Clinic · commercial · fixed price

Job 3998

Complete
Practice refurbishment
For Kingsmere Vets, Bristol. Crew C with Gareth Price. On site 17 Jul to 3 Aug, handed over 10 Aug 2026.
Agreed price
£49,250
ex VAT
Final margin
22.8%
quoted 22.5%
100% of the work done150 m² floor
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Quoted margin22.5%£11,058 on £49,250
Final margin22.8%£11,218 profit
Invoiced so far£49,250of £49,250, £46,787 paid, £2,463 retention held
Where the money went
PersonHoursLabour costDifference
DK
Dave Kerr
Lead fitter, crew C, £35/h at cost
80 h
of 81 h estimated
£2,800
of £2,835
-£35
TA
Tom Ashby
Joiner, crew C, £30/h at cost
80 h
of 81 h estimated
£2,400
of £2,430
-£30
ER
Ellie Rudd
Apprentice joiner, crew C, £16/h at cost
64 h
of 59.5 h estimated
£1,024
of £952
+£72
RF
Rob Finch
Decorator, £28/h at cost
24 h
of 24.5 h estimated
£672
of £686
-£14
SK
Sam Kerridge
Labourer and driver, £22/h at cost
24 h
of 24.5 h estimated
£528
of £539
-£11
True labour cost. The 3 clinics and practices finished this year really took 1.94 h per m² of floor, against the old rule of 1.8. This job: 150 m² floor, priced on 270.5 h. Rule of thumb: 1.8 h per m² of floor. New quotes now use the true rate →
Cost week by week
£38,032 spent over 4 weeks, against a £38,192 estimate
LabourMaterialsSubcontract
Extras and variations · 0
Variations →
No extras on this job.
Timesheets · 272 h, £7,424 at cost
Timesheets →
Week ofPersonHoursCostStatus
3 Aug
Tap for the days
RFRob Finch8 h
1 day
£224.00
at £28/h
approved
27 Jul
Tap for the days
DKDave Kerr32 h
4 days
£1,120.00
at £35/h
approved
27 Jul
Tap for the days
EREllie Rudd24 h
3 days
£384.00
at £16/h
approved
27 Jul
Tap for the days
RFRob Finch16 h
2 days
£448.00
at £28/h
approved
27 Jul
Tap for the days
TATom Ashby32 h
4 days
£960.00
at £30/h
approved
20 Jul
Tap for the days
DKDave Kerr40 h
5 days
£1,400.00
at £35/h
approved
20 Jul
Tap for the days
EREllie Rudd32 h
4 days
£512.00
at £16/h
approved
20 Jul
Tap for the days
SKSam Kerridge16 h
2 days
£352.00
at £22/h
approved
20 Jul
Tap for the days
TATom Ashby40 h
5 days
£1,200.00
at £30/h
approved
13 Jul
Tap for the days
DKDave Kerr8 h
1 day
£280.00
at £35/h
approved
13 Jul
Tap for the days
EREllie Rudd8 h
1 day
£128.00
at £16/h
approved
13 Jul
Tap for the days
SKSam Kerridge8 h
1 day
£176.00
at £22/h
approved
13 Jul
Tap for the days
TATom Ashby8 h
1 day
£240.00
at £30/h
approved
Purchases · 5, £16,358
Purchases →
OrderWhatStatusNet
PO-5410
Cotsmoor Flooring Trade, raised 23 Jul
Safety flooringDelivered 30 Jul, billed£2,958.91
PO-5402
Voltmere Electrical Wholesale, raised 17 Jul
Lighting and electricalDelivered 20 Jul, billed£3,244.65
PO-5397
Kestle Timber, raised 16 Jul
Joinery timber and sheetDelivered 20 Jul, billed£2,637.03
PO-5392
Avonmere Builders Merchants, raised 13 Jul
Partitions, board and ceilingsDelivered 16 Jul, billed£4,977.59
PO-5390
Linmouth Bathroom Supply, raised 11 Jul
Clinical sinks and tapsDelivered 20 Jul, billed£2,540.16
Subcontractor invoices · 5, £14,250
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3687
Andy Rees Electrical, 3 Aug
Electrics and data, second fixPaid£3,205.00
SC-3688
Jon Haskins Plumbing and Heating, 3 Aug
Plumbing, second fixPaid£2,495.00
SC-3686
Nick Weller Flooring, 31 Jul
Floor laying, supply-laid by the floor layerPaid£2,850.00
SC-3671
Jon Haskins Plumbing and Heating, 21 Jul
Plumbing, first fixPaid£2,495.00
SC-3668
Andy Rees Electrical, 20 Jul
Electrics and data, first fixPaid£3,205.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2343
issued 4 Jun
Deposit
1 line
Paid 6 Jul£12,312.50£14,036.24
£616 retention held
posted
INV-2392
issued 27 Jul
Progress
1 line
Paid 15 Aug£24,625.00£28,072.50
£1,231 retention held
posted
INV-2403
issued 11 Aug
Completion
1 line
Paid 2 Sep£12,312.50£14,036.24
£616 retention held
posted
Stages £49,250 + billed extras £0 = £49,250 on invoices. £49,250 sent, £46,787 paid, £2,463 retention held until the defects period ends.
KV
Kingsmere Vets
Contact: Laura Pullin · client since 18 May 2026
Site56 Corn Street, Bristol
Phone0117 496 0957
PortalLive: progress, extras, invoices
See what Laura sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerGareth Price
CrewCrew C: Dave, Tom, Ellie
Booked2 Jun 2026
StartedFri 17 Jul
Handed over10 Aug 2026
Retention5% held to the end of defects
Timeline
Handed over and closed
Gareth · 10 Aug 15:00
Andy Rees Electrical: Electrics and data, second fix, £3,205.00
Andy Rees · 3 Aug 17:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £2,495.00
Jon Haskins · 3 Aug 17:00
Nick Weller Flooring: Floor laying, supply-laid by the floor layer, £2,850.00
Nick Weller · 31 Jul 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £2,495.00
Jon Haskins · 21 Jul 17:00
Andy Rees Electrical: Electrics and data, first fix, £3,205.00
Andy Rees · 20 Jul 17:00
First day on site: Dave, Ellie, Sam, Tom
Site app · 17 Jul 07:30
Booked: £49,250 ex VAT
Owen · 2 Jun 11:00