For Claire and Toby Davies, Knowle. Crew A with Kate Lyons. On site 13 Apr to 22 Apr, handed over 26 Apr 2026.
Agreed price
£23,400
ex VAT
Final margin
25.5%
quoted 26.6%
100% of the work done15 cabinets
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Quoted margin26.6%£6,228 on £23,400
Final margin25.5%£5,975 profit
Invoiced so far£23,400of £23,400, £23,400 paid
Where the money went
PersonHoursLabour costDifference
SR
Steve Rowe
Lead fitter, crew A, £34/h at cost
64 h
of 60.5 h estimated
£2,176
of £2,057
+£119
LD
Liam Doyle
Joiner, crew A, £30/h at cost
64 h
of 60.5 h estimated
£1,920
of £1,815
+£105
JP
Josh Penrose
Apprentice joiner, crew A, £16/h at cost
48 h
of 38 h estimated
£768
of £608
+£160
RF
Rob Finch
Decorator, £28/h at cost
16 h
of 14 h estimated
£448
of £392
+£56
True labour cost. The 15 kitchens finished this year really took 12.95 h per cabinet, against the old rule of 11.5. This job: 15 cabinets, priced on 173 h. Rule of thumb: 11.5 h per cabinet. New quotes now use the true rate →
Cost week by week
£17,425 spent over 3 weeks, against a £17,172 estimate
LabourMaterialsSubcontract
Extras and variations · 0
Variations →
No extras on this job.
Timesheets · 192 h, £5,312 at cost
Timesheets →
Week ofPersonHoursCostStatus
20 Apr
Tap for the days
JPJosh Penrose16 h
2 days
£256.00
at £16/h
approved
from the paper sheets
20 Apr
Tap for the days
LDLiam Doyle24 h
3 days
£720.00
at £30/h
approved
from the paper sheets
20 Apr
Tap for the days
RFRob Finch16 h
2 days
£448.00
at £28/h
approved
from the paper sheets
20 Apr
Tap for the days
SRSteve Rowe24 h
3 days
£816.00
at £34/h
approved
from the paper sheets
13 Apr
Tap for the days
JPJosh Penrose32 h
4 days
£512.00
at £16/h
approved
from the paper sheets
13 Apr
Tap for the days
LDLiam Doyle40 h
5 days
£1,200.00
at £30/h
approved
from the paper sheets
13 Apr
Tap for the days
SRSteve Rowe40 h
5 days
£1,360.00
at £34/h
approved
from the paper sheets
Purchases · 6, £9,113
Purchases →
OrderWhatStatusNet
PO-5257
Brackwell Tiles, raised 11 Apr
Splashback tiles and adhesiveDelivered 16 Apr, billed£371.78
PO-5254
Avonmere Builders Merchants, raised 10 Apr
Plaster, board and sundriesDelivered 13 Apr, billed£370.74
PO-5255
Voltmere Electrical Wholesale, raised 10 Apr
Lighting and electrical fittingsDelivered 13 Apr, billed£367.61
PO-5253
Kestle Timber, raised 9 Apr
Timber, panels and fixingsDelivered 13 Apr, billed£281.47
PO-5252
Halbrook Worktops, raised 8 Apr
Worktops, templated and fittedDelivered 20 Apr, billed£2,477.56
PO-5227
Wrenfold Kitchen Supply, raised 19 Mar
Kitchen units and doorsDelivered 10 Apr, billed£5,243.59
Subcontractor invoices · 5, £3,000
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3549
Gary Pullen Electrical, 22 Apr
Electrics, second fixPaid£675.00
SC-3550
Jon Haskins Plumbing and Heating, 22 Apr
Plumbing, second fixPaid£495.00
SC-3541
Mark Dent Plastering, 16 Apr
Plastering, skim and making goodPaid£660.00
SC-3537
Gary Pullen Electrical, 14 Apr
Electrics, first fixPaid£675.00
SC-3538
Jon Haskins Plumbing and Heating, 14 Apr
Plumbing, first fixPaid£495.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2258
issued 24 Feb
Deposit
1 line
Paid 11 Mar£5,850.00£7,020.00posted
INV-2300
issued 17 Apr
Progress
1 line
Paid 3 May£11,700.00£14,040.00posted
INV-2308
issued 27 Apr
Completion
1 line
Paid 10 May£5,850.00£7,020.00posted
Stages £23,400 + billed extras £0 = £23,400 on invoices. £23,400 sent, £23,400 paid.
CT
Claire and Toby Davies
Claire Davies · client since 12 Feb 2026
Site90 Rowan Drive, Knowle
Phone07700 900326
PortalLive: progress, extras, invoices
See what Claire sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewCrew A: Steve, Liam, Josh
Booked22 Feb 2026
StartedMon 13 Apr
Handed over26 Apr 2026
Timeline
Handed over and closed
Kate · 26 Apr 15:00
Gary Pullen Electrical: Electrics, second fix, £675.00
Gary Pullen · 22 Apr 17:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £495.00
Jon Haskins · 22 Apr 17:00
Mark Dent Plastering: Plastering, skim and making good, £660.00
Mark Dent · 16 Apr 17:00
Gary Pullen Electrical: Electrics, first fix, £675.00
Gary Pullen · 14 Apr 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £495.00
Jon Haskins · 14 Apr 17:00
First day on site: Josh, Liam, Steve
Site app · 13 Apr 07:30
Booked: £23,400 ex VAT
Owen · 22 Feb 11:00