Variation V-3959-1
Not captured yet
This is the next number for an extra on Job 3959 (Gazzard). It fills in the moment a fitter captures one on the crew phone, with the client's signature.
Extra on Job 3959 · Kitchen fit-out
V-3959-1
BilledCaptured on the crew phone todayExtra wall unit and filler
For Lisa Gazzard, Saltford. Raised by Steve Rowe on Mon 16 Mar (before the site app, from the job sheet).
Price to the client
£1,700
What it cost us
£1,030
Margin on it
£670
See it in the client portalReminders go automatically every 3 working days.
Adds them to the completion invoice going out Fri 16 Oct, posted to Xero as a draft. The same Try-it as the dashboard.
Open DRAFT-01On DRAFT-01, the completion invoice going out Fri 16 Oct. Job 3959 is back to its quoted margin.
Job 3959 has no invoice waiting to go out. It goes on the next stage invoice, or on its own invoice today if Kate sends one.
Sent today 10:42
From site to money in the bank
Billed on INV-2284, paid- RecordedMon 16 Mar 11:30From the job sheet
- PricedOn the job sheet
- Client approvedTue 17 Mar 19:00By email
- BilledMon 30 Mar 16:00On INV-2284
- PaidFri 10 Apr 10:30Matched from Xero
What the client asked for, and why
Imported from the job sheet and the Xero invoice.
No photos: recorded from the job sheet before the site app.
Price build-up
from the estimate when it was pricedLabour20 h at £30.00 an hour£600.00
MaterialsFrom the estimate£430.00
Cost to Larchfield£1,030.00
Price to the client, ex VAT£1,700.00
Margin on the extra£670.00, 39.4%
Everything that happened to it
oldest firstRecorded from the job sheet
Mon 16 Mar 11:30 · Steve Rowe
Approved by email
Tue 17 Mar 19:00 · Lisa Gazzard
Mon 30 Mar 16:00 · Auto
Fri 10 Apr 10:30 · Xero
Client sign-off
Approved by email
Approved by email by Lisa Gazzard, Tue 17 Mar 19:00.
Billed on
Posted to XeroQuoted margin24.5%
Final margin24.5%
Captured on the crew phone today