Bathroom · domestic · fixed price
Job 4010
CompleteBathroom refit
For Henry Cleeve, Portishead. Crew B with Kate Lyons. On site 17 Aug to 20 Aug, handed over 25 Aug 2026.
Agreed price
£11,900
ex VAT
Final margin
27.6%
quoted 26.0%
100% of the work done22 m² tiled
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
CostEstimateActual so farFinalDifference
Labour88 h logged against 92.5 h estimated, at each person's true cost rate£2,601£2,432£2,432-£1696.5% underMaterials5 purchases received£4,050£4,034£4,034-£160.4% underSubcontract5 invoices from the plumber, electrician and plasterer£2,150£2,150£2,150On budgetTotal cost£8,801£8,616£8,616-£1852.1% underQuoted margin26.0%£3,099 on £11,900
Final margin27.6%£3,284 profit
Invoiced so far£11,900of £11,900, £11,900 paid
Where the money went
| Person | Hours | Labour cost | Difference |
|---|---|---|---|
MT Mike Tanner Lead fitter and tiler, crew B, £34/h at cost | 32 h of 37 h estimated | £1,088 of £1,258 | -£170 |
RH Ryan Hale Fitter, crew B, £30/h at cost | 32 h of 32.5 h estimated | £960 of £975 | -£15 |
CW Callum Webb Apprentice fitter, crew B, £16/h at cost | 24 h of 23 h estimated | £384 of £368 | +£16 |
True labour cost. The 25 bathrooms finished this year really took 4.5 h per m² tiled, against the old rule of 4.2. This job: 22 m² tiled, priced on 92.5 h. Rule of thumb: 4.2 h per m² tiled. New quotes now use the true rate →
| Estimate line | Estimate | Ordered | Received | Difference |
|---|---|---|---|---|
Sanitaryware and brassware Linmouth Bathroom Supply, PO-5425 | £1,940 | £1,942 | £1,942 | +£2 |
Wall and floor tiles, adhesive, grout Brackwell Tiles, PO-5440 | £1,090 | £1,089 | £1,089 | -£1 |
Board, tanking and sundries Avonmere Builders Merchants, PO-5444 | £530 | £515 | £515 | -£15 |
Lighting and extractor Voltmere Electrical Wholesale, PO-5443 | £200 | £200 | £200 | on budget |
Timber and fixings Kestle Timber, PO-5439 | £290 | £288 | £288 | -£2 |
Materials count when they are delivered and signed for on site. Nothing is on order and not received. Supplier bills post to Xero from here.
| Trade | Agreed | Invoiced | Difference |
|---|---|---|---|
Plumbing Jon Haskins Plumbing and Heating, 2 invoices | £1,330 | £1,330 | on the agreed price |
Electrics Gary Pullen Electrical, 2 invoices | £390 | £390 | on the agreed price |
Plastering Mark Dent Plastering, 1 invoice | £430 | £430 | on the agreed price |
The forecast counts each trade at its agreed price until it invoices more.
Agreed price
stage invoices at 25%, 50% and 25%
£11,900.00
Revenue
£11,900.00
Labour
final
- £2,432.00
Materials
final
- £4,034.09
Subcontract
final
- £2,150.00
Profit
27.6% margin, quoted at 26.0% (£3,099)
£3,283.91
Cost week by week
£8,616 spent over 2 weeks, against a £8,801 estimate
LabourMaterialsSubcontract
| Week of | Hours | Labour | Materials | Subcontract | Total |
|---|---|---|---|---|---|
| 10 Aug | 0 h | £0 | £1,942 | £0 | £1,942 |
| 17 Aug | 88 h | £2,432 | £2,092 | £2,150 | £6,674 |
Extras and variations · 0
Variations →No extras on this job.
