LIVE DEMO
Shop · commercial · fixed price

Job 4022

In progress
Shop refit
For Wyvern Cycles, Bristol. Crew C with Gareth Price. Started 5 Oct, handover Fri 20 Nov.
Agreed price
£34,200
ex VAT
Margin now
19.4%
quoted 21.0%
10% of the work done120 m² floor
Client's portal view
Job note
Strip-out done and the electrician has started first fix. Crew C starts on Mon 26 Oct.
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Live from the site app
Quoted margin21.0%£7,169 on £34,200
Margin now19.4%£6,652 profit on the forecast
Invoiced so far£8,550of £34,200, £8,123 paid, £428 retention held
Where the money went
PersonHoursLabour costLeft in the estimate
SK
Sam Kerridge
Labourer and driver, £22/h at cost
24 h
of 12 h estimated
£528
of £264
+£264 over
DK
Dave Kerr
Lead fitter, crew C, £35/h at cost
0 h
of 39.5 h estimated
£0
of £1,383
£1,383
TA
Tom Ashby
Joiner, crew C, £30/h at cost
0 h
of 39.5 h estimated
£0
of £1,185
£1,185
ER
Ellie Rudd
Apprentice joiner, crew C, £16/h at cost
0 h
of 29 h estimated
£0
of £464
£464
RF
Rob Finch
Decorator, £28/h at cost
0 h
of 12 h estimated
£0
of £336
£336
Cost week by week
£15,170 spent over 3 weeks, against a £27,032 estimate
LabourMaterialsSubcontract
Extras and variations · 0
Variations →
No extras on this job.
Timesheets · 24 h, £528 at cost
Timesheets →
Week ofPersonHoursCostStatus
12 Oct
Tap for the days
SKSam Kerridge8 h
1 day
£176.00
at £22/h
submitted, approve Fri
5 Oct
Tap for the days
SKSam Kerridge16 h
2 days
£352.00
at £22/h
approved
Purchases · 4, £14,752
Purchases →
OrderWhatStatusNet
PO-5539
Cotsmoor Flooring Trade, raised 14 Oct
FlooringOn order, due 12 Nov£2,899.85
PO-5516
Voltmere Electrical Wholesale, raised 5 Oct
Lighting and electricalDelivered 8 Oct, billed£3,266.73
PO-5512
Kestle Timber, raised 4 Oct
Shopfitting timber and sheetDelivered 8 Oct, bill to come£4,090.09
PO-5500
Avonmere Builders Merchants, raised 29 Sep
Partitions, board and ceilingsDelivered 2 Oct, billed£4,495.24
Subcontractor invoices · 1, £2,790
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3769
Andy Rees Electrical, 12 Oct
Electrics and lighting, first fixApproved, in Xero£2,790.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2423
issued 2 Sep
Deposit
1 line
Paid 24 Sep£8,550.00£9,747.00
£428 retention held
posted
Stages £8,550 + billed extras £0 = £8,550 on invoices. £8,550 sent, £8,123 paid, £428 retention held until the defects period ends.
WC
Wyvern Cycles
Contact: Jenny Ellison · client since 28 Aug 2026
Site14 East Street, Bristol
Phone0117 496 0474
PortalLive: progress, extras, invoices
See what Jenny sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerGareth Price
CrewCrew C: Dave, Tom, Ellie
Booked31 Aug 2026
StartedMon 5 Oct
HandoverFri 20 Nov
Retention5% held to the end of defects
On the schedule
Schedule →
This week and next
Timeline
Andy Rees Electrical: Electrics and lighting, first fix, £2,790.00
Andy Rees · Mon 12 Oct 17:00
First day on site: Sam
Site app · 5 Oct 07:30
Booked: £34,200 ex VAT
Owen · 31 Aug 11:00