LIVE DEMO
Kitchen · domestic · fixed price

Job 3945

Complete
Kitchen-diner fit-out
For Lisa Kingscott, Downend. Crew A with Kate Lyons. On site 30 Jan to 11 Feb, handed over 19 Feb 2026.
Agreed price
£24,650
ex VAT
Final margin
22.7%
quoted 26.4%
100% of the work done16 cabinets
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Quoted margin26.4%£6,518 on £24,650
Final margin22.7%£5,591 profit
Invoiced so far£24,650of £24,650, £24,650 paid
Where the money went
PersonHoursLabour costDifference
SR
Steve Rowe
Lead fitter, crew A, £34/h at cost
72 h
of 64.5 h estimated
£2,448
of £2,193
+£255
LD
Liam Doyle
Joiner, crew A, £30/h at cost
72 h
of 64.5 h estimated
£2,160
of £1,935
+£225
JP
Josh Penrose
Apprentice joiner, crew A, £16/h at cost
56 h
of 40.5 h estimated
£896
of £648
+£248
RF
Rob Finch
Decorator, £28/h at cost
16 h
of 14.5 h estimated
£448
of £406
+£42
True labour cost. The 15 kitchens finished this year really took 12.95 h per cabinet, against the old rule of 11.5. This job: 16 cabinets, priced on 184 h. Rule of thumb: 11.5 h per cabinet. New quotes now use the true rate →
Cost week by week
£19,059 spent over 3 weeks, against a £18,132 estimate
LabourMaterialsSubcontract
Extras and variations · 0
Variations →
No extras on this job.
Timesheets · 216 h, £5,952 at cost
Timesheets →
Week ofPersonHoursCostStatus
9 Feb
Tap for the days
JPJosh Penrose16 h
2 days
£256.00
at £16/h
approved
from the paper sheets
9 Feb
Tap for the days
LDLiam Doyle24 h
3 days
£720.00
at £30/h
approved
from the paper sheets
9 Feb
Tap for the days
RFRob Finch16 h
2 days
£448.00
at £28/h
approved
from the paper sheets
9 Feb
Tap for the days
SRSteve Rowe24 h
3 days
£816.00
at £34/h
approved
from the paper sheets
2 Feb
Tap for the days
JPJosh Penrose32 h
4 days
£512.00
at £16/h
approved
from the paper sheets
2 Feb
Tap for the days
LDLiam Doyle40 h
5 days
£1,200.00
at £30/h
approved
from the paper sheets
2 Feb
Tap for the days
SRSteve Rowe40 h
5 days
£1,360.00
at £34/h
approved
from the paper sheets
26 Jan
Tap for the days
JPJosh Penrose8 h
1 day
£128.00
at £16/h
approved
from the paper sheets
26 Jan
Tap for the days
LDLiam Doyle8 h
1 day
£240.00
at £30/h
approved
from the paper sheets
26 Jan
Tap for the days
SRSteve Rowe8 h
1 day
£272.00
at £34/h
approved
from the paper sheets
Purchases · 6, £10,057
Purchases →
OrderWhatStatusNet
PO-5159
Brackwell Tiles, raised 30 Jan
Splashback tiles and adhesiveDelivered 4 Feb, billed£392.66
PO-5158
Halbrook Worktops, raised 28 Jan
Worktops, templated and fittedDelivered 9 Feb, billed£2,725.96
PO-5155
Avonmere Builders Merchants, raised 27 Jan
Plaster, board and sundriesDelivered 30 Jan, billed£400.85
PO-5156
Voltmere Electrical Wholesale, raised 27 Jan
Lighting and electrical fittingsDelivered 30 Jan, billed£404.88
PO-5151
Kestle Timber, raised 26 Jan
Timber, panels and fixingsDelivered 30 Jan, billed£300.43
PO-5123
Wrenfold Kitchen Supply, raised 7 Jan
Kitchen units and doorsDelivered 29 Jan, billed£5,831.90
Subcontractor invoices · 5, £3,050
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3457
Gary Pullen Electrical, 11 Feb
Electrics, second fixPaid£685.00
SC-3458
Jon Haskins Plumbing and Heating, 11 Feb
Plumbing, second fixPaid£505.00
SC-3450
Mark Dent Plastering, 4 Feb
Plastering, skim and making goodPaid£670.00
SC-3442
Gary Pullen Electrical, 2 Feb
Electrics, first fixPaid£685.00
SC-3443
Jon Haskins Plumbing and Heating, 2 Feb
Plumbing, first fixPaid£505.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2205
issued 15 Dec 2025
Deposit
1 line
Paid 25 Dec 2025£6,162.50£7,395.00posted
INV-2241
issued 5 Feb
Progress
1 line
Paid 18 Feb£12,325.00£14,790.00posted
INV-2254
issued 20 Feb
Completion
1 line
Paid 4 Mar£6,162.50£7,395.00posted
Stages £24,650 + billed extras £0 = £24,650 on invoices. £24,650 sent, £24,650 paid.
LK
Lisa Kingscott
Lisa Kingscott · client since 1 Dec 2025
Site21 Hollybush Lane, Downend
Phone07700 900123
PortalLive: progress, extras, invoices
See what Lisa sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewCrew A: Steve, Liam, Josh
Booked11 Dec 2025
StartedFri 30 Jan
Handed over19 Feb 2026
Timeline
Handed over and closed
Kate · 19 Feb 15:00
Gary Pullen Electrical: Electrics, second fix, £685.00
Gary Pullen · 11 Feb 17:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £505.00
Jon Haskins · 11 Feb 17:00
Mark Dent Plastering: Plastering, skim and making good, £670.00
Mark Dent · 4 Feb 17:00
Gary Pullen Electrical: Electrics, first fix, £685.00
Gary Pullen · 2 Feb 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £505.00
Jon Haskins · 2 Feb 17:00
First day on site: Josh, Liam, Steve
Site app · 30 Jan 07:30
Booked: £24,650 ex VAT
Owen · 11 Dec 2025 11:00