Timesheets · 88 h, £2,432 at cost
Timesheets →| Week of | Person | Hours | Cost | Status |
|---|---|---|---|---|
| 17 Aug Tap for the days Mon 17 Aug8 hTS-01052 Tue 18 Aug8 hTS-01062 Thu 20 Aug8 hTS-01082 | CWCallum Webb | 24 h 3 days | £384.00 at £16/h | approved |
| 17 Aug Tap for the days Mon 17 Aug8 hTS-01057 Tue 18 Aug8 hTS-01067 Wed 19 Aug8 hTS-01075 Thu 20 Aug8 hTS-01087 | MTMike Tanner | 32 h 4 days | £1,088.00 at £34/h | approved |
| 17 Aug Tap for the days Mon 17 Aug8 hTS-01059 Tue 18 Aug8 hTS-01069 Wed 19 Aug8 hTS-01077 Thu 20 Aug8 hTS-01089 | RHRyan Hale | 32 h 4 days | £960.00 at £30/h | approved |
Purchases · 5, £4,034
Purchases →| Order | What | Status | Net |
|---|---|---|---|
| PO-5443 Voltmere Electrical Wholesale, raised 14 Aug | Lighting and extractor | Delivered 17 Aug, billed | £199.75 |
| PO-5444 Avonmere Builders Merchants, raised 14 Aug | Board, tanking and sundries | Delivered 17 Aug, billed | £514.95 |
| PO-5439 Kestle Timber, raised 13 Aug | Timber and fixings | Delivered 17 Aug, billed | £288.43 |
| PO-5440 Brackwell Tiles, raised 13 Aug | Wall and floor tiles, adhesive, grout | Delivered 18 Aug, billed | £1,089.32 |
| PO-5425 Linmouth Bathroom Supply, raised 5 Aug | Sanitaryware and brassware | Delivered 14 Aug, billed | £1,941.64 |
Subcontractor invoices · 5, £2,150
Tap one for the subcontractor| Invoice | Work | Status | Amount |
|---|---|---|---|
| SC-3711 Jon Haskins Plumbing and Heating, 20 Aug | Plumbing, second fix | Paid | £665.00 |
Jon Haskins Plumbing and HeatingPlumber, Bedminster. Day rate £250. Insured to May 2027. Gas Safe registered. | |||
| SC-3712 Gary Pullen Electrical, 20 Aug | Electrics, second fix | Paid | £195.00 |
Gary Pullen ElectricalElectrician, Kingswood. Day rate £260. Insured to Mar 2027. Domestic jobs. Part P registered. | |||
| SC-3708 Mark Dent Plastering, 18 Aug | Plastering, skim and making good | Paid | £430.00 |
Mark Dent PlasteringPlasterer, Brislington. Day rate £220. Insured to Feb 2027. Skim and dry-lining. | |||
| SC-3705 Jon Haskins Plumbing and Heating, 17 Aug | Plumbing, first fix | Paid | £665.00 |
Jon Haskins Plumbing and HeatingPlumber, Bedminster. Day rate £250. Insured to May 2027. Gas Safe registered. | |||
| SC-3706 Gary Pullen Electrical, 17 Aug | Electrics, first fix | Paid | £195.00 |
Gary Pullen ElectricalElectrician, Kingswood. Day rate £260. Insured to Mar 2027. Domestic jobs. Part P registered. | |||
Invoices · posted to Xero when sent
Billing →| Invoice | Stage | Status | Net | Gross | Xero |
|---|---|---|---|---|---|
| INV-2386 issued 20 Jul | Deposit 1 line | Paid 5 Aug | £2,975.00 | £3,570.00 | posted |
| INV-2410 issued 18 Aug | Progress 1 line | Paid 23 Aug | £5,950.00 | £7,140.00 | posted |
| INV-2416 issued 26 Aug | Completion 1 line | Paid 3 Sep | £2,975.00 | £3,570.00 | posted |
Stages £11,900 + billed extras £0 = £11,900 on invoices. £11,900 sent, £11,900 paid.
Client
Client page →Henry Cleeve
Henry Cleeve · client since 18 Jun 2026
Site83 Orchard Rise, Portishead
Phone07700 900467
PortalLive: progress, extras, invoices
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewCrew B: Mike, Ryan, Callum
Booked18 Jul 2026
StartedMon 17 Aug
Handed over25 Aug 2026
Timeline
Handed over and closed
Kate · 25 Aug 15:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £665.00
Jon Haskins · 20 Aug 17:00
Gary Pullen Electrical: Electrics, second fix, £195.00
Gary Pullen · 20 Aug 17:00
Mark Dent Plastering: Plastering, skim and making good, £430.00
Mark Dent · 18 Aug 17:00
Delivered: Wall and floor tiles, adhesive, grout from Brackwell Tiles (PO-5440, £1,089.32)
Mike Tanner · 18 Aug 08:15
Jon Haskins Plumbing and Heating: Plumbing, first fix, £665.00
Jon Haskins · 17 Aug 17:00
Gary Pullen Electrical: Electrics, first fix, £195.00
Gary Pullen · 17 Aug 17:00
Delivered: Timber and fixings from Kestle Timber (PO-5439, £288.43)
Mike Tanner · 17 Aug 08:15
Delivered: Lighting and extractor from Voltmere Electrical Wholesale (PO-5443, £199.75)
Mike Tanner · 17 Aug 08:15
Delivered: Board, tanking and sundries from Avonmere Builders Merchants (PO-5444, £514.95)
Mike Tanner · 17 Aug 08:15
First day on site: Callum, Mike, Ryan
Site app · 17 Aug 07:30
Delivered: Sanitaryware and brassware from Linmouth Bathroom Supply (PO-5425, £1,941.64)
Mike Tanner · 14 Aug 08:15
Booked: £11,900 ex VAT
Owen · 18 Jul 11:00