LIVE DEMO
Bathroom · domestic · fixed price

Job 4024

In progresslosing margin
Family bathroom
For Ruth and Colin Emery, Downend. Crew B with Kate Lyons. Started 5 Oct, handover Fri 23 Oct.
Agreed price
£10,350
ex VAT
Margin now
16.4%
quoted 23.5%
40% of the work done18 m² tiled
Losing margin
Quoted at 23.5%, 16.4% now. Stripped out and first fix done. The wall tiles came in a different batch shade and 9 m² were re-ordered; labour is running well ahead of the work done. Tiling from Fri 16 Oct.
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Live from the site app
Quoted margin23.5%£2,431 on £10,350
Margin now16.4%£1,701 with the extras not billed
With the extras billed18.7%£1,991 profit
Where the money went
PersonHoursLabour costLeft in the estimate
MT
Mike Tanner
Lead fitter and tiler, crew B, £34/h at cost
24 h
of 30 h estimated
£816
of £1,020
£204
CW
Callum Webb
Apprentice fitter, crew B, £16/h at cost
16 h
of 19 h estimated
£256
of £304
£48
RH
Ryan Hale
Fitter, crew B, £30/h at cost
0 h
of 26.5 h estimated
£0
of £795
£795
True labour cost. The 25 bathrooms finished this year really took 4.5 h per m² tiled, against the old rule of 4.2. This job: 18 m² tiled, priced on 75.5 h. Rule of thumb: 4.2 h per m² tiled. New quotes now use the true rate →
Cost week by week
£6,558 spent over 3 weeks, against a £7,919 estimate
LabourMaterialsSubcontract
Extras and variations · 1
Variations →
Timesheets · 40 h, £1,072 at cost
Timesheets →
Week ofPersonHoursCostStatus
5 Oct
Tap for the days
CWCallum Webb16 h
2 days
£256.00
at £16/h
approved
5 Oct
Tap for the days
MTMike Tanner24 h
3 days
£816.00
at £34/h
approved
Purchases · 5, £4,256
Purchases →
OrderWhatStatusNet
PO-5521
Brackwell Tiles, raised 8 Oct
Wall and floor tiles, adhesive, groutDelivered 13 Oct, bill to come£1,129.75
PO-5506
Avonmere Builders Merchants, raised 3 Oct
Board, tanking and sundriesDelivered 6 Oct, bill to come£580.28
PO-5508
Voltmere Electrical Wholesale, raised 3 Oct
Lighting and extractorDelivered 6 Oct, bill to come£216.78
PO-5505
Kestle Timber, raised 2 Oct
Timber and fixingsDelivered 6 Oct, billed£299.25
PO-5489
Linmouth Bathroom Supply, raised 23 Sep
Sanitaryware and brasswareDelivered 2 Oct, billed£2,029.87
Subcontractor invoices · 3, £1,230
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3772
Mark Dent Plastering, 13 Oct
Plastering, skim and making goodApproved, in Xero£410.00
SC-3761
Jon Haskins Plumbing and Heating, 8 Oct
Plumbing, first fixApproved, in Xero£635.00
SC-3759
Gary Pullen Electrical, 7 Oct
Electrics, first fixApproved, in Xero£185.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2428
issued 9 Sep
Deposit
1 line
Paid 22 Sep£2,587.50£3,105.00posted
Stages £2,588 + billed extras £0 = £2,588 on invoices. £2,588 sent, £2,588 paid.
RC
Ruth and Colin Emery
Ruth Emery · client since 1 Sep 2026
Site15 Woodside Road, Downend
Phone07700 900368
PortalLive: progress, extras, invoices
See what Ruth sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewCrew B: Mike, Ryan, Callum
Booked7 Sep 2026
StartedMon 5 Oct
HandoverFri 23 Oct
On the schedule
Schedule →
This week and next
Timeline
Mark Dent Plastering: Plastering, skim and making good, £410.00
Mark Dent · Tue 13 Oct 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £635.00
Jon Haskins · 8 Oct 17:00
Gary Pullen Electrical: Electrics, first fix, £185.00
Gary Pullen · 7 Oct 17:00
First day on site: Callum, Mike
Site app · 5 Oct 07:30
Booked: £10,350 ex VAT
Owen · 7 Sep 11:00