Job 3991

Complete
Office fit-out
For Orchard Gate Solicitors, Bristol. Crew C with Gareth Price. On site 26 Jun to 1 Jul, handed over 9 Jul 2026.
Agreed price
£29,600
ex VAT
Final margin
22.1%
quoted 22.5%
100% of the work done121 m² floor
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Quoted margin22.5%£6,654 on £29,600
Final margin22.1%£6,548 profit
Invoiced so far£29,600of £29,600, £28,120 paid, £1,480 retention held
Where the money went
PersonHoursLabour costDifference
DK
Dave Kerr
Lead fitter, crew C, £35/h at cost
32 h
of 32.5 h estimated
£1,120
of £1,138
-£17
TA
Tom Ashby
Joiner, crew C, £30/h at cost
32 h
of 32.5 h estimated
£960
of £975
-£15
ER
Ellie Rudd
Apprentice joiner, crew C, £16/h at cost
24 h
of 24 h estimated
£384
of £384
on budget
RF
Rob Finch
Decorator, £28/h at cost
8 h
of 10 h estimated
£224
of £280
-£56
SK
Sam Kerridge
Labourer and driver, £22/h at cost
8 h
of 10 h estimated
£176
of £220
-£44
True labour cost. The 7 offices finished this year really took 0.95 h per m² of floor, against the old rule of 0.9. This job: 121 m² floor, priced on 109 h. Rule of thumb: 0.9 h per m² of floor. New quotes now use the true rate →
Cost week by week
£23,052 spent over 2 weeks, against a £22,947 estimate
LabourMaterialsSubcontract
Extras and variations · 0
Variations →
No extras on this job.
Timesheets · 104 h, £2,864 at cost
Timesheets →
Week ofPersonHoursCostStatus
29 Jun
Tap for the days
DKDave Kerr24 h
3 days
£840.00
at £35/h
approved
29 Jun
Tap for the days
EREllie Rudd16 h
2 days
£256.00
at £16/h
approved
29 Jun
Tap for the days
RFRob Finch8 h
1 day
£224.00
at £28/h
approved
29 Jun
Tap for the days
TATom Ashby24 h
3 days
£720.00
at £30/h
approved
22 Jun
Tap for the days
DKDave Kerr8 h
1 day
£280.00
at £35/h
approved
22 Jun
Tap for the days
EREllie Rudd8 h
1 day
£128.00
at £16/h
approved
22 Jun
Tap for the days
SKSam Kerridge8 h
1 day
£176.00
at £22/h
approved
22 Jun
Tap for the days
TATom Ashby8 h
1 day
£240.00
at £30/h
approved
Purchases · 4, £11,122
Purchases →
OrderWhatStatusNet
PO-5363
Cotsmoor Flooring Trade, raised 24 Jun
FlooringDelivered 1 Jul, billed£2,632.84
PO-5362
Voltmere Electrical Wholesale, raised 23 Jun
Lighting and electricalDelivered 26 Jun, billed£2,431.64
PO-5359
Avonmere Builders Merchants, raised 22 Jun
Partitions, board and ceilingsDelivered 25 Jun, billed£4,082.59
PO-5361
Kestle Timber, raised 22 Jun
Joinery timber and sheetDelivered 26 Jun, billed£1,974.47
Subcontractor invoices · 4, £9,067
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3642
Andy Rees Electrical, 1 Jul
Electrics and data, second fixPaid£2,720.05
SC-3643
Nick Weller Flooring, 1 Jul
Floor laying, supply-laid by the floor layerPaid£1,362.71
SC-3639
Mark Dent Plastering, 29 Jun
Plastering, skim and making goodPaid£2,264.03
SC-3637
Andy Rees Electrical, 26 Jun
Electrics and data, first fixPaid£2,720.06
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2329
issued 20 May
Deposit
1 line
Paid 11 Jun£7,400.00£8,436.00
£370 retention held
posted
INV-2365
issued 29 Jun
Progress
1 line
Paid 23 Jul£14,800.00£16,872.00
£740 retention held
posted
INV-2375
issued 10 Jul
Completion
1 line
Paid 31 Jul£7,400.00£8,436.00
£370 retention held
posted
Stages £29,600 + billed extras £0 = £29,600 on invoices. £29,600 sent, £28,120 paid, £1,480 retention held until the defects period ends.
OG
Orchard Gate Solicitors
Contact: Zoe Vickery · client since 27 Apr 2026
Site11 Corn Street, Bristol
Phone0117 496 0689
PortalLive: progress, extras, invoices
See what Zoe sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerGareth Price
CrewCrew C: Dave, Tom, Ellie
Booked18 May 2026
StartedFri 26 Jun
Handed over9 Jul 2026
Retention5% held to the end of defects
Timeline
Handed over and closed
Gareth · 9 Jul 15:00
Andy Rees Electrical: Electrics and data, second fix, £2,720.05
Andy Rees · 1 Jul 17:00
Nick Weller Flooring: Floor laying, supply-laid by the floor layer, £1,362.71
Nick Weller · 1 Jul 17:00
Mark Dent Plastering: Plastering, skim and making good, £2,264.03
Mark Dent · 29 Jun 17:00
Andy Rees Electrical: Electrics and data, first fix, £2,720.06
Andy Rees · 26 Jun 17:00
First day on site: Dave, Ellie, Sam, Tom
Site app · 26 Jun 07:30
Booked: £29,600 ex VAT
Owen · 18 May 11:00