LIVE DEMO
Bathroom · domestic · fixed price

Job 3958

Complete
Cloakroom and utility refit
For Hannah Filer, Bath. Chris Moss (small works) with Kate Lyons. On site 3 Feb to 9 Feb, handed over 17 Feb 2026.
Agreed price
£10,250
ex VAT
Final margin
30.9%
quoted 30.1%
100% of the work done8 m²
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Quoted margin30.1%£3,086 on £10,250
Final margin30.9%£3,169 profit
Invoiced so far£10,250of £10,250, £10,250 paid
Where the money went
PersonHoursLabour costDifference
CM
Chris Moss
Small works and snagging fitter, £30/h at cost
40 h
of 38.5 h estimated
£1,200
of £1,155
+£45
SK
Sam Kerridge
Labourer and driver, £22/h at cost
8 h
of 9.5 h estimated
£176
of £209
-£33
Rule of thumb: 6 h per m².
Cost week by week
£7,081 spent over 2 weeks, against a £7,164 estimate
LabourMaterialsSubcontract
Extras and variations · 0
Variations →
No extras on this job.
Timesheets · 48 h, £1,376 at cost
Timesheets →
Week ofPersonHoursCostStatus
9 Feb
Tap for the days
CMChris Moss8 h
1 day
£240.00
at £30/h
approved
from the paper sheets
2 Feb
Tap for the days
CMChris Moss32 h
4 days
£960.00
at £30/h
approved
from the paper sheets
2 Feb
Tap for the days
SKSam Kerridge8 h
1 day
£176.00
at £22/h
approved
from the paper sheets
Purchases · 4, £4,305
Purchases →
OrderWhatStatusNet
PO-5160
Avonmere Builders Merchants, raised 31 Jan
Board and sundriesDelivered 3 Feb, billed£422.54
PO-5161
Brackwell Tiles, raised 31 Jan
Tiles and adhesiveDelivered 5 Feb, billed£649.95
PO-5147
Linmouth Bathroom Supply, raised 24 Jan
Sanitaryware and brasswareDelivered 2 Feb, billed£2,118.61
PO-5141
Wrenfold Kitchen Supply, raised 19 Jan
Utility unitsDelivered 3 Feb, billed£1,113.86
Subcontractor invoices · 4, £1,400
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3454
Jon Haskins Plumbing and Heating, 9 Feb
Plumbing, second fixPaid£525.00
SC-3455
Gary Pullen Electrical, 9 Feb
Electrics, second fixPaid£175.00
SC-3451
Jon Haskins Plumbing and Heating, 4 Feb
Plumbing, first fixPaid£525.00
SC-3449
Gary Pullen Electrical, 3 Feb
Electrics, first fixPaid£175.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2226
issued 20 Jan
Deposit
1 line
Paid 31 Jan£2,562.50£3,075.00posted
INV-2243
issued 6 Feb
Progress
1 line
Paid 13 Feb£5,125.00£6,150.00posted
INV-2253
issued 18 Feb
Completion
1 line
Paid 27 Feb£2,562.50£3,075.00posted
Stages £10,250 + billed extras £0 = £10,250 on invoices. £10,250 sent, £10,250 paid.
HF
Hannah Filer
Hannah Filer · client since 5 Dec 2025
Site98 Station Road, Bath
Phone07700 900331
PortalLive: progress, extras, invoices
See what Hannah sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewChris Moss, small works
Booked18 Jan 2026
StartedTue 3 Feb
Handed over17 Feb 2026
Timeline
Handed over and closed
Kate · 17 Feb 15:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £525.00
Jon Haskins · 9 Feb 17:00
Gary Pullen Electrical: Electrics, second fix, £175.00
Gary Pullen · 9 Feb 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £525.00
Jon Haskins · 4 Feb 17:00
Gary Pullen Electrical: Electrics, first fix, £175.00
Gary Pullen · 3 Feb 17:00
First day on site: Chris, Sam
Site app · 3 Feb 07:30
Booked: £10,250 ex VAT
Owen · 18 Jan 11:00