Job 4016

Snagging
Bathroom and en-suite
For Julie and Martin Coombs, Keynsham. Crew B with Kate Lyons. Started 7 Sep, handover Mon 19 Oct.
Agreed price
£13,600
ex VAT, +£350 extras billed
Margin now
26.9%
quoted 26.9%
100% of the work done27 m² tiled
Client's portal view
Job note
Silicone touch-ups done. Sign-off visit with the client on Mon 19 Oct.
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Live from the site app
Extras captured on site
1 extra on this job
Every extra ↓
Quoted margin26.9%£3,662 on £13,600
Margin now26.9%£3,757 profit on the forecast
Invoiced so far£10,550of £13,950, £10,550 paid
Where the money went
PersonHoursLabour costDifference
MT
Mike Tanner
Lead fitter and tiler, crew B, £34/h at cost
48 h
of 45.5 h estimated
£1,632
of £1,547
+£85
RH
Ryan Hale
Fitter, crew B, £30/h at cost
40 h
of 39.5 h estimated
£1,200
of £1,185
+£15
CW
Callum Webb
Apprentice fitter, crew B, £16/h at cost
32 h
of 28.5 h estimated
£512
of £456
+£56
True labour cost. The 25 bathrooms finished this year really took 4.5 h per m² tiled, against the old rule of 4.2. This job: 27 m² tiled, priced on 113.5 h. Rule of thumb: 4.2 h per m² tiled. New quotes now use the true rate →
Cost week by week
£10,193 spent over 3 weeks, against a £9,938 estimate
LabourMaterialsSubcontract
Extras and variations · 1
Variations →
Timesheets · 120 h, £3,344 at cost
Timesheets →
Week ofPersonHoursCostStatus
14 Sep
Tap for the days
MTMike Tanner8 h
1 day
£272.00
at £34/h
approved
7 Sep
Tap for the days
CWCallum Webb32 h
4 days
£512.00
at £16/h
approved
7 Sep
Tap for the days
MTMike Tanner40 h
5 days
£1,360.00
at £34/h
approved
7 Sep
Tap for the days
RHRyan Hale40 h
5 days
£1,200.00
at £30/h
approved
Purchases · 5, £4,549
Purchases →
OrderWhatStatusNet
PO-5467
Brackwell Tiles, raised 4 Sep
Wall and floor tiles, adhesive, groutDelivered 9 Sep, billed£1,253.91
PO-5468
Avonmere Builders Merchants, raised 4 Sep
Board, tanking and sundriesDelivered 7 Sep, billed£588.19
PO-5470
Voltmere Electrical Wholesale, raised 4 Sep
Lighting and extractorDelivered 7 Sep, billed£221.85
PO-5466
Kestle Timber, raised 3 Sep
Timber and fixingsDelivered 7 Sep, billed£321.87
PO-5455
Linmouth Bathroom Supply, raised 26 Aug
Sanitaryware and brasswareDelivered 4 Sep, billed£2,162.87
Subcontractor invoices · 5, £2,300
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3742
Jon Haskins Plumbing and Heating, 14 Sep
Plumbing, second fixPaid£715.00
SC-3743
Gary Pullen Electrical, 14 Sep
Electrics, second fixPaid£205.00
SC-3736
Mark Dent Plastering, 9 Sep
Plastering, skim and making goodPaid£460.00
SC-3735
Jon Haskins Plumbing and Heating, 8 Sep
Plumbing, first fixPaid£715.00
SC-3733
Gary Pullen Electrical, 7 Sep
Electrics, first fixPaid£205.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2406
issued 12 Aug
Deposit
1 line
Paid 26 Aug£3,400.00£4,080.00posted
INV-2429
issued 10 Sep
Progress
1 line
Paid 24 Sep£6,800.00£8,160.00posted
INV-2431
issued 14 Sep
Variation
1 line, with V-4016-1
Paid 27 Sep£350.00£420.00posted
DRAFT-05
goes out 19 Oct
Completion
1 line
Draft, goes out Mon 19 Oct£3,400.00£4,080.00not yet
Stages £13,600 + billed extras £350 = £13,950 on invoices. £10,550 sent, £10,550 paid.
JM
Julie and Martin Coombs
Julie Coombs · client since 28 Jul 2026
Site12 Orchard Rise, Keynsham
Phone07700 900813
PortalLive: progress, extras, invoices
See what Julie sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewCrew B: Mike, Ryan, Callum
Booked10 Aug 2026
StartedMon 7 Sep
HandoverMon 19 Oct
On the schedule
Schedule →
This week and next
Timeline
Jon Haskins Plumbing and Heating: Plumbing, second fix, £715.00
Jon Haskins · 14 Sep 17:00
Gary Pullen Electrical: Electrics, second fix, £205.00
Gary Pullen · 14 Sep 17:00
Mark Dent Plastering: Plastering, skim and making good, £460.00
Mark Dent · 9 Sep 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £715.00
Jon Haskins · 8 Sep 17:00
Gary Pullen Electrical: Electrics, first fix, £205.00
Gary Pullen · 7 Sep 17:00
First day on site: Callum, Mike, Ryan
Site app · 7 Sep 07:30
Booked: £13,600 ex VAT
Owen · 10 Aug 11:00