Kitchen · domestic · fixed price
Job 3952
CompleteKitchen fit-out
For Amanda and James Pocock, Cotham. Crew A with Kate Lyons. On site 18 Feb to 26 Feb, handed over 4 Mar 2026.
Agreed price
£20,300
ex VAT
Final margin
20.7%
quoted 25.7%
100% of the work done13 cabinets
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
CostEstimateActual so farFinalDifference
Labour168 h logged against 150 h estimated, at each person's true cost rate£4,224£4,672£4,672+£44810.6% overMaterials6 purchases received£8,050£8,620£8,620+£5707.1% overSubcontract5 invoices from the electrician, plumber and plasterer£2,800£2,800£2,800On budgetTotal cost£15,074£16,092£16,092+£1,0186.8% overQuoted margin25.7%£5,226 on £20,300
Final margin20.7%£4,208 profit
Invoiced so far£20,300of £20,300, £20,300 paid
Where the money went
| Person | Hours | Labour cost | Difference |
|---|---|---|---|
SR Steve Rowe Lead fitter, crew A, £34/h at cost | 56 h of 52.5 h estimated | £1,904 of £1,785 | +£119 |
LD Liam Doyle Joiner, crew A, £30/h at cost | 56 h of 52.5 h estimated | £1,680 of £1,575 | +£105 |
JP Josh Penrose Apprentice joiner, crew A, £16/h at cost | 40 h of 33 h estimated | £640 of £528 | +£112 |
RF Rob Finch Decorator, £28/h at cost | 16 h of 12 h estimated | £448 of £336 | +£112 |
True labour cost. The 15 kitchens finished this year really took 12.95 h per cabinet, against the old rule of 11.5. This job: 13 cabinets, priced on 150 h. Rule of thumb: 11.5 h per cabinet. New quotes now use the true rate →
| Estimate line | Estimate | Ordered | Received | Difference |
|---|---|---|---|---|
Kitchen units and doors Wrenfold Kitchen Supply, PO-5150 | £4,670 | £5,053 | £5,053 | +£383 |
Worktops, templated and fitted Halbrook Worktops, PO-5175 | £2,170 | £2,265 | £2,265 | +£95 |
Plaster, board and sundries Avonmere Builders Merchants, PO-5182 | £320 | £353 | £353 | +£33 |
Timber, panels and fixings Kestle Timber, PO-5178 | £240 | £255 | £255 | +£15 |
Lighting and electrical fittings Voltmere Electrical Wholesale, PO-5184 | £320 | £342 | £342 | +£22 |
Splashback tiles and adhesive Brackwell Tiles, PO-5183 | £330 | £352 | £352 | +£22 |
Materials count when they are delivered and signed for on site. Nothing is on order and not received. Supplier bills post to Xero from here.
| Trade | Agreed | Invoiced | Difference |
|---|---|---|---|
Electrics Gary Pullen Electrical, 2 invoices | £1,260 | £1,260 | on the agreed price |
Plumbing Jon Haskins Plumbing and Heating, 2 invoices | £920 | £920 | on the agreed price |
Plastering Mark Dent Plastering, 1 invoice | £620 | £620 | on the agreed price |
The forecast counts each trade at its agreed price until it invoices more.
Agreed price
stage invoices at 25%, 50% and 25%
£20,300.00
Revenue
£20,300.00
Labour
final
- £4,672.00
Materials
final
- £8,619.54
Subcontract
final
- £2,800.00
Profit
20.7% margin, quoted at 25.7% (£5,226)
£4,208.46
Cost week by week
£16,092 spent over 2 weeks, against a £15,074 estimate
LabourMaterialsSubcontract
| Week of | Hours | Labour | Materials | Subcontract | Total |
|---|---|---|---|---|---|
| 16 Feb | 64 h | £1,792 | £6,355 | £1,710 | £9,857 |
| 23 Feb | 104 h | £2,880 | £2,265 | £1,090 | £6,235 |
Extras and variations · 0
Variations →No extras on this job.
