Bathroom · domestic · fixed price

Job 3955

Complete
Bathroom refit
For Lisa Nash, Totterdown. Crew B with Kate Lyons. On site 17 Feb to 19 Feb, handed over 24 Feb 2026.
Agreed price
£9,400
ex VAT
Final margin
23.7%
quoted 26.1%
100% of the work done14 m² tiled
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Quoted margin26.1%£2,454 on £9,400
Final margin23.7%£2,224 profit
Invoiced so far£9,400of £9,400, £9,400 paid
Where the money went
PersonHoursLabour costDifference
MT
Mike Tanner
Lead fitter and tiler, crew B, £34/h at cost
24 h
of 23.5 h estimated
£816
of £799
+£17
RH
Ryan Hale
Fitter, crew B, £30/h at cost
24 h
of 20.5 h estimated
£720
of £615
+£105
CW
Callum Webb
Apprentice fitter, crew B, £16/h at cost
16 h
of 14.5 h estimated
£256
of £232
+£24
True labour cost. The 25 bathrooms finished this year really took 4.5 h per m² tiled, against the old rule of 4.2. This job: 14 m² tiled, priced on 58.5 h. Rule of thumb: 4.2 h per m² tiled. New quotes now use the true rate →
Cost week by week
£7,176 spent over 1 week, against a £6,946 estimate
LabourMaterialsSubcontract
Extras and variations · 0
Variations →
No extras on this job.
Timesheets · 64 h, £1,792 at cost
Timesheets →
Week ofPersonHoursCostStatus
16 Feb
Tap for the days
CWCallum Webb16 h
2 days
£256.00
at £16/h
approved
from the paper sheets
16 Feb
Tap for the days
MTMike Tanner24 h
3 days
£816.00
at £34/h
approved
from the paper sheets
16 Feb
Tap for the days
RHRyan Hale24 h
3 days
£720.00
at £30/h
approved
from the paper sheets
Purchases · 5, £3,484
Purchases →
OrderWhatStatusNet
PO-5179
Voltmere Electrical Wholesale, raised 14 Feb
Lighting and extractorDelivered 17 Feb, billed£169.38
PO-5180
Avonmere Builders Merchants, raised 14 Feb
Board, tanking and sundriesDelivered 17 Feb, billed£455.15
PO-5176
Brackwell Tiles, raised 13 Feb
Wall and floor tiles, adhesive, groutDelivered 18 Feb, billed£943.20
PO-5177
Kestle Timber, raised 13 Feb
Timber and fixingsDelivered 17 Feb, billed£243.67
PO-5167
Linmouth Bathroom Supply, raised 7 Feb
Sanitaryware and brasswareDelivered 16 Feb, billed£1,672.18
Subcontractor invoices · 5, £1,900
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3469
Jon Haskins Plumbing and Heating, 19 Feb
Plumbing, second fixPaid£590.00
SC-3470
Gary Pullen Electrical, 19 Feb
Electrics, second fixPaid£170.00
SC-3465
Mark Dent Plastering, 18 Feb
Plastering, skim and making goodPaid£380.00
SC-3463
Jon Haskins Plumbing and Heating, 17 Feb
Plumbing, first fixPaid£590.00
SC-3464
Gary Pullen Electrical, 17 Feb
Electrics, first fixPaid£170.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2221
issued 16 Jan
Deposit
1 line
Paid 1 Feb£2,350.00£2,820.00posted
INV-2252
issued 18 Feb
Progress
1 line
Paid 5 Mar£4,700.00£5,640.00posted
INV-2259
issued 25 Feb
Completion
1 line
Paid 6 Mar£2,350.00£2,820.00posted
Stages £9,400 + billed extras £0 = £9,400 on invoices. £9,400 sent, £9,400 paid.
LN
Lisa Nash
Lisa Nash · client since 19 Dec 2025
Site80 Kingsley Road, Totterdown
Phone07700 900942
PortalLive: progress, extras, invoices
See what Lisa sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewCrew B: Mike, Ryan, Callum
Booked14 Jan 2026
StartedTue 17 Feb
Handed over24 Feb 2026
Timeline
Handed over and closed
Kate · 24 Feb 15:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £590.00
Jon Haskins · 19 Feb 17:00
Gary Pullen Electrical: Electrics, second fix, £170.00
Gary Pullen · 19 Feb 17:00
Mark Dent Plastering: Plastering, skim and making good, £380.00
Mark Dent · 18 Feb 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £590.00
Jon Haskins · 17 Feb 17:00
Gary Pullen Electrical: Electrics, first fix, £170.00
Gary Pullen · 17 Feb 17:00
First day on site: Callum, Mike, Ryan
Site app · 17 Feb 07:30
Booked: £9,400 ex VAT
Owen · 14 Jan 11:00