Job 4006

Snagging
Kitchen fit-out
For Rosie and Ben Tremlett, Redland. Crew A with Kate Lyons. Started 10 Aug, handover Mon 19 Oct.
Agreed price
£43,900
ex VAT, +£480 extras billed
Margin now
25.7%
quoted 25.9%
100% of the work done30 cabinets
Client's portal view
Job note
One larder door arrived scratched. The replacement is in; Chris fits it on Mon 19 Oct, then the completion invoice goes.
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Live from the site app
Extras captured on site
1 extra on this job
Every extra ↓
Quoted margin25.9%£11,352 on £43,900
Margin now25.7%£11,393 profit on the forecast
Invoiced so far£33,405of £44,380, £33,405 paid
Where the money went
PersonHoursLabour costDifference
SR
Steve Rowe
Lead fitter, crew A, £34/h at cost
120 h
of 120.5 h estimated
£4,080
of £4,097
-£17
LD
Liam Doyle
Joiner, crew A, £30/h at cost
120 h
of 120.5 h estimated
£3,600
of £3,615
-£15
JP
Josh Penrose
Apprentice joiner, crew A, £16/h at cost
96 h
of 76 h estimated
£1,536
of £1,216
+£320
RF
Rob Finch
Decorator, £28/h at cost
24 h
of 27.5 h estimated
£672
of £770
-£98
True labour cost. The 15 kitchens finished this year really took 12.95 h per cabinet, against the old rule of 11.5. This job: 30 cabinets, priced on 344.5 h. Rule of thumb: 11.5 h per cabinet. New quotes now use the true rate →
Cost week by week
£32,987 spent over 5 weeks, against a £32,548 estimate
LabourMaterialsSubcontract
Extras and variations · 1
Variations →
Timesheets · 360 h, £9,888 at cost
Timesheets →
Week ofPersonHoursCostStatus
31 Aug
Tap for the days
RFRob Finch24 h
3 days
£672.00
at £28/h
approved
24 Aug
Tap for the days
JPJosh Penrose32 h
4 days
£512.00
at £16/h
approved
24 Aug
Tap for the days
LDLiam Doyle40 h
5 days
£1,200.00
at £30/h
approved
24 Aug
Tap for the days
SRSteve Rowe40 h
5 days
£1,360.00
at £34/h
approved
17 Aug
Tap for the days
JPJosh Penrose32 h
4 days
£512.00
at £16/h
approved
17 Aug
Tap for the days
LDLiam Doyle40 h
5 days
£1,200.00
at £30/h
approved
17 Aug
Tap for the days
SRSteve Rowe40 h
5 days
£1,360.00
at £34/h
approved
10 Aug
Tap for the days
JPJosh Penrose32 h
4 days
£512.00
at £16/h
approved
10 Aug
Tap for the days
LDLiam Doyle40 h
5 days
£1,200.00
at £30/h
approved
10 Aug
Tap for the days
SRSteve Rowe40 h
5 days
£1,360.00
at £34/h
approved
Purchases · 6, £18,849
Purchases →
OrderWhatStatusNet
PO-5441
Brackwell Tiles, raised 14 Aug
Splashback tiles and adhesiveDelivered 19 Aug, billed£764.06
PO-5442
Halbrook Worktops, raised 14 Aug
Worktops, templated and fittedDelivered 26 Aug, billed£5,040.34
PO-5431
Voltmere Electrical Wholesale, raised 8 Aug
Lighting and electrical fittingsDelivered 11 Aug, billed£759.49
PO-5432
Avonmere Builders Merchants, raised 8 Aug
Plaster, board and sundriesDelivered 11 Aug, billed£741.49
PO-5430
Kestle Timber, raised 7 Aug
Timber, panels and fixingsDelivered 11 Aug, billed£575.78
PO-5398
Wrenfold Kitchen Supply, raised 16 Jul
Kitchen units and doorsDelivered 7 Aug, billed£10,967.82
Subcontractor invoices · 5, £4,250
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3725
Gary Pullen Electrical, 3 Sep
Electrics, second fixPaid£955.00
SC-3726
Jon Haskins Plumbing and Heating, 3 Sep
Plumbing, second fixPaid£700.00
SC-3710
Mark Dent Plastering, 19 Aug
Plastering, skim and making goodPaid£940.00
SC-3702
Jon Haskins Plumbing and Heating, 13 Aug
Plumbing, first fixPaid£700.00
SC-3700
Gary Pullen Electrical, 12 Aug
Electrics, first fixPaid£955.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2371
issued 1 Jul
Deposit
1 line
Paid 6 Jul£10,975.00£13,170.00posted
INV-2412
issued 24 Aug
Progress
1 line
Paid 4 Sep£21,950.00£26,340.00posted
INV-2413
issued 24 Aug
Variation
1 line, with V-4006-1
Paid 7 Sep£480.00£576.00posted
DRAFT-04
goes out 19 Oct
Completion
1 line
Draft, goes out Mon 19 Oct£10,975.00£13,170.00not yet
Stages £43,900 + billed extras £480 = £44,380 on invoices. £33,405 sent, £33,405 paid.
RB
Rosie and Ben Tremlett
Rosie Tremlett · client since 22 Jun 2026
Site31 Belmont Avenue, Redland
Phone07700 900899
PortalLive: progress, extras, invoices
See what Rosie sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewCrew A: Steve, Liam, Josh
Booked29 Jun 2026
StartedMon 10 Aug
HandoverMon 19 Oct
On the schedule
Schedule →
This week and next
Timeline
Gary Pullen Electrical: Electrics, second fix, £955.00
Gary Pullen · 3 Sep 17:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £700.00
Jon Haskins · 3 Sep 17:00
Mark Dent Plastering: Plastering, skim and making good, £940.00
Mark Dent · 19 Aug 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £700.00
Jon Haskins · 13 Aug 17:00
Gary Pullen Electrical: Electrics, first fix, £955.00
Gary Pullen · 12 Aug 17:00
First day on site: Josh, Liam, Steve
Site app · 10 Aug 07:30
Booked: £43,900 ex VAT
Owen · 29 Jun 11:00