Variation V-3989-1
Not captured yet
This is the next number for an extra on Job 3989 (Naish). It fills in the moment a fitter captures one on the crew phone, with the client's signature.
Extra on Job 3989 · Kitchen and utility fit-out
V-3989-1
BilledCaptured on the crew phone todayExtra wall unit and filler
For Elaine and Graham Naish, Bedminster. Raised by Steve Rowe on Fri 26 Jun.
Price to the client
£1,140
What it cost us
£695
Margin on it
£445
See it in the client portalReminders go automatically every 3 working days.
Adds them to the completion invoice going out Fri 16 Oct, posted to Xero as a draft. The same Try-it as the dashboard.
Open DRAFT-01On DRAFT-01, the completion invoice going out Fri 16 Oct. Job 3989 is back to its quoted margin.
Job 3989 has no invoice waiting to go out. It goes on the next stage invoice, or on its own invoice today if Kate sends one.
Sent today 10:42
From site to money in the bank
Billed on INV-2374, paid- Captured on siteFri 26 Jun 11:30Steve Rowe
- PricedFri 26 Jun 16:00Kate Lyons
- Client approvedSat 27 Jun 19:00In the client portal
- BilledMon 6 Jul 16:00On INV-2374
- PaidFri 17 Jul 10:30Matched from Xero
What the client asked for, and why
Captured on site in the crew app.
Photo 126 Jun 11:30
Price build-up
from the estimate when it was pricedLabour13.5 h at £30.00 an hour£405.00
MaterialsFrom the estimate£290.00
Cost to Larchfield£695.00
Price to the client, ex VAT£1,140.00
Margin on the extra£445.00, 39.0%
Everything that happened to it
oldest firstCaptured on site in the crew app, 1 photo
Fri 26 Jun 11:30 · Steve Rowe
Priced at £1,140
Fri 26 Jun 16:00 · Kate Lyons
Approved in the client portal
Sat 27 Jun 19:00 · Elaine Naish
Mon 6 Jul 16:00 · Auto
Fri 17 Jul 10:30 · Xero
Client sign-off
Approved in the portal
Approved in the client portal by Elaine Naish, Sat 27 Jun 19:00.
Billed on
Posted to XeroQuoted margin23.2%
Final margin28.7%
Captured on the crew phone today