Bathroom · domestic · fixed price
Job 4014
CompleteFamily bathroom
For Louise Durbin, Bedminster. Crew B with Kate Lyons. On site 24 Aug to 27 Aug, handed over 6 Sep 2026.
Agreed price
£11,450
ex VAT
Final margin
23.6%
quoted 24.6%
100% of the work done21 m² tiled
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
CostEstimateActual so farFinalDifference
Labour88 h logged against 88.5 h estimated, at each person's true cost rate£2,489£2,432£2,432-£572.3% underMaterials5 purchases received£4,000£4,168£4,168+£1684.2% overSubcontract5 invoices from the plumber, electrician and plasterer£2,150£2,150£2,150On budgetTotal cost£8,639£8,750£8,750+£1111.3% overQuoted margin24.6%£2,811 on £11,450
Final margin23.6%£2,700 profit
Invoiced so far£11,450of £11,450, £11,450 paid
Where the money went
| Person | Hours | Labour cost | Difference |
|---|---|---|---|
MT Mike Tanner Lead fitter and tiler, crew B, £34/h at cost | 32 h of 35.5 h estimated | £1,088 of £1,207 | -£119 |
RH Ryan Hale Fitter, crew B, £30/h at cost | 32 h of 31 h estimated | £960 of £930 | +£30 |
CW Callum Webb Apprentice fitter, crew B, £16/h at cost | 24 h of 22 h estimated | £384 of £352 | +£32 |
True labour cost. The 25 bathrooms finished this year really took 4.5 h per m² tiled, against the old rule of 4.2. This job: 21 m² tiled, priced on 88.5 h. Rule of thumb: 4.2 h per m² tiled. New quotes now use the true rate →
| Estimate line | Estimate | Ordered | Received | Difference |
|---|---|---|---|---|
Sanitaryware and brassware Linmouth Bathroom Supply, PO-5437 | £1,920 | £1,984 | £1,984 | +£64 |
Wall and floor tiles, adhesive, grout Brackwell Tiles, PO-5449 | £1,080 | £1,143 | £1,143 | +£63 |
Board, tanking and sundries Avonmere Builders Merchants, PO-5451 | £520 | £552 | £552 | +£32 |
Lighting and extractor Voltmere Electrical Wholesale, PO-5452 | £200 | £201 | £201 | +£1 |
Timber and fixings Kestle Timber, PO-5450 | £280 | £288 | £288 | +£8 |
Materials count when they are delivered and signed for on site. Nothing is on order and not received. Supplier bills post to Xero from here.
| Trade | Agreed | Invoiced | Difference |
|---|---|---|---|
Plumbing Jon Haskins Plumbing and Heating, 2 invoices | £1,330 | £1,330 | on the agreed price |
Electrics Gary Pullen Electrical, 2 invoices | £390 | £390 | on the agreed price |
Plastering Mark Dent Plastering, 1 invoice | £430 | £430 | on the agreed price |
The forecast counts each trade at its agreed price until it invoices more.
Agreed price
stage invoices at 25%, 50% and 25%
£11,450.00
Revenue
£11,450.00
Labour
final
- £2,432.00
Materials
final
- £4,167.60
Subcontract
final
- £2,150.00
Profit
23.6% margin, quoted at 24.6% (£2,811)
£2,700.40
Cost week by week
£8,750 spent over 2 weeks, against a £8,639 estimate
LabourMaterialsSubcontract
| Week of | Hours | Labour | Materials | Subcontract | Total |
|---|---|---|---|---|---|
| 17 Aug | 0 h | £0 | £1,984 | £0 | £1,984 |
| 24 Aug | 88 h | £2,432 | £2,184 | £2,150 | £6,766 |
Extras and variations · 0
Variations →No extras on this job.
