Office · commercial · fixed price

Job 3967

Complete
Office fit-out
For Brightwater Insurance Brokers, Bristol. Crew C with Gareth Price. On site 1 Apr to 14 Apr, handed over 17 Apr 2026.
Agreed price
£50,850
ex VAT
Final margin
18.0%
quoted 19.4%
100% of the work done216 m² floor
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Quoted margin19.4%£9,885 on £50,850
Final margin18.0%£9,172 profit
Invoiced so far£50,850of £50,850, £48,307 paid, £2,543 retention held
Where the money went
PersonHoursLabour costDifference
DK
Dave Kerr
Lead fitter, crew C, £35/h at cost
64 h
of 58.5 h estimated
£2,240
of £2,048
+£193
TA
Tom Ashby
Joiner, crew C, £30/h at cost
64 h
of 58.5 h estimated
£1,920
of £1,755
+£165
ER
Ellie Rudd
Apprentice joiner, crew C, £16/h at cost
48 h
of 43 h estimated
£768
of £688
+£80
RF
Rob Finch
Decorator, £28/h at cost
16 h
of 17.5 h estimated
£448
of £490
-£42
SK
Sam Kerridge
Labourer and driver, £22/h at cost
16 h
of 17.5 h estimated
£352
of £385
-£33
True labour cost. The 7 offices finished this year really took 0.95 h per m² of floor, against the old rule of 0.9. This job: 216 m² floor, priced on 195 h. Rule of thumb: 0.9 h per m² of floor. New quotes now use the true rate →
Cost week by week
£41,678 spent over 3 weeks, against a £40,966 estimate
LabourMaterialsSubcontract
Extras and variations · 0
Variations →
No extras on this job.
Timesheets · 208 h, £5,728 at cost
Timesheets →
Week ofPersonHoursCostStatus
13 Apr
Tap for the days
DKDave Kerr16 h
2 days
£560.00
at £35/h
approved
from the paper sheets
13 Apr
Tap for the days
EREllie Rudd16 h
2 days
£256.00
at £16/h
approved
from the paper sheets
13 Apr
Tap for the days
RFRob Finch16 h
2 days
£448.00
at £28/h
approved
from the paper sheets
13 Apr
Tap for the days
TATom Ashby16 h
2 days
£480.00
at £30/h
approved
from the paper sheets
6 Apr
Tap for the days
DKDave Kerr32 h
4 days
£1,120.00
at £35/h
approved
from the paper sheets
6 Apr
Tap for the days
EREllie Rudd24 h
3 days
£384.00
at £16/h
approved
from the paper sheets
6 Apr
Tap for the days
TATom Ashby32 h
4 days
£960.00
at £30/h
approved
from the paper sheets
30 Mar
Tap for the days
DKDave Kerr16 h
2 days
£560.00
at £35/h
approved
from the paper sheets
30 Mar
Tap for the days
EREllie Rudd8 h
1 day
£128.00
at £16/h
approved
from the paper sheets
30 Mar
Tap for the days
SKSam Kerridge16 h
2 days
£352.00
at £22/h
approved
from the paper sheets
30 Mar
Tap for the days
TATom Ashby16 h
2 days
£480.00
at £30/h
approved
from the paper sheets
Purchases · 4, £20,850
Purchases →
OrderWhatStatusNet
PO-5248
Cotsmoor Flooring Trade, raised 6 Apr
FlooringDelivered 13 Apr, billed£5,023.65
PO-5241
Voltmere Electrical Wholesale, raised 29 Mar
Lighting and electricalDelivered 1 Apr, billed£4,670.13
PO-5239
Kestle Timber, raised 28 Mar
Joinery timber and sheetDelivered 1 Apr, billed£3,678.83
PO-5240
Avonmere Builders Merchants, raised 28 Mar
Partitions, board and ceilingsDelivered 31 Mar, billed£7,477.35
Subcontractor invoices · 4, £15,100
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3536
Andy Rees Electrical, 14 Apr
Electrics and data, second fixPaid£4,530.00
SC-3533
Nick Weller Flooring, 13 Apr
Floor laying, supply-laid by the floor layerPaid£2,260.00
SC-3529
Mark Dent Plastering, 8 Apr
Plastering, skim and making goodPaid£3,780.00
SC-3524
Andy Rees Electrical, 2 Apr
Electrics and data, first fixPaid£4,530.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2257
issued 23 Feb
Deposit
1 line
Paid 26 Mar£12,712.50£14,492.24
£636 retention held
posted
INV-2292
issued 7 Apr
Progress
1 line
Paid 10 May£25,425.00£28,984.50
£1,271 retention held
posted
INV-2304
issued 20 Apr
Completion
1 line
Paid 21 May£12,712.50£14,492.24
£636 retention held
posted
Stages £50,850 + billed extras £0 = £50,850 on invoices. £50,850 sent, £48,307 paid, £2,543 retention held until the defects period ends.
BI
Brightwater Insurance Brokers
Contact: Laura Lovell · client since 31 Jan 2026
Site105 Park Street, Bristol
Phone0117 496 0692
PortalLive: progress, extras, invoices
See what Laura sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerGareth Price
CrewCrew C: Dave, Tom, Ellie
Booked20 Feb 2026
StartedWed 1 Apr
Handed over17 Apr 2026
Retention5% held to the end of defects
Timeline
Handed over and closed
Gareth · 17 Apr 15:00
Andy Rees Electrical: Electrics and data, second fix, £4,530.00
Andy Rees · 14 Apr 17:00
Nick Weller Flooring: Floor laying, supply-laid by the floor layer, £2,260.00
Nick Weller · 13 Apr 17:00
Mark Dent Plastering: Plastering, skim and making good, £3,780.00
Mark Dent · 8 Apr 17:00
Andy Rees Electrical: Electrics and data, first fix, £4,530.00
Andy Rees · 2 Apr 17:00
First day on site: Dave, Sam, Tom
Site app · 1 Apr 07:30
Booked: £50,850 ex VAT
Owen · 20 Feb 11:00