LIVE DEMO
Office · commercial · fixed price

Job 4005

Snagging
Office refurbishment, two floors
For Saltmarsh Lettings, Bristol. Crew C with Gareth Price. Started 3 Aug, handover Fri 23 Oct.
Agreed price
£100,200
ex VAT, +£1,640 extras billed
Margin now
18.8%
quoted 19.1%
100% of the work done427 m² floor
Client's portal view
Job note
Practical completion signed. Two blinds and a door closer left on the snag list; 5% retention held.
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Live from the site app
Extras captured on site
1 extra on this job
Every extra ↓
Quoted margin19.1%£19,166 on £100,200
Margin now18.8%£19,111 profit on the forecast
Invoiced so far£101,840of £101,840, £96,748 paid, £5,092 retention held
Where the money went
PersonHoursLabour costDifference
DK
Dave Kerr
Lead fitter, crew C, £35/h at cost
120 h
of 115.5 h estimated
£4,200
of £4,043
+£158
TA
Tom Ashby
Joiner, crew C, £30/h at cost
120 h
of 115.5 h estimated
£3,600
of £3,465
+£135
ER
Ellie Rudd
Apprentice joiner, crew C, £16/h at cost
96 h
of 84.5 h estimated
£1,536
of £1,352
+£184
RF
Rob Finch
Decorator, £28/h at cost
40 h
of 34.5 h estimated
£1,120
of £966
+£154
SK
Sam Kerridge
Labourer and driver, £22/h at cost
16 h
of 34.5 h estimated
£352
of £759
-£407
True labour cost. The 7 offices finished this year really took 0.95 h per m² of floor, against the old rule of 0.9. This job: 427 m² floor, priced on 384.5 h. Rule of thumb: 0.9 h per m² of floor. New quotes now use the true rate →
Cost week by week
£82,729 spent over 4 weeks, against a £81,035 estimate
LabourMaterialsSubcontract
Extras and variations · 1
Variations →
Timesheets · 392 h, £10,808 at cost
Timesheets →
Week ofPersonHoursCostStatus
17 Aug
Tap for the days
DKDave Kerr40 h
5 days
£1,400.00
at £35/h
approved
17 Aug
Tap for the days
EREllie Rudd32 h
4 days
£512.00
at £16/h
approved
17 Aug
Tap for the days
RFRob Finch40 h
5 days
£1,120.00
at £28/h
approved
17 Aug
Tap for the days
TATom Ashby40 h
5 days
£1,200.00
at £30/h
approved
10 Aug
Tap for the days
DKDave Kerr40 h
5 days
£1,400.00
at £35/h
approved
10 Aug
Tap for the days
EREllie Rudd32 h
4 days
£512.00
at £16/h
approved
10 Aug
Tap for the days
TATom Ashby40 h
5 days
£1,200.00
at £30/h
approved
3 Aug
Tap for the days
DKDave Kerr40 h
5 days
£1,400.00
at £35/h
approved
3 Aug
Tap for the days
EREllie Rudd32 h
4 days
£512.00
at £16/h
approved
3 Aug
Tap for the days
SKSam Kerridge16 h
2 days
£352.00
at £22/h
approved
3 Aug
Tap for the days
TATom Ashby40 h
5 days
£1,200.00
at £30/h
approved
Purchases · 4, £42,021
Purchases →
OrderWhatStatusNet
PO-5436
Cotsmoor Flooring Trade, raised 12 Aug
FlooringDelivered 19 Aug, billed£9,976.86
PO-5423
Voltmere Electrical Wholesale, raised 1 Aug
Lighting and electricalDelivered 4 Aug, billed£9,324.96
PO-5419
Kestle Timber, raised 31 Jul
Joinery timber and sheetDelivered 4 Aug, billed£7,593.33
PO-5415
Avonmere Builders Merchants, raised 28 Jul
Partitions, board and ceilingsDelivered 31 Jul, billed£15,125.95
Subcontractor invoices · 4, £29,900
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3715
Andy Rees Electrical, 21 Aug
Electrics and data, second fixPaid£8,970.00
SC-3709
Nick Weller Flooring, 19 Aug
Floor laying, supply-laid by the floor layerPaid£4,480.00
SC-3698
Mark Dent Plastering, 11 Aug
Plastering, skim and making goodPaid£7,480.00
SC-3693
Andy Rees Electrical, 5 Aug
Electrics and data, first fixPaid£8,970.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2370
issued 1 Jul
Deposit
1 line
Paid 23 Jul£25,050.00£28,557.00
£1,253 retention held
posted
INV-2404
issued 12 Aug
Progress
1 line
Paid 14 Sep£50,100.00£57,114.00
£2,505 retention held
posted
INV-2418
issued 28 Aug
Variation
1 line, with V-4005-1
Paid 19 Sep£1,640.00£1,869.60
£82 retention held
posted
INV-2419
issued 28 Aug
Completion (practical completion)
1 line
Paid 4 Oct£25,050.00£28,557.00
£1,253 retention held
posted
Stages £100,200 + billed extras £1,640 = £101,840 on invoices. £101,840 sent, £96,748 paid, £5,092 retention held until the defects period ends.
SL
Saltmarsh Lettings
Contact: Harriet Gane · client since 1 Jun 2026
Site125 Queens Road, Bristol
Phone0117 496 0875
PortalLive: progress, extras, invoices
See what Harriet sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerGareth Price
CrewCrew C: Dave, Tom, Ellie
Booked29 Jun 2026
StartedMon 3 Aug
HandoverFri 23 Oct
Retention5% held to the end of defects
On the schedule
Schedule →
This week and next
Timeline
Andy Rees Electrical: Electrics and data, second fix, £8,970.00
Andy Rees · 21 Aug 17:00
Nick Weller Flooring: Floor laying, supply-laid by the floor layer, £4,480.00
Nick Weller · 19 Aug 17:00
Mark Dent Plastering: Plastering, skim and making good, £7,480.00
Mark Dent · 11 Aug 17:00
Andy Rees Electrical: Electrics and data, first fix, £8,970.00
Andy Rees · 5 Aug 17:00
First day on site: Dave, Ellie, Sam, Tom
Site app · 3 Aug 07:30
Booked: £100,200 ex VAT
Owen · 29 Jun 11:00