Kitchen · domestic · fixed price
Job 3959
CompleteKitchen fit-out
For Lisa Gazzard, Saltford. Crew A with Kate Lyons. On site 11 Mar to 24 Mar, handed over 29 Mar 2026.
Agreed price
£25,450
ex VAT, +£1,700 extras billed
Final margin
24.5%
quoted 24.5%
100% of the work done17 cabinets
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
CostEstimateActual so farFinalDifference
Labour216 h logged against 195.5 h estimated, at each person's true cost rate£5,506£5,952£5,952+£4468.1% overMaterials6 purchases received£10,550£11,399£11,399+£8498.0% overSubcontract5 invoices from the electrician, plumber and plasterer£3,150£3,150£3,150On budgetTotal cost£19,206£20,501£20,501+£1,2956.7% overExtras captured on site
1 extra on this job
Quoted margin24.5%£6,244 on £25,450
Final margin24.5%£6,649 profit
Invoiced so far£27,150of £27,150, £27,150 paid
Where the money went
| Person | Hours | Labour cost | Difference |
|---|---|---|---|
SR Steve Rowe Lead fitter, crew A, £34/h at cost | 72 h of 68.5 h estimated | £2,448 of £2,329 | +£119 |
LD Liam Doyle Joiner, crew A, £30/h at cost | 72 h of 68.5 h estimated | £2,160 of £2,055 | +£105 |
JP Josh Penrose Apprentice joiner, crew A, £16/h at cost | 56 h of 43 h estimated | £896 of £688 | +£208 |
RF Rob Finch Decorator, £28/h at cost | 16 h of 15.5 h estimated | £448 of £434 | +£14 |
True labour cost. The 15 kitchens finished this year really took 12.95 h per cabinet, against the old rule of 11.5. This job: 17 cabinets, priced on 195.5 h. Rule of thumb: 11.5 h per cabinet. New quotes now use the true rate →
| Estimate line | Estimate | Ordered | Received | Difference |
|---|---|---|---|---|
Kitchen units and doors Wrenfold Kitchen Supply, PO-5187 | £6,120 | £6,526 | £6,526 | +£406 |
Worktops, templated and fitted Halbrook Worktops, PO-5212 | £2,850 | £3,129 | £3,129 | +£279 |
Plaster, board and sundries Avonmere Builders Merchants, PO-5215 | £420 | £464 | £464 | +£44 |
Timber, panels and fixings Kestle Timber, PO-5210 | £320 | £346 | £346 | +£26 |
Lighting and electrical fittings Voltmere Electrical Wholesale, PO-5214 | £420 | £465 | £465 | +£45 |
Splashback tiles and adhesive Brackwell Tiles, PO-5217 | £420 | £469 | £469 | +£49 |
Materials count when they are delivered and signed for on site. Nothing is on order and not received. Supplier bills post to Xero from here.
| Trade | Agreed | Invoiced | Difference |
|---|---|---|---|
Electrics Gary Pullen Electrical, 2 invoices | £1,420 | £1,420 | on the agreed price |
Plumbing Jon Haskins Plumbing and Heating, 2 invoices | £1,040 | £1,040 | on the agreed price |
Plastering Mark Dent Plastering, 1 invoice | £690 | £690 | on the agreed price |
The forecast counts each trade at its agreed price until it invoices more.
