Office · commercial · fixed price

Job 3956

Complete
Office refurbishment
For Harlow Vance Consulting, Bristol. Crew C with Gareth Price. On site 27 Feb to 11 Mar, handed over 21 Mar 2026.
Agreed price
£47,350
ex VAT
Final margin
19.4%
quoted 22.2%
100% of the work done194 m² floor
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Quoted margin22.2%£10,497 on £47,350
Final margin19.4%£9,198 profit
Invoiced so far£47,350of £47,350, £44,982 paid, £2,368 retention held
Where the money went
PersonHoursLabour costDifference
DK
Dave Kerr
Lead fitter, crew C, £35/h at cost
56 h
of 52.5 h estimated
£1,960
of £1,838
+£123
TA
Tom Ashby
Joiner, crew C, £30/h at cost
56 h
of 52.5 h estimated
£1,680
of £1,575
+£105
ER
Ellie Rudd
Apprentice joiner, crew C, £16/h at cost
48 h
of 38.5 h estimated
£768
of £616
+£152
RF
Rob Finch
Decorator, £28/h at cost
16 h
of 15.5 h estimated
£448
of £434
+£14
SK
Sam Kerridge
Labourer and driver, £22/h at cost
16 h
of 15.5 h estimated
£352
of £341
+£11
True labour cost. The 7 offices finished this year really took 0.95 h per m² of floor, against the old rule of 0.9. This job: 194 m² floor, priced on 174.5 h. Rule of thumb: 0.9 h per m² of floor. New quotes now use the true rate →
Cost week by week
£38,152 spent over 3 weeks, against a £36,854 estimate
LabourMaterialsSubcontract
Extras and variations · 0
Variations →
No extras on this job.
Timesheets · 192 h, £5,208 at cost
Timesheets →
Week ofPersonHoursCostStatus
9 Mar
Tap for the days
DKDave Kerr8 h
1 day
£280.00
at £35/h
approved
from the paper sheets
9 Mar
Tap for the days
EREllie Rudd8 h
1 day
£128.00
at £16/h
approved
from the paper sheets
9 Mar
Tap for the days
RFRob Finch16 h
2 days
£448.00
at £28/h
approved
from the paper sheets
9 Mar
Tap for the days
TATom Ashby8 h
1 day
£240.00
at £30/h
approved
from the paper sheets
2 Mar
Tap for the days
DKDave Kerr40 h
5 days
£1,400.00
at £35/h
approved
from the paper sheets
2 Mar
Tap for the days
EREllie Rudd32 h
4 days
£512.00
at £16/h
approved
from the paper sheets
2 Mar
Tap for the days
SKSam Kerridge8 h
1 day
£176.00
at £22/h
approved
from the paper sheets
2 Mar
Tap for the days
TATom Ashby40 h
5 days
£1,200.00
at £30/h
approved
from the paper sheets
23 Feb
Tap for the days
DKDave Kerr8 h
1 day
£280.00
at £35/h
approved
from the paper sheets
23 Feb
Tap for the days
EREllie Rudd8 h
1 day
£128.00
at £16/h
approved
from the paper sheets
23 Feb
Tap for the days
SKSam Kerridge8 h
1 day
£176.00
at £22/h
approved
from the paper sheets
23 Feb
Tap for the days
TATom Ashby8 h
1 day
£240.00
at £30/h
approved
from the paper sheets
Purchases · 4, £19,344
Purchases →
OrderWhatStatusNet
PO-5206
Cotsmoor Flooring Trade, raised 3 Mar
FlooringDelivered 10 Mar, billed£4,576.81
PO-5196
Voltmere Electrical Wholesale, raised 24 Feb
Lighting and electricalDelivered 27 Feb, billed£4,323.62
PO-5194
Kestle Timber, raised 23 Feb
Joinery timber and sheetDelivered 27 Feb, billed£3,555.56
PO-5195
Avonmere Builders Merchants, raised 23 Feb
Partitions, board and ceilingsDelivered 26 Feb, billed£6,888.01
Subcontractor invoices · 4, £13,600
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3497
Andy Rees Electrical, 11 Mar
Electrics and data, second fixPaid£4,080.00
SC-3494
Nick Weller Flooring, 10 Mar
Floor laying, supply-laid by the floor layerPaid£2,040.00
SC-3486
Mark Dent Plastering, 4 Mar
Plastering, skim and making goodPaid£3,400.00
SC-3482
Andy Rees Electrical, 2 Mar
Electrics and data, first fixPaid£4,080.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2224
issued 19 Jan
Deposit
1 line
Paid 14 Feb£11,837.50£13,494.74
£592 retention held
posted
INV-2265
issued 5 Mar
Progress
1 line
Paid 7 Apr£23,675.00£26,989.50
£1,184 retention held
posted
INV-2281
issued 23 Mar
Completion
1 line
Paid 19 Apr£11,837.50£13,494.74
£592 retention held
posted
Stages £47,350 + billed extras £0 = £47,350 on invoices. £47,350 sent, £44,982 paid, £2,368 retention held until the defects period ends.
HV
Harlow Vance Consulting
Contact: Dominic Durbin · client since 29 Dec 2025
Site62 High Street, Bristol
Phone0117 496 0631
PortalLive: progress, extras, invoices
See what Dominic sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerGareth Price
CrewCrew C: Dave, Tom, Ellie
Booked15 Jan 2026
StartedFri 27 Feb
Handed over21 Mar 2026
Retention5% held to the end of defects
Timeline
Handed over and closed
Gareth · 21 Mar 15:00
Andy Rees Electrical: Electrics and data, second fix, £4,080.00
Andy Rees · 11 Mar 17:00
Nick Weller Flooring: Floor laying, supply-laid by the floor layer, £2,040.00
Nick Weller · 10 Mar 17:00
Mark Dent Plastering: Plastering, skim and making good, £3,400.00
Mark Dent · 4 Mar 17:00
Andy Rees Electrical: Electrics and data, first fix, £4,080.00
Andy Rees · 2 Mar 17:00
First day on site: Dave, Ellie, Sam, Tom
Site app · 27 Feb 07:30
Booked: £47,350 ex VAT
Owen · 15 Jan 11:00