Bathroom · domestic · fixed price

Job 4019

In progressheld
Family bathroom
For Elaine Porter, Frenchay. Crew B with Kate Lyons. Started 21 Sep, handover Fri 6 Nov.
Agreed price
£12,100
ex VAT
Margin now
23.5%
quoted 25.1%
40% of the work done23 m² tiled
Client's portal view
Held
Held at first fix: the wall-hung WC frame has to go in before the walls are boarded, and the client has not signed the variation yet.
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Live from the site app
Extras captured on site
1 extra on this job
Every extra ↓
Quoted margin25.1%£3,037 on £12,100
Margin now23.5%£2,840 profit on the forecast
Invoiced so far£3,025of £12,100, £3,025 paid
Where the money went
PersonHoursLabour costLeft in the estimate
MT
Mike Tanner
Lead fitter and tiler, crew B, £34/h at cost
16 h
of 38.5 h estimated
£544
of £1,309
£765
RH
Ryan Hale
Fitter, crew B, £30/h at cost
16 h
of 34 h estimated
£480
of £1,020
£540
CW
Callum Webb
Apprentice fitter, crew B, £16/h at cost
8 h
of 24 h estimated
£128
of £384
£256
True labour cost. The 25 bathrooms finished this year really took 4.5 h per m² tiled, against the old rule of 4.2. This job: 23 m² tiled, priced on 96.5 h. Rule of thumb: 4.2 h per m² tiled. New quotes now use the true rate →
Cost week by week
£6,752 spent over 4 weeks, against a £9,063 estimate
LabourMaterialsSubcontract
Extras and variations · 1
Variations →
Timesheets · 40 h, £1,152 at cost
Timesheets →
Week ofPersonHoursCostStatus
21 Sep
Tap for the days
CWCallum Webb8 h
1 day
£128.00
at £16/h
approved
21 Sep
Tap for the days
MTMike Tanner16 h
2 days
£544.00
at £34/h
approved
21 Sep
Tap for the days
RHRyan Hale16 h
2 days
£480.00
at £30/h
approved
Purchases · 5, £4,280
Purchases →
OrderWhatStatusNet
PO-5513
Brackwell Tiles, raised 4 Oct
Wall and floor tiles, adhesive, groutDelivered 9 Oct, bill to come£1,166.68
PO-5485
Avonmere Builders Merchants, raised 21 Sep
Board, tanking and sundriesDelivered 24 Sep, billed£541.16
PO-5486
Voltmere Electrical Wholesale, raised 21 Sep
Lighting and extractorDelivered 24 Sep, billed£220.47
PO-5484
Kestle Timber, raised 20 Sep
Timber and fixingsDelivered 24 Sep, billed£295.89
PO-5472
Linmouth Bathroom Supply, raised 9 Sep
Sanitaryware and brasswareDelivered 18 Sep, billed£2,055.95
Subcontractor invoices · 3, £1,320
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3764
Mark Dent Plastering, 9 Oct
Plastering, skim and making goodApproved, in Xero£440.00
SC-3754
Jon Haskins Plumbing and Heating, 30 Sep
Plumbing, first fixApproved, in Xero£680.00
SC-3750
Gary Pullen Electrical, 28 Sep
Electrics, first fixApproved, in Xero£200.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2417
issued 26 Aug
Deposit
1 line
Paid 31 Aug£3,025.00£3,630.00posted
Stages £3,025 + billed extras £0 = £3,025 on invoices. £3,025 sent, £3,025 paid.
EP
Elaine Porter
Elaine Porter · client since 11 Aug 2026
Site3 Linden Close, Frenchay
Phone07700 900930
PortalLive: progress, extras, invoices
See what Elaine sees in the portal
Messages in the portal
A reminder: the wall-hung WC needs your OK before Mike can board the walls. Everything else is ready.
Kate · 13 Oct 09:00
Here is the price for the wall-hung WC and concealed frame. Approve it here and Mike carries on.
Kate · 6 Oct 14:05
People and dates
Project managerKate Lyons
CrewCrew B: Mike, Ryan, Callum
Booked24 Aug 2026
StartedMon 21 Sep
HandoverFri 6 Nov
On the schedule
Schedule →
This week and next
Timeline
Mark Dent Plastering: Plastering, skim and making good, £440.00
Mark Dent · Fri 9 Oct 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £680.00
Jon Haskins · 30 Sep 17:00
Gary Pullen Electrical: Electrics, first fix, £200.00
Gary Pullen · 28 Sep 17:00
First day on site: Callum, Mike, Ryan
Site app · 21 Sep 07:30
Booked: £12,100 ex VAT
Owen · 24 Aug 11:00