Timesheets · 168 h, £4,672 at cost
Timesheets →| Week of | Person | Hours | Cost | Status |
|---|---|---|---|---|
| 23 Feb Tap for the days Mon 23 Feb8 hTS-00247 Tue 24 Feb8 hTS-00252 Thu 26 Feb8 hTS-00260 | JPJosh Penrose | 24 h 3 days | £384.00 at £16/h | approved from the paper sheets |
| 23 Feb Tap for the days Mon 23 Feb8 hTS-00248 Tue 24 Feb8 hTS-00253 Wed 25 Feb8 hTS-00256 Thu 26 Feb8 hTS-00261 | LDLiam Doyle | 32 h 4 days | £960.00 at £30/h | approved from the paper sheets |
| 23 Feb Tap for the days Wed 25 Feb8 hTS-00257 Thu 26 Feb8 hTS-00263 | RFRob Finch | 16 h 2 days | £448.00 at £28/h | approved from the paper sheets |
| 23 Feb Tap for the days Mon 23 Feb8 hTS-00250 Tue 24 Feb8 hTS-00255 Wed 25 Feb8 hTS-00258 Thu 26 Feb8 hTS-00265 | SRSteve Rowe | 32 h 4 days | £1,088.00 at £34/h | approved from the paper sheets |
| 16 Feb Tap for the days Thu 19 Feb8 hTS-00231 Fri 20 Feb8 hTS-00240 | JPJosh Penrose | 16 h 2 days | £256.00 at £16/h | approved from the paper sheets |
| 16 Feb Tap for the days Wed 18 Feb8 hTS-00221 Thu 19 Feb8 hTS-00232 Fri 20 Feb8 hTS-00241 | LDLiam Doyle | 24 h 3 days | £720.00 at £30/h | approved from the paper sheets |
| 16 Feb Tap for the days Wed 18 Feb8 hTS-00225 Thu 19 Feb8 hTS-00235 Fri 20 Feb8 hTS-00242 | SRSteve Rowe | 24 h 3 days | £816.00 at £34/h | approved from the paper sheets |
Purchases · 6, £8,620
Purchases →| Order | What | Status | Net |
|---|---|---|---|
| PO-5182 Avonmere Builders Merchants, raised 15 Feb | Plaster, board and sundries | Delivered 18 Feb, billed | £352.81 |
| PO-5183 Brackwell Tiles, raised 15 Feb | Splashback tiles and adhesive | Delivered 20 Feb, billed | £351.64 |
| PO-5184 Voltmere Electrical Wholesale, raised 15 Feb | Lighting and electrical fittings | Delivered 18 Feb, billed | £341.95 |
| PO-5178 Kestle Timber, raised 14 Feb | Timber, panels and fixings | Delivered 18 Feb, billed | £255.18 |
| PO-5175 Halbrook Worktops, raised 12 Feb | Worktops, templated and fitted | Delivered 24 Feb, billed | £2,264.77 |
| PO-5150 Wrenfold Kitchen Supply, raised 26 Jan | Kitchen units and doors | Delivered 17 Feb, billed | £5,053.19 |
Subcontractor invoices · 5, £2,800
Tap one for the subcontractor| Invoice | Work | Status | Amount |
|---|---|---|---|
| SC-3475 Gary Pullen Electrical, 26 Feb | Electrics, second fix | Paid | £630.00 |
Gary Pullen ElectricalElectrician, Kingswood. Day rate £260. Insured to Mar 2027. Domestic jobs. Part P registered. | |||
| SC-3476 Jon Haskins Plumbing and Heating, 26 Feb | Plumbing, second fix | Paid | £460.00 |
Jon Haskins Plumbing and HeatingPlumber, Bedminster. Day rate £250. Insured to May 2027. Gas Safe registered. | |||
| SC-3471 Mark Dent Plastering, 20 Feb | Plastering, skim and making good | Paid | £620.00 |
Mark Dent PlasteringPlasterer, Brislington. Day rate £220. Insured to Feb 2027. Skim and dry-lining. | |||
| SC-3467 Gary Pullen Electrical, 19 Feb | Electrics, first fix | Paid | £630.00 |
Gary Pullen ElectricalElectrician, Kingswood. Day rate £260. Insured to Mar 2027. Domestic jobs. Part P registered. | |||
| SC-3468 Jon Haskins Plumbing and Heating, 19 Feb | Plumbing, first fix | Paid | £460.00 |
Jon Haskins Plumbing and HeatingPlumber, Bedminster. Day rate £250. Insured to May 2027. Gas Safe registered. | |||
Invoices · posted to Xero when sent
Billing →| Invoice | Stage | Status | Net | Gross | Xero |
|---|---|---|---|---|---|
| INV-2212 issued 2 Jan | Deposit 1 line | Paid 17 Jan | £5,075.00 | £6,090.00 | posted |
| INV-2256 issued 23 Feb | Progress 1 line | Paid 7 Mar | £10,150.00 | £12,180.00 | posted |
| INV-2264 issued 5 Mar | Completion 1 line | Paid 21 Mar | £5,075.00 | £6,090.00 | posted |
Stages £20,300 + billed extras £0 = £20,300 on invoices. £20,300 sent, £20,300 paid.
Client
Client page →Amanda and James Pocock
Amanda Pocock · client since 20 Dec 2025
Site54 Church Lane, Cotham
Phone07700 900846
PortalLive: progress, extras, invoices
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewCrew A: Steve, Liam, Josh
Booked30 Dec 2025
StartedWed 18 Feb
Handed over4 Mar 2026
Timeline
Handed over and closed
Kate · 4 Mar 15:00
Gary Pullen Electrical: Electrics, second fix, £630.00
Gary Pullen · 26 Feb 17:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £460.00
Jon Haskins · 26 Feb 17:00
Delivered: Worktops, templated and fitted from Halbrook Worktops (PO-5175, £2,264.77)
Steve Rowe · 24 Feb 08:15
Mark Dent Plastering: Plastering, skim and making good, £620.00
Mark Dent · 20 Feb 17:00
Delivered: Splashback tiles and adhesive from Brackwell Tiles (PO-5183, £351.64)
Steve Rowe · 20 Feb 08:15
Gary Pullen Electrical: Electrics, first fix, £630.00
Gary Pullen · 19 Feb 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £460.00
Jon Haskins · 19 Feb 17:00
Delivered: Timber, panels and fixings from Kestle Timber (PO-5178, £255.18)
Steve Rowe · 18 Feb 08:15
Delivered: Plaster, board and sundries from Avonmere Builders Merchants (PO-5182, £352.81)
Steve Rowe · 18 Feb 08:15
Delivered: Lighting and electrical fittings from Voltmere Electrical Wholesale (PO-5184, £341.95)
Steve Rowe · 18 Feb 08:15
First day on site: Liam, Steve
Site app · 18 Feb 07:30
Delivered: Kitchen units and doors from Wrenfold Kitchen Supply (PO-5150, £5,053.19)
Steve Rowe · 17 Feb 08:15
Booked: £20,300 ex VAT
Owen · 30 Dec 2025 11:00