LIVE DEMO
Bathroom · domestic · fixed price

Job 4027

In progress
Bathroom refit
For Jane and Simon Cottle, Southville. Crew B with Kate Lyons. Started 12 Oct, handover Fri 23 Oct.
Agreed price
£13,100
ex VAT
Margin now
22.8%
quoted 24.1%
55% of the work done27 m² tiled
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Live from the site app
Extras captured on site
1 extra on this job
Every extra ↓
Quoted margin24.1%£3,162 on £13,100
Margin now22.8%£2,983 profit on the forecast
Invoiced so far£9,825of £13,100, £3,275 paid
Where the money went
PersonHoursLabour costLeft in the estimate
MT
Mike Tanner
Lead fitter and tiler, crew B, £34/h at cost
24 h
of 45.5 h estimated
£816
of £1,547
£731
RH
Ryan Hale
Fitter, crew B, £30/h at cost
24 h
of 39.5 h estimated
£720
of £1,185
£465
CW
Callum Webb
Apprentice fitter, crew B, £16/h at cost
16 h
of 28.5 h estimated
£256
of £456
£200
True labour cost. The 25 bathrooms finished this year really took 4.5 h per m² tiled, against the old rule of 4.2. This job: 27 m² tiled, priced on 113.5 h. Rule of thumb: 4.2 h per m² tiled. New quotes now use the true rate →
Ryan Hale was on site longer than his timesheet says
Wed 14 Oct: clocked 07:29 to 16:44, on site 8.75 h, logged 8 h
Job cost understated by £22.50
Cost week by week
£6,079 spent over 2 weeks, against a £9,938 estimate
LabourMaterialsSubcontract
Extras and variations · 1
Variations →
Timesheets · 64 h, £1,792 at cost
Timesheets →
Week ofPersonHoursCostStatus
12 Oct
Tap for the days
CWCallum Webb16 h
2 days
£256.00
at £16/h
submitted, approve Fri
12 Oct
Tap for the days
MTMike Tanner24 h
3 days
£816.00
at £34/h
submitted, approve Fri
12 Oct
Tap for the days
RHRyan Hale24 h
3 days
£720.00
at £30/h
submitted, approve Fri
Purchases · 5, £4,591
Purchases →
OrderWhatStatusNet
PO-5531
Brackwell Tiles, raised 11 Oct
Wall and floor tiles, adhesive, groutOn order, due 16 Oct£1,224.29
PO-5525
Avonmere Builders Merchants, raised 10 Oct
Board, tanking and sundriesDelivered 13 Oct, bill to come£587.68
PO-5528
Voltmere Electrical Wholesale, raised 10 Oct
Lighting and extractorDelivered 13 Oct, bill to come£226.27
PO-5524
Kestle Timber, raised 9 Oct
Timber and fixingsDelivered 13 Oct, bill to come£320.42
PO-5502
Linmouth Bathroom Supply, raised 30 Sep
Sanitaryware and brasswareDelivered 9 Oct, bill to come£2,232.16
Subcontractor invoices · 2, £920
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3775
Jon Haskins Plumbing and Heating, 14 Oct
Plumbing, first fixApproved, in Xero£715.00
SC-3773
Gary Pullen Electrical, 13 Oct
Electrics, first fixApproved, in Xero£205.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2433
issued 16 Sep
Deposit
1 line
Paid 2 Oct£3,275.00£3,930.00posted
INV-2453
issued 14 Oct
Progress
1 line
Sent, due 28 Oct£6,550.00£7,860.00posted
Stages £9,825 + billed extras £0 = £9,825 on invoices. £9,825 sent, £3,275 paid.
JS
Jane and Simon Cottle
Jane Cottle · client since 8 Sep 2026
Site27 Mill Lane, Southville
Phone07700 900863
PortalLive: progress, extras, invoices
See what Jane sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewCrew B: Mike, Ryan, Callum
Booked14 Sep 2026
StartedMon 12 Oct
HandoverFri 23 Oct
On the schedule
Schedule →
This week and next
Timeline
Jon Haskins Plumbing and Heating: Plumbing, first fix, £715.00
Jon Haskins · Yesterday 17:00
Gary Pullen Electrical: Electrics, first fix, £205.00
Gary Pullen · Tue 13 Oct 17:00
First day on site: Callum, Mike, Ryan
Site app · Mon 12 Oct 07:30
Booked: £13,100 ex VAT
Owen · 14 Sep 11:00