Agreed price
stage invoices at 25%, 50% and 25%
£25,450.00
Extras billed
V-3959-1
£1,700.00
Revenue
£27,150.00
Labour
final
- £5,952.00
Materials
final
- £11,398.69
Subcontract
final
- £3,150.00
Profit
24.5% margin, quoted at 24.5% (£6,244)
£6,649.31
Cost week by week
£20,501 spent over 3 weeks, against a £19,206 estimate
LabourMaterialsSubcontract
| Week of | Hours | Labour | Materials | Subcontract | Total |
|---|---|---|---|---|---|
| 9 Mar | 64 h | £1,792 | £7,801 | £1,230 | £10,823 |
| 16 Mar | 112 h | £3,072 | £3,598 | £690 | £7,360 |
| 23 Mar | 40 h | £1,088 | £0 | £1,230 | £2,318 |
Extras and variations · 1
Variations →Timesheets · 216 h, £5,952 at cost
Timesheets →| Week of | Person | Hours | Cost | Status |
|---|---|---|---|---|
| 23 Mar Tap for the days Mon 23 Mar8 hTS-00387 | JPJosh Penrose | 8 h 1 day | £128.00 at £16/h | approved from the paper sheets |
| 23 Mar Tap for the days Mon 23 Mar8 hTS-00388 | LDLiam Doyle | 8 h 1 day | £240.00 at £30/h | approved from the paper sheets |
| 23 Mar Tap for the days Mon 23 Mar8 hTS-00390 Tue 24 Mar8 hTS-00395 | RFRob Finch | 16 h 2 days | £448.00 at £28/h | approved from the paper sheets |
| 23 Mar Tap for the days Mon 23 Mar8 hTS-00392 | SRSteve Rowe | 8 h 1 day | £272.00 at £34/h | approved from the paper sheets |
| 16 Mar Tap for the days Mon 16 Mar8 hTS-00349 Tue 17 Mar8 hTS-00356 Thu 19 Mar8 hTS-00369 Fri 20 Mar8 hTS-00378 | JPJosh Penrose | 32 h 4 days | £512.00 at £16/h | approved from the paper sheets |
| 16 Mar Tap for the days Mon 16 Mar8 hTS-00350 Tue 17 Mar8 hTS-00357 Wed 18 Mar8 hTS-00361 Thu 19 Mar8 hTS-00370 Fri 20 Mar8 hTS-00379 | LDLiam Doyle | 40 h 5 days | £1,200.00 at £30/h | approved from the paper sheets |
| 16 Mar Tap for the days Mon 16 Mar8 hTS-00352 Tue 17 Mar8 hTS-00358 Wed 18 Mar8 hTS-00364 Thu 19 Mar8 hTS-00373 Fri 20 Mar8 hTS-00382 | SRSteve Rowe | 40 h 5 days | £1,360.00 at £34/h | approved from the paper sheets |
| 9 Mar Tap for the days Thu 12 Mar8 hTS-00332 Fri 13 Mar8 hTS-00340 | JPJosh Penrose | 16 h 2 days | £256.00 at £16/h | approved from the paper sheets |
| 9 Mar Tap for the days Wed 11 Mar8 hTS-00326 Thu 12 Mar8 hTS-00333 Fri 13 Mar8 hTS-00341 | LDLiam Doyle | 24 h 3 days | £720.00 at £30/h | approved from the paper sheets |
| 9 Mar Tap for the days Wed 11 Mar8 hTS-00330 Thu 12 Mar8 hTS-00336 Fri 13 Mar8 hTS-00345 | SRSteve Rowe | 24 h 3 days | £816.00 at £34/h | approved from the paper sheets |
Purchases · 6, £11,399
Purchases →| Order | What | Status | Net |
|---|---|---|---|
| PO-5217 Brackwell Tiles, raised 12 Mar | Splashback tiles and adhesive | Delivered 17 Mar, billed | £469.27 |
| PO-5214 Voltmere Electrical Wholesale, raised 9 Mar | Lighting and electrical fittings | Delivered 12 Mar, billed | £464.97 |
| PO-5215 Avonmere Builders Merchants, raised 9 Mar | Plaster, board and sundries | Delivered 12 Mar, billed | £463.55 |
| PO-5210 Kestle Timber, raised 8 Mar | Timber, panels and fixings | Delivered 12 Mar, billed | £345.84 |
| PO-5212 Halbrook Worktops, raised 8 Mar | Worktops, templated and fitted | Delivered 20 Mar, billed | £3,128.62 |
| PO-5187 Wrenfold Kitchen Supply, raised 16 Feb | Kitchen units and doors | Delivered 10 Mar, billed | £6,526.44 |
Subcontractor invoices · 5, £3,150
