Bathroom and en-suite
For Ruth and Dominic Sparrow, Totterdown. Crew B with Kate Lyons. On site 29 Jan to 2 Feb, handed over 7 Feb 2026.
Agreed price
£8,900
ex VAT
Final margin
18.0%
quoted 23.8%
100% of the work done13 m² tiled
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Quoted margin23.8%£2,116 on £8,900
Final margin18.0%£1,605 profit
Invoiced so far£8,900of £8,900, £8,900 paid
Where the money went
PersonHoursLabour costDifference
MT
Mike Tanner
Lead fitter and tiler, crew B, £34/h at cost
24 h
of 22 h estimated
£816
of £748
+£68
RH
Ryan Hale
Fitter, crew B, £30/h at cost
24 h
of 19 h estimated
£720
of £570
+£150
CW
Callum Webb
Apprentice fitter, crew B, £16/h at cost
24 h
of 13.5 h estimated
£384
of £216
+£168
True labour cost. The 25 bathrooms finished this year really took 4.5 h per m² tiled, against the old rule of 4.2. This job: 13 m² tiled, priced on 54.5 h. Rule of thumb: 4.2 h per m² tiled. New quotes now use the true rate →
Cost week by week
£7,295 spent over 2 weeks, against a £6,784 estimate
LabourMaterialsSubcontract
Extras and variations · 0
Variations →
No extras on this job.
Timesheets · 72 h, £1,920 at cost
Timesheets →
Week ofPersonHoursCostStatus
2 Feb
Tap for the days
CWCallum Webb8 h
1 day
£128.00
at £16/h
approved
from the paper sheets
2 Feb
Tap for the days
MTMike Tanner8 h
1 day
£272.00
at £34/h
approved
from the paper sheets
2 Feb
Tap for the days
RHRyan Hale8 h
1 day
£240.00
at £30/h
approved
from the paper sheets
26 Jan
Tap for the days
CWCallum Webb16 h
2 days
£256.00
at £16/h
approved
from the paper sheets
26 Jan
Tap for the days
MTMike Tanner16 h
2 days
£544.00
at £34/h
approved
from the paper sheets
26 Jan
Tap for the days
RHRyan Hale16 h
2 days
£480.00
at £30/h
approved
from the paper sheets
Purchases · 5, £3,475
Purchases →
OrderWhatStatusNet
PO-5153
Voltmere Electrical Wholesale, raised 26 Jan
Lighting and extractorDelivered 29 Jan, billed£183.59
PO-5154
Avonmere Builders Merchants, raised 26 Jan
Board, tanking and sundriesDelivered 29 Jan, billed£475.71
PO-5148
Kestle Timber, raised 25 Jan
Timber and fixingsDelivered 29 Jan, billed£239.10
PO-5149
Brackwell Tiles, raised 25 Jan
Wall and floor tiles, adhesive, groutDelivered 30 Jan, billed£930.91
PO-5140
Linmouth Bathroom Supply, raised 19 Jan
Sanitaryware and brasswareDelivered 28 Jan, billed£1,645.69
Subcontractor invoices · 5, £1,900
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3445
Jon Haskins Plumbing and Heating, 2 Feb
Plumbing, second fixPaid£590.00
SC-3446
Gary Pullen Electrical, 2 Feb
Electrics, second fixPaid£170.00
SC-3441
Mark Dent Plastering, 30 Jan
Plastering, skim and making goodPaid£380.00
SC-3439
Jon Haskins Plumbing and Heating, 29 Jan
Plumbing, first fixPaid£590.00
SC-3440
Gary Pullen Electrical, 29 Jan
Electrics, first fixPaid£170.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2210
issued 25 Dec 2025
Deposit
1 line
Paid 1 Jan£2,225.00£2,670.00posted
INV-2239
issued 2 Feb
Progress
1 line
Paid 11 Feb£4,450.00£5,340.00posted
INV-2245
issued 9 Feb
Completion
1 line
Paid 19 Feb£2,225.00£2,670.00posted
Stages £8,900 + billed extras £0 = £8,900 on invoices. £8,900 sent, £8,900 paid.
RD
Ruth and Dominic Sparrow
Ruth Sparrow · client since 30 Nov 2025
Site76 Grange Road, Totterdown
Phone07700 900455
PortalLive: progress, extras, invoices
See what Ruth sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewCrew B: Mike, Ryan, Callum
Booked23 Dec 2025
StartedThu 29 Jan
Handed over7 Feb 2026
Timeline
Handed over and closed
Kate · 7 Feb 15:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £590.00
Jon Haskins · 2 Feb 17:00
Gary Pullen Electrical: Electrics, second fix, £170.00
Gary Pullen · 2 Feb 17:00
Mark Dent Plastering: Plastering, skim and making good, £380.00
Mark Dent · 30 Jan 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £590.00
Jon Haskins · 29 Jan 17:00
Gary Pullen Electrical: Electrics, first fix, £170.00
Gary Pullen · 29 Jan 17:00
First day on site: Callum, Mike, Ryan
Site app · 29 Jan 07:30
Booked: £8,900 ex VAT