Office · commercial · fixed price

Job 3995

Complete
Office refurbishment
For Gulliver Partners, Bristol. Crew C with Gareth Price. On site 9 Jul to 13 Jul, handed over 17 Jul 2026.
Agreed price
£20,250
ex VAT, +£1,550 extras billed
Final margin
22.3%
quoted 20.2%
100% of the work done85 m² floor
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Extras captured on site
2 extras on this job
Every extra ↓
Quoted margin20.2%£4,083 on £20,250
Final margin22.3%£4,863 profit
Invoiced so far£21,800of £21,800, £20,710 paid, £1,090 retention held
Where the money went
PersonHoursLabour costDifference
DK
Dave Kerr
Lead fitter, crew C, £35/h at cost
24 h
of 23 h estimated
£840
of £805
+£35
TA
Tom Ashby
Joiner, crew C, £30/h at cost
24 h
of 23 h estimated
£720
of £690
+£30
ER
Ellie Rudd
Apprentice joiner, crew C, £16/h at cost
24 h
of 17 h estimated
£384
of £272
+£112
RF
Rob Finch
Decorator, £28/h at cost
8 h
of 7 h estimated
£224
of £196
+£28
SK
Sam Kerridge
Labourer and driver, £22/h at cost
8 h
of 7 h estimated
£176
of £154
+£22
True labour cost. The 7 offices finished this year really took 0.95 h per m² of floor, against the old rule of 0.9. This job: 85 m² floor, priced on 77 h. Rule of thumb: 0.9 h per m² of floor. New quotes now use the true rate →
Cost week by week
£16,937 spent over 2 weeks, against a £16,167 estimate
LabourMaterialsSubcontract
Extras and variations · 2
Variations →
Timesheets · 88 h, £2,344 at cost
Timesheets →
Week ofPersonHoursCostStatus
13 Jul
Tap for the days
DKDave Kerr8 h
1 day
£280.00
at £35/h
approved
13 Jul
Tap for the days
EREllie Rudd8 h
1 day
£128.00
at £16/h
approved
13 Jul
Tap for the days
RFRob Finch8 h
1 day
£224.00
at £28/h
approved
13 Jul
Tap for the days
TATom Ashby8 h
1 day
£240.00
at £30/h
approved
6 Jul
Tap for the days
DKDave Kerr16 h
2 days
£560.00
at £35/h
approved
6 Jul
Tap for the days
EREllie Rudd16 h
2 days
£256.00
at £16/h
approved
6 Jul
Tap for the days
SKSam Kerridge8 h
1 day
£176.00
at £22/h
approved
6 Jul
Tap for the days
TATom Ashby16 h
2 days
£480.00
at £30/h
approved
Purchases · 4, £8,179
Purchases →
OrderWhatStatusNet
PO-5385
Cotsmoor Flooring Trade, raised 6 Jul
FlooringDelivered 13 Jul, billed£1,953.29
PO-5386
Voltmere Electrical Wholesale, raised 6 Jul
Lighting and electricalDelivered 9 Jul, billed£1,809.31
PO-5380
Avonmere Builders Merchants, raised 5 Jul
Partitions, board and ceilingsDelivered 8 Jul, billed£2,936.63
PO-5381
Kestle Timber, raised 5 Jul
Joinery timber and sheetDelivered 9 Jul, billed£1,480.11
Subcontractor invoices · 4, £6,414
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3661
Andy Rees Electrical, 13 Jul
Electrics and data, second fixPaid£1,924.23
SC-3662
Nick Weller Flooring, 13 Jul
Floor laying, supply-laid by the floor layerPaid£959.42
SC-3660
Mark Dent Plastering, 10 Jul
Plastering, skim and making goodPaid£1,606.22
SC-3657
Andy Rees Electrical, 9 Jul
Electrics and data, first fixPaid£1,924.23
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2338
issued 1 Jun
Deposit
1 line
Paid 6 Jul£5,062.50£5,771.24
£253 retention held
posted
INV-2380
issued 13 Jul
Progress
1 line
Paid 20 Aug£10,125.00£11,542.50
£506 retention held
posted
INV-2383
issued 20 Jul
Completion
3 lines, with V-3995-1, V-3995-2
Paid 19 Aug£6,612.50£7,538.24
£331 retention held
posted
Stages £20,250 + billed extras £1,550 = £21,800 on invoices. £21,800 sent, £20,710 paid, £1,090 retention held until the defects period ends.
GP
Gulliver Partners
Contact: Zoe Selby · client since 10 May 2026
Site105 Whiteladies Road, Bristol
Phone0117 496 0552
PortalLive: progress, extras, invoices
See what Zoe sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerGareth Price
CrewCrew C: Dave, Tom, Ellie
Booked28 May 2026
StartedThu 9 Jul
Handed over17 Jul 2026
Retention5% held to the end of defects
Timeline
Handed over and closed
Gareth · 17 Jul 15:00
Andy Rees Electrical: Electrics and data, second fix, £1,924.23
Andy Rees · 13 Jul 17:00
Nick Weller Flooring: Floor laying, supply-laid by the floor layer, £959.42
Nick Weller · 13 Jul 17:00
Mark Dent Plastering: Plastering, skim and making good, £1,606.22
Mark Dent · 10 Jul 17:00
Andy Rees Electrical: Electrics and data, first fix, £1,924.23
Andy Rees · 9 Jul 17:00
First day on site: Dave, Ellie, Sam, Tom
Site app · 9 Jul 07:30
Booked: £20,250 ex VAT
Owen · 28 May 11:00