Bathroom · domestic · fixed price

Job 4003

Complete
En-suite shower room
For Louise Bevan, Knowle. Crew B with Kate Lyons. On site 27 Jul to 29 Jul, handed over 4 Aug 2026.
Agreed price
£9,700
ex VAT
Final margin
26.2%
quoted 25.6%
100% of the work done15 m² tiled
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Quoted margin25.6%£2,484 on £9,700
Final margin26.2%£2,537 profit
Invoiced so far£9,700of £9,700, £9,700 paid
Where the money went
PersonHoursLabour costDifference
MT
Mike Tanner
Lead fitter and tiler, crew B, £34/h at cost
24 h
of 25 h estimated
£816
of £850
-£34
RH
Ryan Hale
Fitter, crew B, £30/h at cost
24 h
of 22 h estimated
£720
of £660
+£60
CW
Callum Webb
Apprentice fitter, crew B, £16/h at cost
16 h
of 16 h estimated
£256
of £256
on budget
True labour cost. The 25 bathrooms finished this year really took 4.5 h per m² tiled, against the old rule of 4.2. This job: 15 m² tiled, priced on 63 h. Rule of thumb: 4.2 h per m² tiled. New quotes now use the true rate →
Cost week by week
£7,163 spent over 2 weeks, against a £7,216 estimate
LabourMaterialsSubcontract
Extras and variations · 0
Variations →
No extras on this job.
Timesheets · 64 h, £1,792 at cost
Timesheets →
Week ofPersonHoursCostStatus
27 Jul
Tap for the days
CWCallum Webb16 h
2 days
£256.00
at £16/h
approved
27 Jul
Tap for the days
MTMike Tanner24 h
3 days
£816.00
at £34/h
approved
27 Jul
Tap for the days
RHRyan Hale24 h
3 days
£720.00
at £30/h
approved
Purchases · 5, £3,421
Purchases →
OrderWhatStatusNet
PO-5411
Avonmere Builders Merchants, raised 24 Jul
Board, tanking and sundriesDelivered 27 Jul, billed£439.89
PO-5413
Voltmere Electrical Wholesale, raised 24 Jul
Lighting and extractorDelivered 27 Jul, billed£178.55
PO-5408
Brackwell Tiles, raised 23 Jul
Wall and floor tiles, adhesive, groutDelivered 28 Jul, billed£930.96
PO-5409
Kestle Timber, raised 23 Jul
Timber and fixingsDelivered 27 Jul, billed£227.15
PO-5393
Linmouth Bathroom Supply, raised 15 Jul
Sanitaryware and brasswareDelivered 24 Jul, billed£1,644.56
Subcontractor invoices · 5, £1,950
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3684
Jon Haskins Plumbing and Heating, 29 Jul
Plumbing, second fixPaid£605.00
SC-3685
Gary Pullen Electrical, 29 Jul
Electrics, second fixPaid£175.00
SC-3681
Mark Dent Plastering, 28 Jul
Plastering, skim and making goodPaid£390.00
SC-3679
Jon Haskins Plumbing and Heating, 27 Jul
Plumbing, first fixPaid£605.00
SC-3680
Gary Pullen Electrical, 27 Jul
Electrics, first fixPaid£175.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2362
issued 26 Jun
Deposit
1 line
Paid 5 Jul£2,425.00£2,910.00posted
INV-2395
issued 28 Jul
Progress
1 line
Paid 13 Aug£4,850.00£5,820.00posted
INV-2400
issued 5 Aug
Completion
1 line
Paid 18 Aug£2,425.00£2,910.00posted
Stages £9,700 + billed extras £0 = £9,700 on invoices. £9,700 sent, £9,700 paid.
LB
Louise Bevan
Louise Bevan · client since 28 May 2026
Site59 Ashgrove Road, Knowle
Phone07700 900252
PortalLive: progress, extras, invoices
See what Louise sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewCrew B: Mike, Ryan, Callum
Booked24 Jun 2026
StartedMon 27 Jul
Handed over4 Aug 2026
Timeline
Handed over and closed
Kate · 4 Aug 15:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £605.00
Jon Haskins · 29 Jul 17:00
Gary Pullen Electrical: Electrics, second fix, £175.00
Gary Pullen · 29 Jul 17:00
Mark Dent Plastering: Plastering, skim and making good, £390.00
Mark Dent · 28 Jul 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £605.00
Jon Haskins · 27 Jul 17:00
Gary Pullen Electrical: Electrics, first fix, £175.00
Gary Pullen · 27 Jul 17:00
First day on site: Callum, Mike, Ryan
Site app · 27 Jul 07:30
Booked: £9,700 ex VAT
Owen · 24 Jun 11:00