Complete
Kitchen fit-out
For Simon Blake, Clevedon. Crew A with Kate Lyons. On site 8 Jul to 16 Jul, handed over 21 Jul 2026.
Agreed price
£19,650
ex VAT
Final margin
22.2%
quoted 23.3%
100% of the work done13 cabinets
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Quoted margin23.3%£4,576 on £19,650
Final margin22.2%£4,356 profit
Invoiced so far£19,650of £19,650, £19,650 paid
Where the money went
PersonHoursLabour costDifference
SR
Steve Rowe
Lead fitter, crew A, £34/h at cost
56 h
of 52.5 h estimated
£1,904
of £1,785
+£119
LD
Liam Doyle
Joiner, crew A, £30/h at cost
56 h
of 52.5 h estimated
£1,680
of £1,575
+£105
JP
Josh Penrose
Apprentice joiner, crew A, £16/h at cost
40 h
of 33 h estimated
£640
of £528
+£112
RF
Rob Finch
Decorator, £28/h at cost
16 h
of 12 h estimated
£448
of £336
+£112
True labour cost. The 15 kitchens finished this year really took 12.95 h per cabinet, against the old rule of 11.5. This job: 13 cabinets, priced on 150 h. Rule of thumb: 11.5 h per cabinet. New quotes now use the true rate →
Cost week by week
£15,294 spent over 2 weeks, against a £15,074 estimate
LabourMaterialsSubcontract
Extras and variations · 0
Variations →
No extras on this job.
Timesheets · 168 h, £4,672 at cost
Timesheets →
Week ofPersonHoursCostStatus
13 Jul
Tap for the days
JPJosh Penrose24 h
3 days
£384.00
at £16/h
approved
13 Jul
Tap for the days
LDLiam Doyle32 h
4 days
£960.00
at £30/h
approved
13 Jul
Tap for the days
RFRob Finch16 h
2 days
£448.00
at £28/h
approved
13 Jul
Tap for the days
SRSteve Rowe32 h
4 days
£1,088.00
at £34/h
approved
6 Jul
Tap for the days
JPJosh Penrose16 h
2 days
£256.00
at £16/h
approved
6 Jul
Tap for the days
LDLiam Doyle24 h
3 days
£720.00
at £30/h
approved
6 Jul
Tap for the days
SRSteve Rowe24 h
3 days
£816.00
at £34/h
approved
Purchases · 6, £7,822
Purchases →
OrderWhatStatusNet
PO-5378
Avonmere Builders Merchants, raised 5 Jul
Plaster, board and sundriesDelivered 8 Jul, billed£304.26
PO-5379
Brackwell Tiles, raised 5 Jul
Splashback tiles and adhesiveDelivered 10 Jul, billed£325.60
PO-5383
Voltmere Electrical Wholesale, raised 5 Jul
Lighting and electrical fittingsDelivered 8 Jul, billed£317.85
PO-5376
Kestle Timber, raised 4 Jul
Timber, panels and fixingsDelivered 8 Jul, billed£234.31
PO-5374
Halbrook Worktops, raised 2 Jul
Worktops, templated and fittedDelivered 14 Jul, billed£2,074.81
PO-5349
Wrenfold Kitchen Supply, raised 15 Jun
Kitchen units and doorsDelivered 7 Jul, billed£4,565.38
Subcontractor invoices · 5, £2,800
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3665
Gary Pullen Electrical, 16 Jul
Electrics, second fixPaid£630.00
SC-3666
Jon Haskins Plumbing and Heating, 16 Jul
Plumbing, second fixPaid£460.00
SC-3659
Mark Dent Plastering, 10 Jul
Plastering, skim and making goodPaid£620.00
SC-3655
Gary Pullen Electrical, 9 Jul
Electrics, first fixPaid£630.00
SC-3656
Jon Haskins Plumbing and Heating, 9 Jul
Plumbing, first fixPaid£460.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2333
issued 29 May
Deposit
1 line
Paid 7 Jun£4,912.50£5,895.00posted
INV-2379
issued 13 Jul
Progress
1 line
Paid 26 Jul£9,825.00£11,790.00posted
INV-2388
issued 22 Jul
Completion
1 line
Paid 30 Jul£4,912.50£5,895.00posted
Stages £19,650 + billed extras £0 = £19,650 on invoices. £19,650 sent, £19,650 paid.
SB
Simon Blake
Simon Blake · client since 9 May 2026
Site60 Park Avenue, Clevedon
Phone07700 900849
PortalLive: progress, extras, invoices
See what Simon sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewCrew A: Steve, Liam, Josh
Booked27 May 2026
StartedWed 8 Jul
Handed over21 Jul 2026
Timeline
Handed over and closed
Kate · 21 Jul 15:00
Gary Pullen Electrical: Electrics, second fix, £630.00
Gary Pullen · 16 Jul 17:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £460.00
Jon Haskins · 16 Jul 17:00
Mark Dent Plastering: Plastering, skim and making good, £620.00
Mark Dent · 10 Jul 17:00
Gary Pullen Electrical: Electrics, first fix, £630.00
Gary Pullen · 9 Jul 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £460.00
Jon Haskins · 9 Jul 17:00
First day on site: Liam, Steve
Site app · 8 Jul 07:30
Booked: £19,650 ex VAT