Timesheets · 88 h, £2,432 at cost
Timesheets →| Week of | Person | Hours | Cost | Status |
|---|---|---|---|---|
| 24 Aug Tap for the days Mon 24 Aug8 hTS-01101 Tue 25 Aug8 hTS-01112 Thu 27 Aug8 hTS-01128 | CWCallum Webb | 24 h 3 days | £384.00 at £16/h | approved |
| 24 Aug Tap for the days Mon 24 Aug8 hTS-01106 Tue 25 Aug8 hTS-01117 Wed 26 Aug8 hTS-01124 Thu 27 Aug8 hTS-01133 | MTMike Tanner | 32 h 4 days | £1,088.00 at £34/h | approved |
| 24 Aug Tap for the days Mon 24 Aug8 hTS-01107 Tue 25 Aug8 hTS-01118 Wed 26 Aug8 hTS-01125 Thu 27 Aug8 hTS-01134 | RHRyan Hale | 32 h 4 days | £960.00 at £30/h | approved |
Purchases · 5, £4,168
Purchases →| Order | What | Status | Net |
|---|---|---|---|
| PO-5451 Avonmere Builders Merchants, raised 21 Aug | Board, tanking and sundries | Delivered 24 Aug, billed | £551.61 |
| PO-5452 Voltmere Electrical Wholesale, raised 21 Aug | Lighting and extractor | Delivered 24 Aug, billed | £201.28 |
| PO-5449 Brackwell Tiles, raised 20 Aug | Wall and floor tiles, adhesive, grout | Delivered 25 Aug, billed | £1,142.56 |
| PO-5450 Kestle Timber, raised 20 Aug | Timber and fixings | Delivered 24 Aug, billed | £288.48 |
| PO-5437 Linmouth Bathroom Supply, raised 12 Aug | Sanitaryware and brassware | Delivered 21 Aug, billed | £1,983.67 |
Subcontractor invoices · 5, £2,150
Tap one for the subcontractor| Invoice | Work | Status | Amount |
|---|---|---|---|
| SC-3720 Jon Haskins Plumbing and Heating, 27 Aug | Plumbing, second fix | Paid | £665.00 |
Jon Haskins Plumbing and HeatingPlumber, Bedminster. Day rate £250. Insured to May 2027. Gas Safe registered. | |||
| SC-3721 Gary Pullen Electrical, 27 Aug | Electrics, second fix | Paid | £195.00 |
Gary Pullen ElectricalElectrician, Kingswood. Day rate £260. Insured to Mar 2027. Domestic jobs. Part P registered. | |||
| SC-3718 Mark Dent Plastering, 25 Aug | Plastering, skim and making good | Paid | £430.00 |
Mark Dent PlasteringPlasterer, Brislington. Day rate £220. Insured to Feb 2027. Skim and dry-lining. | |||
| SC-3716 Jon Haskins Plumbing and Heating, 24 Aug | Plumbing, first fix | Paid | £665.00 |
Jon Haskins Plumbing and HeatingPlumber, Bedminster. Day rate £250. Insured to May 2027. Gas Safe registered. | |||
| SC-3717 Gary Pullen Electrical, 24 Aug | Electrics, first fix | Paid | £195.00 |
Gary Pullen ElectricalElectrician, Kingswood. Day rate £260. Insured to Mar 2027. Domestic jobs. Part P registered. | |||
Invoices · posted to Xero when sent
Billing →| Invoice | Stage | Status | Net | Gross | Xero |
|---|---|---|---|---|---|
| INV-2396 issued 29 Jul | Deposit 1 line | Paid 7 Aug | £2,862.50 | £3,435.00 | posted |
| INV-2415 issued 25 Aug | Progress 1 line | Paid 10 Sep | £5,725.00 | £6,870.00 | posted |
| INV-2425 issued 7 Sep | Completion 1 line | Paid 22 Sep | £2,862.50 | £3,435.00 | posted |
Stages £11,450 + billed extras £0 = £11,450 on invoices. £11,450 sent, £11,450 paid.
Client
Client page →Louise Durbin
Louise Durbin · client since 25 Jun 2026
Site25 Rowan Drive, Bedminster
Phone07700 900104
PortalLive: progress, extras, invoices
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewCrew B: Mike, Ryan, Callum
Booked27 Jul 2026
StartedMon 24 Aug
Handed over6 Sep 2026
Timeline
Handed over and closed
Kate · 6 Sep 15:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £665.00
Jon Haskins · 27 Aug 17:00
Gary Pullen Electrical: Electrics, second fix, £195.00
Gary Pullen · 27 Aug 17:00
Mark Dent Plastering: Plastering, skim and making good, £430.00
Mark Dent · 25 Aug 17:00
Delivered: Wall and floor tiles, adhesive, grout from Brackwell Tiles (PO-5449, £1,142.56)
Mike Tanner · 25 Aug 08:15
Jon Haskins Plumbing and Heating: Plumbing, first fix, £665.00
Jon Haskins · 24 Aug 17:00
Gary Pullen Electrical: Electrics, first fix, £195.00
Gary Pullen · 24 Aug 17:00
Delivered: Timber and fixings from Kestle Timber (PO-5450, £288.48)
Mike Tanner · 24 Aug 08:15
Delivered: Board, tanking and sundries from Avonmere Builders Merchants (PO-5451, £551.61)
Mike Tanner · 24 Aug 08:15
Delivered: Lighting and extractor from Voltmere Electrical Wholesale (PO-5452, £201.28)
Mike Tanner · 24 Aug 08:15
First day on site: Callum, Mike, Ryan
Site app · 24 Aug 07:30
Delivered: Sanitaryware and brassware from Linmouth Bathroom Supply (PO-5437, £1,983.67)
Mike Tanner · 21 Aug 08:15
Booked: £11,450 ex VAT
Owen · 27 Jul 11:00