Bathroom · domestic · fixed price

Job 3961

Complete
Family bathroom
For Paul Lovell, Frenchay. Crew B with Kate Lyons. On site 6 Mar to 13 Mar, handed over 16 Mar 2026.
Agreed price
£12,900
ex VAT, +£1,100 extras billed
Final margin
23.8%
quoted 24.3%
100% of the work done26 m² tiled
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Extras captured on site
2 extras on this job
Every extra ↓
Quoted margin24.3%£3,141 on £12,900
Final margin23.8%£3,337 profit
Invoiced so far£14,000of £14,000, £14,000 paid
Where the money went
PersonHoursLabour costDifference
MT
Mike Tanner
Lead fitter and tiler, crew B, £34/h at cost
48 h
of 43.5 h estimated
£1,632
of £1,479
+£153
RH
Ryan Hale
Fitter, crew B, £30/h at cost
48 h
of 38 h estimated
£1,440
of £1,140
+£300
CW
Callum Webb
Apprentice fitter, crew B, £16/h at cost
40 h
of 27.5 h estimated
£640
of £440
+£200
True labour cost. The 25 bathrooms finished this year really took 4.5 h per m² tiled, against the old rule of 4.2. This job: 26 m² tiled, priced on 109 h. Rule of thumb: 4.2 h per m² tiled. New quotes now use the true rate →
Cost week by week
£10,663 spent over 2 weeks, against a £9,759 estimate
LabourMaterialsSubcontract
Extras and variations · 2
Variations →
Timesheets · 136 h, £3,712 at cost
Timesheets →
Week ofPersonHoursCostStatus
9 Mar
Tap for the days
CWCallum Webb32 h
4 days
£512.00
at £16/h
approved
from the paper sheets
9 Mar
Tap for the days
MTMike Tanner40 h
5 days
£1,360.00
at £34/h
approved
from the paper sheets
9 Mar
Tap for the days
RHRyan Hale40 h
5 days
£1,200.00
at £30/h
approved
from the paper sheets
2 Mar
Tap for the days
CWCallum Webb8 h
1 day
£128.00
at £16/h
approved
from the paper sheets
2 Mar
Tap for the days
MTMike Tanner8 h
1 day
£272.00
at £34/h
approved
from the paper sheets
2 Mar
Tap for the days
RHRyan Hale8 h
1 day
£240.00
at £30/h
approved
from the paper sheets
Purchases · 5, £4,651
Purchases →
OrderWhatStatusNet
PO-5209
Brackwell Tiles, raised 5 Mar
Wall and floor tiles, adhesive, groutDelivered 10 Mar, billed£1,253.41
PO-5207
Voltmere Electrical Wholesale, raised 3 Mar
Lighting and extractorDelivered 6 Mar, billed£224.81
PO-5208
Avonmere Builders Merchants, raised 3 Mar
Board, tanking and sundriesDelivered 6 Mar, billed£603.01
PO-5205
Kestle Timber, raised 2 Mar
Timber and fixingsDelivered 6 Mar, billed£325.70
PO-5197
Linmouth Bathroom Supply, raised 24 Feb
Sanitaryware and brasswareDelivered 5 Mar, billed£2,243.82
Subcontractor invoices · 5, £2,300
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3500
Jon Haskins Plumbing and Heating, 13 Mar
Plumbing, second fixPaid£715.00
SC-3501
Gary Pullen Electrical, 13 Mar
Electrics, second fixPaid£205.00
SC-3495
Mark Dent Plastering, 10 Mar
Plastering, skim and making goodPaid£460.00
SC-3493
Jon Haskins Plumbing and Heating, 9 Mar
Plumbing, first fixPaid£715.00
SC-3490
Gary Pullen Electrical, 6 Mar
Electrics, first fixPaid£205.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2233
issued 29 Jan
Deposit
1 line
Paid 7 Feb£3,225.00£3,870.00posted
INV-2268
issued 9 Mar
Progress
1 line
Paid 22 Mar£6,450.00£7,740.00posted
INV-2277
issued 17 Mar
Completion
3 lines, with V-3961-1, V-3961-2
Paid 29 Mar£4,325.00£5,190.00posted
Stages £12,900 + billed extras £1,100 = £14,000 on invoices. £14,000 sent, £14,000 paid.
PL
Paul Lovell
Paul Lovell · client since 5 Jan 2026
Site57 Elm Park, Frenchay
Phone07700 900429
PortalLive: progress, extras, invoices
See what Paul sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewCrew B: Mike, Ryan, Callum
Booked27 Jan 2026
StartedFri 6 Mar
Handed over16 Mar 2026
Timeline
Handed over and closed
Kate · 16 Mar 15:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £715.00
Jon Haskins · 13 Mar 17:00
Gary Pullen Electrical: Electrics, second fix, £205.00
Gary Pullen · 13 Mar 17:00
Mark Dent Plastering: Plastering, skim and making good, £460.00
Mark Dent · 10 Mar 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £715.00
Jon Haskins · 9 Mar 17:00
Gary Pullen Electrical: Electrics, first fix, £205.00
Gary Pullen · 6 Mar 17:00
First day on site: Callum, Mike, Ryan
Site app · 6 Mar 07:30
Booked: £12,900 ex VAT
Owen · 27 Jan 11:00