Bathroom · domestic · fixed price

Job 4039

Booked
En-suite shower room
For Beth and Alex Gulliver, Cotham. Crew B with Kate Lyons. Booked 12 Oct, starts Mon 16 Nov.
Agreed price
£9,250
ex VAT
Margin now
26.6%
quoted 26.7%
Not started13 m² tiled
Client's portal view
Estimate against actual
Nothing spent yet: the estimate is what it was priced on
Quoted margin26.7%£2,466 on £9,250
Margin now26.6%£2,464 profit on the forecast
Invoiced so far£2,313of £9,250, £0 paid
Where the money went
PersonHoursLabour costLeft in the estimate
MT
Mike Tanner
Lead fitter and tiler, crew B, £34/h at cost
0 h
of 22 h estimated
£0
of £748
£748
RH
Ryan Hale
Fitter, crew B, £30/h at cost
0 h
of 19 h estimated
£0
of £570
£570
CW
Callum Webb
Apprentice fitter, crew B, £16/h at cost
0 h
of 13.5 h estimated
£0
of £216
£216
True labour cost. The 25 bathrooms finished this year really took 4.5 h per m² tiled, against the old rule of 4.2. This job: 13 m² tiled, priced on 54.5 h. Rule of thumb: 4.2 h per m² tiled. New quotes now use the true rate →
Cost week by week
Nothing spent yet
LabourMaterialsSubcontract
No costs yet
Crew time and deliveries start on Mon 16 Nov.
Extras and variations · 0
Variations →
No extras on this job yet. The crew captures any on the site app, with the client's signature.
Timesheets · 0 h, £0 at cost
Timesheets →
No hours logged yet. The crew clock on to the job in the site app from Mon 16 Nov.
Purchases · 1, £1,612
Purchases →
OrderWhatStatusNet
PO-5542
Linmouth Bathroom Supply, raised 14 Oct
Sanitaryware and brasswareOn order, due 13 Nov£1,612.34
Subcontractor invoices · 0, £0
Tap one for the subcontractor
No subcontractor invoices yet.
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2456
issued 14 Oct
Deposit
1 line
Sent, due 28 Oct£2,312.50£2,775.00posted
Stages £2,313 + billed extras £0 = £2,313 on invoices. £2,313 sent, £0 paid.
BA
Beth and Alex Gulliver
Beth Gulliver · client since 6 Oct 2026
Site6 Hawthorn Way, Cotham
Phone07700 900125
PortalLive: progress, extras, invoices
See what Beth sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewCrew B: Mike, Ryan, Callum
Booked12 Oct 2026
StartsMon 16 Nov
HandoverThu 19 Nov
On the schedule
Schedule →
This week and next
Timeline
Booked: £9,250 ex VAT
Owen · Mon 12 Oct 11:00