Kitchen · domestic · fixed price

Job 3971

Complete
Kitchen fit-out
For Beth and Ben Penfold, Frenchay. Crew A with Kate Lyons. On site 29 Apr to 12 May, handed over 19 May 2026.
Agreed price
£22,800
ex VAT
Final margin
23.0%
quoted 24.7%
100% of the work done15 cabinets
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Quoted margin24.7%£5,628 on £22,800
Final margin23.0%£5,233 profit
Invoiced so far£22,800of £22,800, £22,800 paid
Where the money went
PersonHoursLabour costDifference
SR
Steve Rowe
Lead fitter, crew A, £34/h at cost
64 h
of 60.5 h estimated
£2,176
of £2,057
+£119
LD
Liam Doyle
Joiner, crew A, £30/h at cost
64 h
of 60.5 h estimated
£1,920
of £1,815
+£105
JP
Josh Penrose
Apprentice joiner, crew A, £16/h at cost
48 h
of 38 h estimated
£768
of £608
+£160
RF
Rob Finch
Decorator, £28/h at cost
16 h
of 14 h estimated
£448
of £392
+£56
True labour cost. The 15 kitchens finished this year really took 12.95 h per cabinet, against the old rule of 11.5. This job: 15 cabinets, priced on 173 h. Rule of thumb: 11.5 h per cabinet. New quotes now use the true rate →
Cost week by week
£17,567 spent over 3 weeks, against a £17,172 estimate
LabourMaterialsSubcontract
Extras and variations · 0
Variations →
No extras on this job.
Timesheets · 192 h, £5,312 at cost
Timesheets →
Week ofPersonHoursCostStatus
11 May
Tap for the days
JPJosh Penrose8 h
1 day
£128.00
at £16/h
approved
from the paper sheets
11 May
Tap for the days
LDLiam Doyle8 h
1 day
£240.00
at £30/h
approved
from the paper sheets
11 May
Tap for the days
RFRob Finch16 h
2 days
£448.00
at £28/h
approved
from the paper sheets
11 May
Tap for the days
SRSteve Rowe8 h
1 day
£272.00
at £34/h
approved
from the paper sheets
4 May
Tap for the days
JPJosh Penrose24 h
3 days
£384.00
at £16/h
approved
from the paper sheets
4 May
Tap for the days
LDLiam Doyle32 h
4 days
£960.00
at £30/h
approved
from the paper sheets
4 May
Tap for the days
SRSteve Rowe32 h
4 days
£1,088.00
at £34/h
approved
from the paper sheets
27 Apr
Tap for the days
JPJosh Penrose16 h
2 days
£256.00
at £16/h
approved
from the paper sheets
27 Apr
Tap for the days
LDLiam Doyle24 h
3 days
£720.00
at £30/h
approved
from the paper sheets
27 Apr
Tap for the days
SRSteve Rowe24 h
3 days
£816.00
at £34/h
approved
from the paper sheets
Purchases · 6, £9,255
Purchases →
OrderWhatStatusNet
PO-5281
Brackwell Tiles, raised 30 Apr
Splashback tiles and adhesiveDelivered 5 May, billed£388.30
PO-5274
Avonmere Builders Merchants, raised 26 Apr
Plaster, board and sundriesDelivered 29 Apr, billed£376.70
PO-5275
Voltmere Electrical Wholesale, raised 26 Apr
Lighting and electrical fittingsDelivered 29 Apr, billed£373.11
PO-5277
Halbrook Worktops, raised 26 Apr
Worktops, templated and fittedDelivered 8 May, billed£2,473.70
PO-5273
Kestle Timber, raised 25 Apr
Timber, panels and fixingsDelivered 29 Apr, billed£280.19
PO-5249
Wrenfold Kitchen Supply, raised 6 Apr
Kitchen units and doorsDelivered 28 Apr, billed£5,362.84
Subcontractor invoices · 5, £3,000
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3571
Gary Pullen Electrical, 12 May
Electrics, second fixPaid£675.00
SC-3572
Jon Haskins Plumbing and Heating, 12 May
Plumbing, second fixPaid£495.00
SC-3563
Mark Dent Plastering, 5 May
Plastering, skim and making goodPaid£660.00
SC-3557
Gary Pullen Electrical, 30 Apr
Electrics, first fixPaid£675.00
SC-3558
Jon Haskins Plumbing and Heating, 30 Apr
Plumbing, first fixPaid£495.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2271
issued 11 Mar
Deposit
1 line
Paid 19 Mar£5,700.00£6,840.00posted
INV-2311
issued 5 May
Progress
1 line
Paid 12 May£11,400.00£13,680.00posted
INV-2325
issued 20 May
Completion
1 line
Paid 2 Jun£5,700.00£6,840.00posted
Stages £22,800 + billed extras £0 = £22,800 on invoices. £22,800 sent, £22,800 paid.
BB
Beth and Ben Penfold
Beth Penfold · client since 28 Feb 2026
Site51 Park Avenue, Frenchay
Phone07700 900280
PortalLive: progress, extras, invoices
See what Beth sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewCrew A: Steve, Liam, Josh
Booked9 Mar 2026
StartedWed 29 Apr
Handed over19 May 2026
Timeline
Handed over and closed
Kate · 19 May 15:00
Gary Pullen Electrical: Electrics, second fix, £675.00
Gary Pullen · 12 May 17:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £495.00
Jon Haskins · 12 May 17:00
Mark Dent Plastering: Plastering, skim and making good, £660.00
Mark Dent · 5 May 17:00
Gary Pullen Electrical: Electrics, first fix, £675.00
Gary Pullen · 30 Apr 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £495.00
Jon Haskins · 30 Apr 17:00
First day on site: Liam, Steve
Site app · 29 Apr 07:30
Booked: £22,800 ex VAT
Owen · 9 Mar 11:00