Bathroom · domestic · fixed price

Job 3969

Complete
En-suite shower room
For Helen Fletcher, Portishead. Crew B with Kate Lyons. On site 30 Mar to 2 Apr, handed over 6 Apr 2026.
Agreed price
£11,000
ex VAT
Final margin
24.1%
quoted 26.4%
100% of the work done19 m² tiled
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Quoted margin26.4%£2,902 on £11,000
Final margin24.1%£2,653 profit
Invoiced so far£11,000of £11,000, £11,000 paid
Where the money went
PersonHoursLabour costDifference
MT
Mike Tanner
Lead fitter and tiler, crew B, £34/h at cost
32 h
of 32 h estimated
£1,088
of £1,088
on budget
RH
Ryan Hale
Fitter, crew B, £30/h at cost
32 h
of 28 h estimated
£960
of £840
+£120
CW
Callum Webb
Apprentice fitter, crew B, £16/h at cost
24 h
of 20 h estimated
£384
of £320
+£64
True labour cost. The 25 bathrooms finished this year really took 4.5 h per m² tiled, against the old rule of 4.2. This job: 19 m² tiled, priced on 80 h. Rule of thumb: 4.2 h per m² tiled. New quotes now use the true rate →
Cost week by week
£8,347 spent over 2 weeks, against a £8,098 estimate
LabourMaterialsSubcontract
Extras and variations · 0
Variations →
No extras on this job.
Timesheets · 88 h, £2,432 at cost
Timesheets →
Week ofPersonHoursCostStatus
30 Mar
Tap for the days
CWCallum Webb24 h
3 days
£384.00
at £16/h
approved
from the paper sheets
30 Mar
Tap for the days
MTMike Tanner32 h
4 days
£1,088.00
at £34/h
approved
from the paper sheets
30 Mar
Tap for the days
RHRyan Hale32 h
4 days
£960.00
at £30/h
approved
from the paper sheets
Purchases · 5, £3,865
Purchases →
OrderWhatStatusNet
PO-5237
Voltmere Electrical Wholesale, raised 27 Mar
Lighting and extractorDelivered 30 Mar, billed£192.85
PO-5238
Avonmere Builders Merchants, raised 27 Mar
Board, tanking and sundriesDelivered 30 Mar, billed£488.94
PO-5235
Kestle Timber, raised 26 Mar
Timber and fixingsDelivered 30 Mar, billed£274.80
PO-5236
Brackwell Tiles, raised 26 Mar
Wall and floor tiles, adhesive, groutDelivered 31 Mar, billed£1,056.13
PO-5226
Linmouth Bathroom Supply, raised 18 Mar
Sanitaryware and brasswareDelivered 27 Mar, billed£1,852.28
Subcontractor invoices · 5, £2,050
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3525
Jon Haskins Plumbing and Heating, 2 Apr
Plumbing, second fixPaid£635.00
SC-3526
Gary Pullen Electrical, 2 Apr
Electrics, second fixPaid£185.00
SC-3523
Mark Dent Plastering, 31 Mar
Plastering, skim and making goodPaid£410.00
SC-3521
Jon Haskins Plumbing and Heating, 30 Mar
Plumbing, first fixPaid£635.00
SC-3522
Gary Pullen Electrical, 30 Mar
Electrics, first fixPaid£185.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2262
issued 2 Mar
Deposit
1 line
Paid 9 Mar£2,750.00£3,300.00posted
INV-2286
issued 31 Mar
Progress
1 line
Paid 9 Apr£5,500.00£6,600.00posted
INV-2293
issued 7 Apr
Completion
1 line
Paid 17 Apr£2,750.00£3,300.00posted
Stages £11,000 + billed extras £0 = £11,000 on invoices. £11,000 sent, £11,000 paid.
HF
Helen Fletcher
Helen Fletcher · client since 29 Jan 2026
Site51 Hollybush Lane, Portishead
Phone07700 900782
PortalLive: progress, extras, invoices
See what Helen sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewCrew B: Mike, Ryan, Callum
Booked26 Feb 2026
StartedMon 30 Mar
Handed over6 Apr 2026
Timeline
Handed over and closed
Kate · 6 Apr 15:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £635.00
Jon Haskins · 2 Apr 17:00
Gary Pullen Electrical: Electrics, second fix, £185.00
Gary Pullen · 2 Apr 17:00
Mark Dent Plastering: Plastering, skim and making good, £410.00
Mark Dent · 31 Mar 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £635.00
Jon Haskins · 30 Mar 17:00
Gary Pullen Electrical: Electrics, first fix, £185.00
Gary Pullen · 30 Mar 17:00
First day on site: Callum, Mike, Ryan
Site app · 30 Mar 07:30
Booked: £11,000 ex VAT
Owen · 26 Feb 11:00