LIVE DEMO
Bathroom · domestic · fixed price

Job 3948

Complete
Bathroom with walk-in shower
For Richard Harding, Bedminster. Crew B with Kate Lyons. On site 15 Jan to 19 Jan, handed over 25 Jan 2026.
Agreed price
£9,800
ex VAT
Final margin
22.0%
quoted 23.5%
100% of the work done16 m² tiled
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Quoted margin23.5%£2,305 on £9,800
Final margin22.0%£2,155 profit
Invoiced so far£9,800of £9,800, £9,800 paid
Where the money went
PersonHoursLabour costDifference
MT
Mike Tanner
Lead fitter and tiler, crew B, £34/h at cost
24 h
of 27 h estimated
£816
of £918
-£102
RH
Ryan Hale
Fitter, crew B, £30/h at cost
24 h
of 23.5 h estimated
£720
of £705
+£15
CW
Callum Webb
Apprentice fitter, crew B, £16/h at cost
24 h
of 17 h estimated
£384
of £272
+£112
True labour cost. The 25 bathrooms finished this year really took 4.5 h per m² tiled, against the old rule of 4.2. This job: 16 m² tiled, priced on 67.5 h. Rule of thumb: 4.2 h per m² tiled. New quotes now use the true rate →
Cost week by week
£7,645 spent over 2 weeks, against a £7,495 estimate
LabourMaterialsSubcontract
Extras and variations · 0
Variations →
No extras on this job.
Timesheets · 72 h, £1,920 at cost
Timesheets →
Week ofPersonHoursCostStatus
19 Jan
Tap for the days
CWCallum Webb8 h
1 day
£128.00
at £16/h
approved
from the paper sheets
19 Jan
Tap for the days
MTMike Tanner8 h
1 day
£272.00
at £34/h
approved
from the paper sheets
19 Jan
Tap for the days
RHRyan Hale8 h
1 day
£240.00
at £30/h
approved
from the paper sheets
12 Jan
Tap for the days
CWCallum Webb16 h
2 days
£256.00
at £16/h
approved
from the paper sheets
12 Jan
Tap for the days
MTMike Tanner16 h
2 days
£544.00
at £34/h
approved
from the paper sheets
12 Jan
Tap for the days
RHRyan Hale16 h
2 days
£480.00
at £30/h
approved
from the paper sheets
Purchases · 5, £3,725
Purchases →
OrderWhatStatusNet
PO-5127
Voltmere Electrical Wholesale, raised 12 Jan
Lighting and extractorDelivered 15 Jan, billed£183.58
PO-5129
Avonmere Builders Merchants, raised 12 Jan
Board, tanking and sundriesDelivered 15 Jan, billed£483.58
PO-5124
Kestle Timber, raised 11 Jan
Timber and fixingsDelivered 15 Jan, billed£262.38
PO-5125
Brackwell Tiles, raised 11 Jan
Wall and floor tiles, adhesive, groutDelivered 16 Jan, billed£1,003.41
PO-5121
Linmouth Bathroom Supply, raised 5 Jan
Sanitaryware and brasswareDelivered 14 Jan, billed£1,792.12
Subcontractor invoices · 5, £2,000
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3420
Jon Haskins Plumbing and Heating, 19 Jan
Plumbing, second fixPaid£620.00
SC-3421
Gary Pullen Electrical, 19 Jan
Electrics, second fixPaid£180.00
SC-3417
Mark Dent Plastering, 16 Jan
Plastering, skim and making goodPaid£400.00
SC-3415
Jon Haskins Plumbing and Heating, 15 Jan
Plumbing, first fixPaid£620.00
SC-3416
Gary Pullen Electrical, 15 Jan
Electrics, first fixPaid£180.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2208
issued 18 Dec 2025
Deposit
1 line
Paid 25 Dec 2025£2,450.00£2,940.00posted
INV-2222
issued 19 Jan
Progress
1 line
Paid 25 Jan£4,900.00£5,880.00posted
INV-2230
issued 26 Jan
Completion
1 line
Paid 7 Feb£2,450.00£2,940.00posted
Stages £9,800 + billed extras £0 = £9,800 on invoices. £9,800 sent, £9,800 paid.
RH
Richard Harding
Richard Harding · client since 16 Nov 2025
Site5 The Crescent, Bedminster
Phone07700 900622
PortalLive: progress, extras, invoices
See what Richard sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewCrew B: Mike, Ryan, Callum
Booked16 Dec 2025
StartedThu 15 Jan
Handed over25 Jan 2026
Timeline
Handed over and closed
Kate · 25 Jan 15:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £620.00
Jon Haskins · 19 Jan 17:00
Gary Pullen Electrical: Electrics, second fix, £180.00
Gary Pullen · 19 Jan 17:00
Mark Dent Plastering: Plastering, skim and making good, £400.00
Mark Dent · 16 Jan 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £620.00
Jon Haskins · 15 Jan 17:00
Gary Pullen Electrical: Electrics, first fix, £180.00
Gary Pullen · 15 Jan 17:00
First day on site: Callum, Mike, Ryan
Site app · 15 Jan 07:30
Booked: £9,800 ex VAT
Owen · 16 Dec 2025 11:00