Job 3999

Complete
Kitchen-diner fit-out
For Jane and Will Lear, Cotham. Crew A with Kate Lyons. On site 20 Jul to 29 Jul, handed over 7 Aug 2026.
Agreed price
£24,450
ex VAT
Final margin
25.4%
quoted 25.8%
100% of the work done16 cabinets
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Quoted margin25.8%£6,318 on £24,450
Final margin25.4%£6,210 profit
Invoiced so far£24,450of £24,450, £24,450 paid
Where the money went
PersonHoursLabour costDifference
SR
Steve Rowe
Lead fitter, crew A, £34/h at cost
64 h
of 64.5 h estimated
£2,176
of £2,193
-£17
LD
Liam Doyle
Joiner, crew A, £30/h at cost
64 h
of 64.5 h estimated
£1,920
of £1,935
-£15
JP
Josh Penrose
Apprentice joiner, crew A, £16/h at cost
48 h
of 40.5 h estimated
£768
of £648
+£120
RF
Rob Finch
Decorator, £28/h at cost
16 h
of 14.5 h estimated
£448
of £406
+£42
True labour cost. The 15 kitchens finished this year really took 12.95 h per cabinet, against the old rule of 11.5. This job: 16 cabinets, priced on 184 h. Rule of thumb: 11.5 h per cabinet. New quotes now use the true rate →
Cost week by week
£18,240 spent over 3 weeks, against a £18,132 estimate
LabourMaterialsSubcontract
Extras and variations · 0
Variations →
No extras on this job.
Timesheets · 192 h, £5,312 at cost
Timesheets →
Week ofPersonHoursCostStatus
27 Jul
Tap for the days
JPJosh Penrose16 h
2 days
£256.00
at £16/h
approved
27 Jul
Tap for the days
LDLiam Doyle24 h
3 days
£720.00
at £30/h
approved
27 Jul
Tap for the days
RFRob Finch16 h
2 days
£448.00
at £28/h
approved
27 Jul
Tap for the days
SRSteve Rowe24 h
3 days
£816.00
at £34/h
approved
20 Jul
Tap for the days
JPJosh Penrose32 h
4 days
£512.00
at £16/h
approved
20 Jul
Tap for the days
LDLiam Doyle40 h
5 days
£1,200.00
at £30/h
approved
20 Jul
Tap for the days
SRSteve Rowe40 h
5 days
£1,360.00
at £34/h
approved
Purchases · 6, £9,878
Purchases →
OrderWhatStatusNet
PO-5406
Brackwell Tiles, raised 18 Jul
Splashback tiles and adhesiveDelivered 23 Jul, billed£391.22
PO-5403
Avonmere Builders Merchants, raised 17 Jul
Plaster, board and sundriesDelivered 20 Jul, billed£411.25
PO-5404
Voltmere Electrical Wholesale, raised 17 Jul
Lighting and electrical fittingsDelivered 20 Jul, billed£408.83
PO-5400
Kestle Timber, raised 16 Jul
Timber, panels and fixingsDelivered 20 Jul, billed£294.30
PO-5394
Halbrook Worktops, raised 15 Jul
Worktops, templated and fittedDelivered 27 Jul, billed£2,741.79
PO-5365
Wrenfold Kitchen Supply, raised 25 Jun
Kitchen units and doorsDelivered 17 Jul, billed£5,630.79
Subcontractor invoices · 5, £3,050
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3682
Gary Pullen Electrical, 29 Jul
Electrics, second fixPaid£685.00
SC-3683
Jon Haskins Plumbing and Heating, 29 Jul
Plumbing, second fixPaid£505.00
SC-3678
Mark Dent Plastering, 23 Jul
Plastering, skim and making goodPaid£670.00
SC-3672
Gary Pullen Electrical, 21 Jul
Electrics, first fixPaid£685.00
SC-3673
Jon Haskins Plumbing and Heating, 21 Jul
Plumbing, first fixPaid£505.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2345
issued 8 Jun
Deposit
1 line
Paid 19 Jun£6,112.50£7,335.00posted
INV-2391
issued 24 Jul
Progress
1 line
Paid 4 Aug£12,225.00£14,670.00posted
INV-2402
issued 10 Aug
Completion
1 line
Paid 22 Aug£6,112.50£7,335.00posted
Stages £24,450 + billed extras £0 = £24,450 on invoices. £24,450 sent, £24,450 paid.
JW
Jane and Will Lear
Jane Lear · client since 21 May 2026
Site66 Beech Grove, Cotham
Phone07700 900611
PortalLive: progress, extras, invoices
See what Jane sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewCrew A: Steve, Liam, Josh
Booked6 Jun 2026
StartedMon 20 Jul
Handed over7 Aug 2026
Timeline
Handed over and closed
Kate · 7 Aug 15:00
Gary Pullen Electrical: Electrics, second fix, £685.00
Gary Pullen · 29 Jul 17:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £505.00
Jon Haskins · 29 Jul 17:00
Mark Dent Plastering: Plastering, skim and making good, £670.00
Mark Dent · 23 Jul 17:00
Gary Pullen Electrical: Electrics, first fix, £685.00
Gary Pullen · 21 Jul 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £505.00
Jon Haskins · 21 Jul 17:00
First day on site: Josh, Liam, Steve
Site app · 20 Jul 07:30
Booked: £24,450 ex VAT
Owen · 6 Jun 11:00