LIVE DEMO
Kitchen · domestic · fixed price

Job 3942

Complete
Kitchen fit-out
For Stuart Thornton, Chew Magna. Crew A with Kate Lyons. On site 5 Jan to 15 Jan, handed over 21 Jan 2026.
Agreed price
£25,850
ex VAT, +£1,040 extras billed
Final margin
26.9%
quoted 25.7%
100% of the work done17 cabinets
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Extras captured on site
1 extra on this job
Every extra ↓
Quoted margin25.7%£6,644 on £25,850
Final margin26.9%£7,245 profit
Invoiced so far£26,890of £26,890, £26,890 paid
Where the money went
PersonHoursLabour costDifference
SR
Steve Rowe
Lead fitter, crew A, £34/h at cost
72 h
of 68.5 h estimated
£2,448
of £2,329
+£119
LD
Liam Doyle
Joiner, crew A, £30/h at cost
72 h
of 68.5 h estimated
£2,160
of £2,055
+£105
JP
Josh Penrose
Apprentice joiner, crew A, £16/h at cost
56 h
of 43 h estimated
£896
of £688
+£208
RF
Rob Finch
Decorator, £28/h at cost
16 h
of 15.5 h estimated
£448
of £434
+£14
True labour cost. The 15 kitchens finished this year really took 12.95 h per cabinet, against the old rule of 11.5. This job: 17 cabinets, priced on 195.5 h. Rule of thumb: 11.5 h per cabinet. New quotes now use the true rate →
Cost week by week
£19,645 spent over 3 weeks, against a £19,206 estimate
LabourMaterialsSubcontract
Extras and variations · 1
Variations →
Timesheets · 216 h, £5,952 at cost
Timesheets →
Week ofPersonHoursCostStatus
12 Jan
Tap for the days
JPJosh Penrose24 h
3 days
£384.00
at £16/h
approved
from the paper sheets
12 Jan
Tap for the days
LDLiam Doyle32 h
4 days
£960.00
at £30/h
approved
from the paper sheets
12 Jan
Tap for the days
RFRob Finch16 h
2 days
£448.00
at £28/h
approved
from the paper sheets
12 Jan
Tap for the days
SRSteve Rowe32 h
4 days
£1,088.00
at £34/h
approved
from the paper sheets
5 Jan
Tap for the days
JPJosh Penrose32 h
4 days
£512.00
at £16/h
approved
from the paper sheets
5 Jan
Tap for the days
LDLiam Doyle40 h
5 days
£1,200.00
at £30/h
approved
from the paper sheets
5 Jan
Tap for the days
SRSteve Rowe40 h
5 days
£1,360.00
at £34/h
approved
from the paper sheets
Purchases · 6, £10,543
Purchases →
OrderWhatStatusNet
PO-5120
Brackwell Tiles, raised 3 Jan
Splashback tiles and adhesiveDelivered 8 Jan, billed£422.81
PO-5115
Avonmere Builders Merchants, raised 2 Jan
Plaster, board and sundriesDelivered 5 Jan, billed£427.54
PO-5116
Voltmere Electrical Wholesale, raised 2 Jan
Lighting and electrical fittingsDelivered 5 Jan, billed£425.28
PO-5109
Halbrook Worktops, raised 1 Jan
Worktops, templated and fittedDelivered 13 Jan, billed£2,927.45
PO-5110
Kestle Timber, raised 1 Jan
Timber, panels and fixingsDelivered 5 Jan, billed£312.76
PO-5101
Wrenfold Kitchen Supply, raised 11 Dec 2025
Kitchen units and doorsDelivered 2 Jan, billed£6,027.42
Subcontractor invoices · 5, £3,150
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3413
Gary Pullen Electrical, 15 Jan
Electrics, second fixPaid£710.00
SC-3414
Jon Haskins Plumbing and Heating, 15 Jan
Plumbing, second fixPaid£520.00
SC-3409
Mark Dent Plastering, 8 Jan
Plastering, skim and making goodPaid£690.00
SC-3404
Gary Pullen Electrical, 6 Jan
Electrics, first fixPaid£710.00
SC-3405
Jon Haskins Plumbing and Heating, 6 Jan
Plumbing, first fixPaid£520.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2202
issued 26 Nov 2025
Deposit
1 line
Paid 5 Dec 2025£6,462.50£7,755.00posted
INV-2217
issued 12 Jan
Progress
1 line
Paid 19 Jan£12,925.00£15,510.00posted
INV-2227
issued 22 Jan
Completion
2 lines, with V-3942-1
Paid 3 Feb£7,502.50£9,003.00posted
Stages £25,850 + billed extras £1,040 = £26,890 on invoices. £26,890 sent, £26,890 paid.
ST
Stuart Thornton
Stuart Thornton · client since 6 Nov 2025
Site39 Kingsley Road, Chew Magna
Phone07700 900632
PortalLive: progress, extras, invoices
See what Stuart sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewCrew A: Steve, Liam, Josh
Booked24 Nov 2025
StartedMon 5 Jan
Handed over21 Jan 2026
Timeline
Handed over and closed
Kate · 21 Jan 15:00
Gary Pullen Electrical: Electrics, second fix, £710.00
Gary Pullen · 15 Jan 17:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £520.00
Jon Haskins · 15 Jan 17:00
Mark Dent Plastering: Plastering, skim and making good, £690.00
Mark Dent · 8 Jan 17:00
Gary Pullen Electrical: Electrics, first fix, £710.00
Gary Pullen · 6 Jan 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £520.00
Jon Haskins · 6 Jan 17:00
First day on site: Josh, Liam, Steve
Site app · 5 Jan 07:30
Booked: £25,850 ex VAT
Owen · 24 Nov 2025 11:00