Office · commercial · fixed price

Job 3962

Complete
Office refurbishment
For Kestrel Point Software, Bristol. Crew C with Gareth Price. On site 13 Mar to 26 Mar, handed over 31 Mar 2026.
Agreed price
£47,700
ex VAT
Final margin
19.7%
quoted 20.8%
100% of the work done199 m² floor
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Quoted margin20.8%£9,941 on £47,700
Final margin19.7%£9,373 profit
Invoiced so far£47,700of £47,700, £45,315 paid, £2,385 retention held
Where the money went
PersonHoursLabour costDifference
DK
Dave Kerr
Lead fitter, crew C, £35/h at cost
56 h
of 53.5 h estimated
£1,960
of £1,873
+£88
TA
Tom Ashby
Joiner, crew C, £30/h at cost
56 h
of 53.5 h estimated
£1,680
of £1,605
+£75
ER
Ellie Rudd
Apprentice joiner, crew C, £16/h at cost
48 h
of 39.5 h estimated
£768
of £632
+£136
RF
Rob Finch
Decorator, £28/h at cost
16 h
of 16 h estimated
£448
of £448
on budget
SK
Sam Kerridge
Labourer and driver, £22/h at cost
16 h
of 16 h estimated
£352
of £352
on budget
True labour cost. The 7 offices finished this year really took 0.95 h per m² of floor, against the old rule of 0.9. This job: 199 m² floor, priced on 178.5 h. Rule of thumb: 0.9 h per m² of floor. New quotes now use the true rate →
Cost week by week
£38,327 spent over 3 weeks, against a £37,760 estimate
LabourMaterialsSubcontract
Extras and variations · 0
Variations →
No extras on this job.
Timesheets · 192 h, £5,208 at cost
Timesheets →
Week ofPersonHoursCostStatus
23 Mar
Tap for the days
DKDave Kerr8 h
1 day
£280.00
at £35/h
approved
from the paper sheets
23 Mar
Tap for the days
EREllie Rudd8 h
1 day
£128.00
at £16/h
approved
from the paper sheets
23 Mar
Tap for the days
RFRob Finch16 h
2 days
£448.00
at £28/h
approved
from the paper sheets
23 Mar
Tap for the days
TATom Ashby8 h
1 day
£240.00
at £30/h
approved
from the paper sheets
16 Mar
Tap for the days
DKDave Kerr40 h
5 days
£1,400.00
at £35/h
approved
from the paper sheets
16 Mar
Tap for the days
EREllie Rudd32 h
4 days
£512.00
at £16/h
approved
from the paper sheets
16 Mar
Tap for the days
SKSam Kerridge8 h
1 day
£176.00
at £22/h
approved
from the paper sheets
16 Mar
Tap for the days
TATom Ashby40 h
5 days
£1,200.00
at £30/h
approved
from the paper sheets
9 Mar
Tap for the days
DKDave Kerr8 h
1 day
£280.00
at £35/h
approved
from the paper sheets
9 Mar
Tap for the days
EREllie Rudd8 h
1 day
£128.00
at £16/h
approved
from the paper sheets
9 Mar
Tap for the days
SKSam Kerridge8 h
1 day
£176.00
at £22/h
approved
from the paper sheets
9 Mar
Tap for the days
TATom Ashby8 h
1 day
£240.00
at £30/h
approved
from the paper sheets
Purchases · 4, £19,169
Purchases →
OrderWhatStatusNet
PO-5225
Cotsmoor Flooring Trade, raised 18 Mar
FlooringDelivered 25 Mar, billed£4,561.33
PO-5219
Voltmere Electrical Wholesale, raised 13 Mar
Lighting and electricalDelivered 16 Mar, billed£4,154.42
PO-5218
Kestle Timber, raised 12 Mar
Joinery timber and sheetDelivered 16 Mar, billed£3,434.47
PO-5213
Avonmere Builders Merchants, raised 9 Mar
Partitions, board and ceilingsDelivered 12 Mar, billed£7,018.62
Subcontractor invoices · 4, £13,950
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3515
Andy Rees Electrical, 26 Mar
Electrics and data, second fixPaid£4,185.00
SC-3514
Nick Weller Flooring, 25 Mar
Floor laying, supply-laid by the floor layerPaid£2,090.00
SC-3506
Mark Dent Plastering, 19 Mar
Plastering, skim and making goodPaid£3,490.00
SC-3502
Andy Rees Electrical, 16 Mar
Electrics and data, first fixPaid£4,185.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2235
issued 30 Jan
Deposit
1 line
Paid 17 Feb£11,925.00£13,594.50
£596 retention held
posted
INV-2278
issued 19 Mar
Progress
1 line
Paid 6 Apr£23,850.00£27,189.00
£1,193 retention held
posted
INV-2287
issued 1 Apr
Completion
1 line
Paid 1 May£11,925.00£13,594.50
£596 retention held
posted
Stages £47,700 + billed extras £0 = £47,700 on invoices. £47,700 sent, £45,315 paid, £2,385 retention held until the defects period ends.
KP
Kestrel Point Software
Contact: Fiona Dyer · client since 12 Jan 2026
Site98 Regent Street, Bristol
Phone0117 496 0737
PortalLive: progress, extras, invoices
See what Fiona sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerGareth Price
CrewCrew C: Dave, Tom, Ellie
Booked28 Jan 2026
StartedFri 13 Mar
Handed over31 Mar 2026
Retention5% held to the end of defects
Timeline
Handed over and closed
Gareth · 31 Mar 15:00
Andy Rees Electrical: Electrics and data, second fix, £4,185.00
Andy Rees · 26 Mar 17:00
Nick Weller Flooring: Floor laying, supply-laid by the floor layer, £2,090.00
Nick Weller · 25 Mar 17:00
Mark Dent Plastering: Plastering, skim and making good, £3,490.00
Mark Dent · 19 Mar 17:00
Andy Rees Electrical: Electrics and data, first fix, £4,185.00
Andy Rees · 16 Mar 17:00
First day on site: Dave, Ellie, Sam, Tom
Site app · 13 Mar 07:30
Booked: £47,700 ex VAT
Owen · 28 Jan 11:00