Job 4021

Snagging
Bathroom with walk-in shower
For Anna and Will Godwin, Portishead. Crew B with Kate Lyons. Started 28 Sep, handover Fri 16 Oct.
Agreed price
£13,200
ex VAT
Margin now
25.3%
quoted 26.1%
100% of the work done26 m² tiled
Client's portal view
Job note
Fit complete. Waiting for the client to sign the snag list in the portal.
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Live from the site app
Extras captured on site
1 extra on this job
Every extra ↓
Quoted margin26.1%£3,441 on £13,200
Margin now25.3%£3,340 profit on the forecast
Invoiced so far£9,900of £13,200, £9,900 paid
Where the money went
PersonHoursLabour costDifference
MT
Mike Tanner
Lead fitter and tiler, crew B, £34/h at cost
40 h
of 43.5 h estimated
£1,360
of £1,479
-£119
RH
Ryan Hale
Fitter, crew B, £30/h at cost
40 h
of 38 h estimated
£1,200
of £1,140
+£60
CW
Callum Webb
Apprentice fitter, crew B, £16/h at cost
32 h
of 27.5 h estimated
£512
of £440
+£72
True labour cost. The 25 bathrooms finished this year really took 4.5 h per m² tiled, against the old rule of 4.2. This job: 26 m² tiled, priced on 109 h. Rule of thumb: 4.2 h per m² tiled. New quotes now use the true rate →
Cost week by week
£9,860 spent over 2 weeks, against a £9,759 estimate
LabourMaterialsSubcontract
Extras and variations · 1
Variations →
Timesheets · 112 h, £3,072 at cost
Timesheets →
Week ofPersonHoursCostStatus
28 Sep
Tap for the days
CWCallum Webb32 h
4 days
£512.00
at £16/h
approved
28 Sep
Tap for the days
MTMike Tanner40 h
5 days
£1,360.00
at £34/h
approved
28 Sep
Tap for the days
RHRyan Hale40 h
5 days
£1,200.00
at £30/h
approved
Purchases · 5, £4,488
Purchases →
OrderWhatStatusNet
PO-5492
Brackwell Tiles, raised 25 Sep
Wall and floor tiles, adhesive, groutDelivered 30 Sep, billed£1,214.27
PO-5493
Voltmere Electrical Wholesale, raised 25 Sep
Lighting and extractorDelivered 28 Sep, billed£222.54
PO-5495
Avonmere Builders Merchants, raised 25 Sep
Board, tanking and sundriesDelivered 28 Sep, billed£591.60
PO-5490
Kestle Timber, raised 24 Sep
Timber and fixingsDelivered 28 Sep, billed£312.76
PO-5480
Linmouth Bathroom Supply, raised 16 Sep
Sanitaryware and brasswareDelivered 25 Sep, billed£2,147.01
Subcontractor invoices · 5, £2,300
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3757
Jon Haskins Plumbing and Heating, 2 Oct
Plumbing, second fixApproved, in Xero£715.00
SC-3758
Gary Pullen Electrical, 2 Oct
Electrics, second fixApproved, in Xero£205.00
SC-3755
Mark Dent Plastering, 30 Sep
Plastering, skim and making goodApproved, in Xero£460.00
SC-3753
Jon Haskins Plumbing and Heating, 29 Sep
Plumbing, first fixApproved, in Xero£715.00
SC-3751
Gary Pullen Electrical, 28 Sep
Electrics, first fixApproved, in Xero£205.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2422
issued 2 Sep
Deposit
1 line
Paid 10 Sep£3,300.00£3,960.00posted
INV-2441
issued 30 Sep
Progress
1 line
Paid 14 Oct£6,600.00£7,920.00posted
DRAFT-02
goes out 16 Oct
Completion
1 line
Draft, goes out tomorrow£3,300.00£3,960.00not yet
Stages £13,200 + billed extras £0 = £13,200 on invoices. £9,900 sent, £9,900 paid.
AW
Anna and Will Godwin
Anna Godwin · client since 25 Aug 2026
Site40 Meadow View, Portishead
Phone07700 900204
PortalLive: progress, extras, invoices
See what Anna sees in the portal
Messages in the portal
Your snag list is in the portal. Sign it off when you are happy and we will send the completion invoice.
Kate · 5 Oct 17:30
People and dates
Project managerKate Lyons
CrewCrew B: Mike, Ryan, Callum
Booked31 Aug 2026
StartedMon 28 Sep
HandoverFri 16 Oct
On the schedule
Schedule →
This week and next
Timeline
Jon Haskins Plumbing and Heating: Plumbing, second fix, £715.00
Jon Haskins · 2 Oct 17:00
Gary Pullen Electrical: Electrics, second fix, £205.00
Gary Pullen · 2 Oct 17:00
V-4021-1 declined: Client decided against it
Client · 1 Oct 19:30
Mark Dent Plastering: Plastering, skim and making good, £460.00
Mark Dent · 30 Sep 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £715.00
Jon Haskins · 29 Sep 17:00
Gary Pullen Electrical: Electrics, first fix, £205.00
Gary Pullen · 28 Sep 17:00
First day on site: Callum, Mike, Ryan
Site app · 28 Sep 07:30
Booked: £13,200 ex VAT
Owen · 31 Aug 11:00