Tap one for the subcontractor| Invoice | Work | Status | Amount |
|---|---|---|---|
| SC-3510 Gary Pullen Electrical, 24 Mar | Electrics, second fix | Paid | £710.00 |
Gary Pullen ElectricalElectrician, Kingswood. Day rate £260. Insured to Mar 2027. Domestic jobs. Part P registered. | |||
| SC-3511 Jon Haskins Plumbing and Heating, 24 Mar | Plumbing, second fix | Paid | £520.00 |
Jon Haskins Plumbing and HeatingPlumber, Bedminster. Day rate £250. Insured to May 2027. Gas Safe registered. | |||
| SC-3503 Mark Dent Plastering, 17 Mar | Plastering, skim and making good | Paid | £690.00 |
Mark Dent PlasteringPlasterer, Brislington. Day rate £220. Insured to Feb 2027. Skim and dry-lining. | |||
| SC-3499 Jon Haskins Plumbing and Heating, 13 Mar | Plumbing, first fix | Paid | £520.00 |
Jon Haskins Plumbing and HeatingPlumber, Bedminster. Day rate £250. Insured to May 2027. Gas Safe registered. | |||
| SC-3498 Gary Pullen Electrical, 12 Mar | Electrics, first fix | Paid | £710.00 |
Gary Pullen ElectricalElectrician, Kingswood. Day rate £260. Insured to Mar 2027. Domestic jobs. Part P registered. | |||
Invoices · posted to Xero when sent
Billing →| Invoice | Stage | Status | Net | Gross | Xero |
|---|---|---|---|---|---|
| INV-2229 issued 22 Jan | Deposit 1 line | Paid 4 Feb | £6,362.50 | £7,635.00 | posted |
| INV-2276 issued 17 Mar | Progress 1 line | Paid 2 Apr | £12,725.00 | £15,270.00 | posted |
| INV-2284 issued 30 Mar | Completion 2 lines, with V-3959-1 | Paid 10 Apr | £8,062.50 | £9,675.00 | posted |
Stages £25,450 + billed extras £1,700 = £27,150 on invoices. £27,150 sent, £27,150 paid.
Client
Client page →Lisa Gazzard
Lisa Gazzard · client since 10 Jan 2026
Site9 Linden Close, Saltford
Phone07700 900654
PortalLive: progress, extras, invoices
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewCrew A: Steve, Liam, Josh
Booked20 Jan 2026
StartedWed 11 Mar
Handed over29 Mar 2026
Timeline
Handed over and closed
Kate · 29 Mar 15:00
Gary Pullen Electrical: Electrics, second fix, £710.00
Gary Pullen · 24 Mar 17:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £520.00
Jon Haskins · 24 Mar 17:00
Delivered: Worktops, templated and fitted from Halbrook Worktops (PO-5212, £3,128.62)
Steve Rowe · 20 Mar 08:15
V-3959-1 approved by the client (email), £1,700
Client · 17 Mar 19:00
Mark Dent Plastering: Plastering, skim and making good, £690.00
Mark Dent · 17 Mar 17:00
Delivered: Splashback tiles and adhesive from Brackwell Tiles (PO-5217, £469.27)
Steve Rowe · 17 Mar 08:15
Extra captured: Extra wall unit and filler
Steve · 16 Mar 11:30
Jon Haskins Plumbing and Heating: Plumbing, first fix, £520.00
Jon Haskins · 13 Mar 17:00
Gary Pullen Electrical: Electrics, first fix, £710.00
Gary Pullen · 12 Mar 17:00
Delivered: Timber, panels and fixings from Kestle Timber (PO-5210, £345.84)
Steve Rowe · 12 Mar 08:15
Delivered: Lighting and electrical fittings from Voltmere Electrical Wholesale (PO-5214, £464.97)
Steve Rowe · 12 Mar 08:15
Delivered: Plaster, board and sundries from Avonmere Builders Merchants (PO-5215, £463.55)
Steve Rowe · 12 Mar 08:15
First day on site: Liam, Steve
Site app · 11 Mar 07:30
Delivered: Kitchen units and doors from Wrenfold Kitchen Supply (PO-5187, £6,526.44)
Steve Rowe · 10 Mar 08:15
Booked: £25,450 ex VAT
Owen · 20 Jan 11:00