LIVE DEMO
Bathroom · domestic · fixed price

Job 3976

Complete
Downstairs cloakroom
For James Elworthy, Southville. Chris Moss (small works) with Kate Lyons. On site 15 Apr to 17 Apr, handed over 20 Apr 2026.
Agreed price
£8,850
ex VAT, +£470 extras billed
Final margin
30.8%
quoted 29.9%
100% of the work done5 m²
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Extras captured on site
1 extra on this job
Every extra ↓
Quoted margin29.9%£2,648 on £8,850
Final margin30.8%£2,869 profit
Invoiced so far£9,320of £9,320, £9,320 paid
Where the money went
PersonHoursLabour costDifference
CM
Chris Moss
Small works and snagging fitter, £30/h at cost
24 h
of 24 h estimated
£720
of £720
on budget
SK
Sam Kerridge
Labourer and driver, £22/h at cost
8 h
of 6 h estimated
£176
of £132
+£44
Rule of thumb: 6 h per m².
Cost week by week
£6,451 spent over 1 week, against a £6,202 estimate
LabourMaterialsSubcontract
Extras and variations · 1
Variations →
Timesheets · 32 h, £896 at cost
Timesheets →
Week ofPersonHoursCostStatus
13 Apr
Tap for the days
CMChris Moss24 h
3 days
£720.00
at £30/h
approved
from the paper sheets
13 Apr
Tap for the days
SKSam Kerridge8 h
1 day
£176.00
at £22/h
approved
from the paper sheets
Purchases · 4, £4,155
Purchases →
OrderWhatStatusNet
PO-5258
Avonmere Builders Merchants, raised 12 Apr
Board and sundriesDelivered 15 Apr, billed£416.11
PO-5256
Brackwell Tiles, raised 11 Apr
Tiles and adhesiveDelivered 16 Apr, billed£628.24
PO-5246
Linmouth Bathroom Supply, raised 5 Apr
Sanitaryware and brasswareDelivered 14 Apr, billed£2,083.34
PO-5243
Wrenfold Kitchen Supply, raised 31 Mar
Utility unitsDelivered 15 Apr, billed£1,027.64
Subcontractor invoices · 4, £1,400
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3543
Jon Haskins Plumbing and Heating, 17 Apr
Plumbing, second fixPaid£525.00
SC-3544
Gary Pullen Electrical, 17 Apr
Electrics, second fixPaid£175.00
SC-3539
Jon Haskins Plumbing and Heating, 15 Apr
Plumbing, first fixPaid£525.00
SC-3540
Gary Pullen Electrical, 15 Apr
Electrics, first fixPaid£175.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2289
issued 1 Apr
Deposit
1 line
Paid 7 Apr£2,212.50£2,655.00posted
INV-2298
issued 16 Apr
Progress
1 line
Paid 25 Apr£4,425.00£5,310.00posted
INV-2306
issued 21 Apr
Completion
2 lines, with V-3976-1
Paid 26 Apr£2,682.50£3,219.00posted
Stages £8,850 + billed extras £470 = £9,320 on invoices. £9,320 sent, £9,320 paid.
JE
James Elworthy
James Elworthy · client since 14 Feb 2026
Site50 Grange Road, Southville
Phone07700 900982
PortalLive: progress, extras, invoices
See what James sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewChris Moss, small works
Booked30 Mar 2026
StartedWed 15 Apr
Handed over20 Apr 2026
Timeline
Handed over and closed
Kate · 20 Apr 15:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £525.00
Jon Haskins · 17 Apr 17:00
Gary Pullen Electrical: Electrics, second fix, £175.00
Gary Pullen · 17 Apr 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £525.00
Jon Haskins · 15 Apr 17:00
Gary Pullen Electrical: Electrics, first fix, £175.00
Gary Pullen · 15 Apr 17:00
First day on site: Chris, Sam
Site app · 15 Apr 07:30
Booked: £8,850 ex VAT
Owen · 30 Mar 11:00