job.
Timesheets · 144 h, £3,936 at cost
Timesheets →
Week ofPersonHoursCostStatus
22 Jun
Tap for the days
JPJosh Penrose8 h
1 day
£128.00
at £16/h
approved
22 Jun
Tap for the days
LDLiam Doyle8 h
1 day
£240.00
at £30/h
approved
22 Jun
Tap for the days
RFRob Finch8 h
1 day
£224.00
at £28/h
approved
22 Jun
Tap for the days
SRSteve Rowe8 h
1 day
£272.00
at £34/h
approved
15 Jun
Tap for the days
JPJosh Penrose32 h
4 days
£512.00
at £16/h
approved
15 Jun
Tap for the days
LDLiam Doyle40 h
5 days
£1,200.00
at £30/h
approved
15 Jun
Tap for the days
SRSteve Rowe40 h
5 days
£1,360.00
at £34/h
approved
Purchases · 6, £7,082
Purchases →
OrderWhatStatusNet
PO-5345
Avonmere Builders Merchants, raised 12 Jun
Plaster, board and sundriesDelivered 15 Jun, billed£283.92
PO-5346
Voltmere Electrical Wholesale, raised 12 Jun
Lighting and electrical fittingsDelivered 15 Jun, billed£277.19
PO-5347
Brackwell Tiles, raised 12 Jun
Splashback tiles and adhesiveDelivered 17 Jun, billed£283.30
PO-5343
Kestle Timber, raised 11 Jun
Timber, panels and fixingsDelivered 15 Jun, billed£199.81
PO-5333
Halbrook Worktops, raised 7 Jun
Worktops, templated and fittedDelivered 19 Jun, billed£1,884.86
PO-5307
Wrenfold Kitchen Supply, raised 21 May
Kitchen units and doorsDelivered 12 Jun, billed£4,153.37
Subcontractor invoices · 5, £2,650
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3628
Gary Pullen Electrical, 22 Jun
Electrics, second fixPaid£595.00
SC-3629
Jon Haskins Plumbing and Heating, 22 Jun
Plumbing, second fixPaid£435.00
SC-3621
Mark Dent Plastering, 17 Jun
Plastering, skim and making goodPaid£590.00
SC-3619
Jon Haskins Plumbing and Heating, 16 Jun
Plumbing, first fixPaid£435.00
SC-3617
Gary Pullen Electrical, 15 Jun
Electrics, first fixPaid£595.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2314
issued 5 May
Deposit
1 line
Paid 16 May£4,300.00£5,160.00posted
INV-2355
issued 18 Jun
Progress
1 line
Paid 30 Jun£8,600.00£10,320.00posted
INV-2367
issued 30 Jun
Completion
1 line
Paid 10 Jul£4,300.00£5,160.00posted
Stages £17,200 + billed extras £0 = £17,200 on invoices. £17,200 sent, £17,200 paid.
CK
Catherine Keedwell
Catherine Keedwell · client since 16 Apr 2026
Site25 Hollybush Lane, Clevedon
Phone07700 900345
PortalLive: progress, extras, invoices
See what Catherine sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewCrew A: Steve, Liam, Josh
Booked1 May 2026
StartedMon 15 Jun
Handed over29 Jun 2026
Timeline
Handed over and closed
Kate · 29 Jun 15:00
Gary Pullen Electrical: Electrics, second fix, £595.00
Gary Pullen · 22 Jun 17:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £435.00
Jon Haskins · 22 Jun 17:00
Mark Dent Plastering: Plastering, skim and making good, £590.00
Mark Dent · 17 Jun 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £435.00
Jon Haskins · 16 Jun 17:00
Gary Pullen Electrical: Electrics, first fix, £595.00
Gary Pullen · 15 Jun 17:00
First day on site: Josh, Liam, Steve
Site app · 15 Jun 07:30
Booked: £17,200 ex VAT
Owen · 1 May 11:00