LIVE DEMO
Bathroom · domestic · fixed price

Job 3977

Complete
Bathroom and en-suite
For Catherine Hembrow, Bedminster. Crew B with Kate Lyons. On site 30 Apr to 7 May, handed over 12 May 2026.
Agreed price
£13,050
ex VAT
Final margin
23.4%
quoted 23.8%
100% of the work done27 m² tiled
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Quoted margin23.8%£3,112 on £13,050
Final margin23.4%£3,055 profit
Invoiced so far£13,050of £13,050, £13,050 paid
Where the money went
PersonHoursLabour costDifference
MT
Mike Tanner
Lead fitter and tiler, crew B, £34/h at cost
40 h
of 45.5 h estimated
£1,360
of £1,547
-£187
RH
Ryan Hale
Fitter, crew B, £30/h at cost
40 h
of 39.5 h estimated
£1,200
of £1,185
+£15
CW
Callum Webb
Apprentice fitter, crew B, £16/h at cost
32 h
of 28.5 h estimated
£512
of £456
+£56
True labour cost. The 25 bathrooms finished this year really took 4.5 h per m² tiled, against the old rule of 4.2. This job: 27 m² tiled, priced on 113.5 h. Rule of thumb: 4.2 h per m² tiled. New quotes now use the true rate →
Cost week by week
£9,995 spent over 2 weeks, against a £9,938 estimate
LabourMaterialsSubcontract
Extras and variations · 0
Variations →
No extras on this job.
Timesheets · 112 h, £3,072 at cost
Timesheets →
Week ofPersonHoursCostStatus
4 May
Tap for the days
CWCallum Webb16 h
2 days
£256.00
at £16/h
approved
from the paper sheets
4 May
Tap for the days
MTMike Tanner24 h
3 days
£816.00
at £34/h
approved
from the paper sheets
4 May
Tap for the days
RHRyan Hale24 h
3 days
£720.00
at £30/h
approved
from the paper sheets
27 Apr
Tap for the days
CWCallum Webb16 h
2 days
£256.00
at £16/h
approved
from the paper sheets
27 Apr
Tap for the days
MTMike Tanner16 h
2 days
£544.00
at £34/h
approved
from the paper sheets
27 Apr
Tap for the days
RHRyan Hale16 h
2 days
£480.00
at £30/h
approved
from the paper sheets
Purchases · 5, £4,504
Purchases →
OrderWhatStatusNet
PO-5282
Brackwell Tiles, raised 30 Apr
Wall and floor tiles, adhesive, groutDelivered 5 May, billed£1,231.88
PO-5278
Avonmere Builders Merchants, raised 27 Apr
Board, tanking and sundriesDelivered 30 Apr, billed£561.23
PO-5279
Voltmere Electrical Wholesale, raised 27 Apr
Lighting and extractorDelivered 30 Apr, billed£218.51
PO-5276
Kestle Timber, raised 26 Apr
Timber and fixingsDelivered 30 Apr, billed£306.70
PO-5270
Linmouth Bathroom Supply, raised 20 Apr
Sanitaryware and brasswareDelivered 29 Apr, billed£2,185.21
Subcontractor invoices · 5, £2,420
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3565
Jon Haskins Plumbing and Heating, 7 May
Plumbing, second fixPaid£752.18
SC-3566
Gary Pullen Electrical, 7 May
Electrics, second fixPaid£215.66
SC-3564
Mark Dent Plastering, 5 May
Plastering, skim and making goodPaid£483.92
SC-3561
Jon Haskins Plumbing and Heating, 1 May
Plumbing, first fixPaid£752.18
SC-3559
Gary Pullen Electrical, 30 Apr
Electrics, first fixPaid£215.66
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2290
issued 1 Apr
Deposit
1 line
Paid 7 Apr£3,262.50£3,915.00posted
INV-2312
issued 5 May
Progress
1 line
Paid 16 May£6,525.00£7,830.00posted
INV-2321
issued 13 May
Completion
1 line
Paid 29 May£3,262.50£3,915.00posted
Stages £13,050 + billed extras £0 = £13,050 on invoices. £13,050 sent, £13,050 paid.
CH
Catherine Hembrow
Catherine Hembrow · client since 1 Mar 2026
Site48 Station Road, Bedminster
Phone07700 900569
PortalLive: progress, extras, invoices
See what Catherine sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewCrew B: Mike, Ryan, Callum
Booked30 Mar 2026
StartedThu 30 Apr
Handed over12 May 2026
Timeline
Handed over and closed
Kate · 12 May 15:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £752.18
Jon Haskins · 7 May 17:00
Gary Pullen Electrical: Electrics, second fix, £215.66
Gary Pullen · 7 May 17:00
Mark Dent Plastering: Plastering, skim and making good, £483.92
Mark Dent · 5 May 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £752.18
Jon Haskins · 1 May 17:00
Gary Pullen Electrical: Electrics, first fix, £215.66
Gary Pullen · 30 Apr 17:00
First day on site: Callum, Mike, Ryan
Site app · 30 Apr 07:30
Booked: £13,050 ex VAT
Owen · 30 Mar 11:00