Job 3989

Complete
Kitchen and utility fit-out
For Elaine and Graham Naish, Bedminster. Crew A with Kate Lyons. On site 25 Jun to 2 Jul, handed over 5 Jul 2026.
Agreed price
£18,300
ex VAT, +£1,140 extras billed
Final margin
28.7%
quoted 23.2%
100% of the work done12 cabinets
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Extras captured on site
1 extra on this job
Every extra ↓
Quoted margin23.2%£4,250 on £18,300
Final margin28.7%£5,584 profit
Invoiced so far£19,440of £19,440, £19,440 paid
Where the money went
PersonHoursLabour costDifference
SR
Steve Rowe
Lead fitter, crew A, £34/h at cost
48 h
of 48.5 h estimated
£1,632
of £1,649
-£17
LD
Liam Doyle
Joiner, crew A, £30/h at cost
48 h
of 48.5 h estimated
£1,440
of £1,455
-£15
JP
Josh Penrose
Apprentice joiner, crew A, £16/h at cost
40 h
of 30.5 h estimated
£640
of £488
+£152
RF
Rob Finch
Decorator, £28/h at cost
8 h
of 11 h estimated
£224
of £308
-£84
True labour cost. The 15 kitchens finished this year really took 12.95 h per cabinet, against the old rule of 11.5. This job: 12 cabinets, priced on 138.5 h. Rule of thumb: 11.5 h per cabinet. New quotes now use the true rate →
Cost week by week
£13,856 spent over 2 weeks, against a £14,050 estimate
LabourMaterialsSubcontract
Extras and variations · 1
Variations →
Timesheets · 144 h, £3,936 at cost
Timesheets →
Week ofPersonHoursCostStatus
29 Jun
Tap for the days
JPJosh Penrose24 h
3 days
£384.00
at £16/h
approved
29 Jun
Tap for the days
LDLiam Doyle32 h
4 days
£960.00
at £30/h
approved
29 Jun
Tap for the days
RFRob Finch8 h
1 day
£224.00
at £28/h
approved
29 Jun
Tap for the days
SRSteve Rowe32 h
4 days
£1,088.00
at £34/h
approved
22 Jun
Tap for the days
JPJosh Penrose16 h
2 days
£256.00
at £16/h
approved
22 Jun
Tap for the days
LDLiam Doyle16 h
2 days
£480.00
at £30/h
approved
22 Jun
Tap for the days
SRSteve Rowe16 h
2 days
£544.00
at £34/h
approved
Purchases · 6, £7,220
Purchases →
OrderWhatStatusNet
PO-5364
Brackwell Tiles, raised 24 Jun
Splashback tiles and adhesiveDelivered 29 Jun, billed£286.28
PO-5358
Voltmere Electrical Wholesale, raised 22 Jun
Lighting and electrical fittingsDelivered 25 Jun, billed£289.92
PO-5360
Avonmere Builders Merchants, raised 22 Jun
Plaster, board and sundriesDelivered 25 Jun, billed£296.14
PO-5356
Kestle Timber, raised 21 Jun
Timber, panels and fixingsDelivered 25 Jun, billed£212.20
PO-5354
Halbrook Worktops, raised 19 Jun
Worktops, templated and fittedDelivered 1 Jul, billed£1,975.01
PO-5327
Wrenfold Kitchen Supply, raised 2 Jun
Kitchen units and doorsDelivered 24 Jun, billed£4,160.03
Subcontractor invoices · 5, £2,700
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3646
Gary Pullen Electrical, 2 Jul
Electrics, second fixPaid£610.00
SC-3647
Jon Haskins Plumbing and Heating, 2 Jul
Plumbing, second fixPaid£445.00
SC-3638
Mark Dent Plastering, 29 Jun
Plastering, skim and making goodPaid£590.00
SC-3636
Jon Haskins Plumbing and Heating, 26 Jun
Plumbing, first fixPaid£445.00
SC-3635
Gary Pullen Electrical, 25 Jun
Electrics, first fixPaid£610.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2320
issued 11 May
Deposit
1 line
Paid 24 May£4,575.00£5,490.00posted
INV-2364
issued 29 Jun
Progress
1 line
Paid 12 Jul£9,150.00£10,980.00posted
INV-2374
issued 6 Jul
Completion
2 lines, with V-3989-1
Paid 17 Jul£5,715.00£6,858.00posted
Stages £18,300 + billed extras £1,140 = £19,440 on invoices. £19,440 sent, £19,440 paid.
EG
Elaine and Graham Naish
Elaine Naish · client since 26 Apr 2026
Site95 Grange Road, Bedminster
Phone07700 900859
PortalLive: progress, extras, invoices
See what Elaine sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewCrew A: Steve, Liam, Josh
Booked8 May 2026
StartedThu 25 Jun
Handed over5 Jul 2026
Timeline
Handed over and closed
Kate · 5 Jul 15:00
Gary Pullen Electrical: Electrics, second fix, £610.00
Gary Pullen · 2 Jul 17:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £445.00
Jon Haskins · 2 Jul 17:00
Mark Dent Plastering: Plastering, skim and making good, £590.00
Mark Dent · 29 Jun 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £445.00
Jon Haskins · 26 Jun 17:00
Gary Pullen Electrical: Electrics, first fix, £610.00
Gary Pullen · 25 Jun 17:00
First day on site: Josh, Liam, Steve
Site app · 25 Jun 07:30
Booked: £18,300 ex VAT
Owen · 8 May 11:00