Bathroom · domestic · fixed price

Job 4029

In progress
Cloakroom and utility refit
For Victoria Kemp, Totterdown. Chris Moss (small works) with Kate Lyons. Started 7 Oct, handover Thu 22 Oct.
Agreed price
£9,900
ex VAT
Margin now
30.0%
quoted 30.9%
75% of the work done7 m²
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Live from the site app
Quoted margin30.9%£3,058 on £9,900
Margin now30.0%£2,972 profit on the forecast
Invoiced so far£7,425of £9,900, £2,475 paid
Where the money went
PersonHoursLabour costLeft in the estimate
CM
Chris Moss
Small works and snagging fitter, £30/h at cost
32 h
of 33.5 h estimated
£960
of £1,005
£45
SK
Sam Kerridge
Labourer and driver, £22/h at cost
0 h
of 8.5 h estimated
£0
of £187
£187
Rule of thumb: 6 h per m².
Cost week by week
£5,930 spent over 2 weeks, against a £6,842 estimate
LabourMaterialsSubcontract
Extras and variations · 0
Variations →
No extras on this job.
Timesheets · 32 h, £960 at cost
Timesheets →
Week ofPersonHoursCostStatus
12 Oct
Tap for the days
CMChris Moss8 h
1 day
£240.00
at £30/h
submitted, approve Fri
5 Oct
Tap for the days
CMChris Moss24 h
3 days
£720.00
at £30/h
approved
Purchases · 4, £4,270
Purchases →
OrderWhatStatusNet
PO-5522
Brackwell Tiles, raised 8 Oct
Tiles and adhesiveDelivered 13 Oct, bill to come£638.19
PO-5517
Avonmere Builders Merchants, raised 5 Oct
Board and sundriesDelivered 8 Oct, bill to come£420.44
PO-5497
Linmouth Bathroom Supply, raised 27 Sep
Sanitaryware and brasswareDelivered 6 Oct, bill to come£2,155.35
PO-5491
Wrenfold Kitchen Supply, raised 24 Sep
Utility unitsDelivered 8 Oct, billed£1,056.36
Subcontractor invoices · 2, £700
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3766
Jon Haskins Plumbing and Heating, 9 Oct
Plumbing, first fixApproved, in Xero£525.00
SC-3762
Gary Pullen Electrical, 8 Oct
Electrics, first fixApproved, in Xero£175.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2437
issued 25 Sep
Deposit
1 line
Paid 2 Oct£2,475.00£2,970.00posted
INV-2455
issued 14 Oct
Progress
1 line
Sent, due 28 Oct£4,950.00£5,940.00posted
Stages £7,425 + billed extras £0 = £7,425 on invoices. £7,425 sent, £2,475 paid.
VK
Victoria Kemp
Victoria Kemp · client since 17 Sep 2026
Site5 Hawthorn Way, Totterdown
Phone07700 900112
PortalLive: progress, extras, invoices
See what Victoria sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewChris Moss, small works
Booked23 Sep 2026
StartedWed 7 Oct
HandoverThu 22 Oct
On the schedule
Schedule →
This week and next
Timeline
Jon Haskins Plumbing and Heating: Plumbing, first fix, £525.00
Jon Haskins · Fri 9 Oct 17:00
Gary Pullen Electrical: Electrics, first fix, £175.00
Gary Pullen · 8 Oct 17:00
First day on site: Chris
Site app · 7 Oct 07:30
Booked: £9,900 ex VAT
Owen · 23 Sep 11:00