Bathroom · domestic · fixed price

Job 4013

Complete
Bathroom with walk-in shower
For Karen and Henry Winter, Totterdown. Crew B with Kate Lyons. On site 1 Sep to 4 Sep, handed over 11 Sep 2026.
Agreed price
£11,650
ex VAT, +£660 extras billed
Final margin
30.0%
quoted 24.5%
100% of the work done22 m² tiled
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Extras captured on site
1 extra on this job
Every extra ↓
Quoted margin24.5%£2,849 on £11,650
Final margin30.0%£3,696 profit
Invoiced so far£12,310of £12,310, £8,738 paid
Where the money went
PersonHoursLabour costDifference
MT
Mike Tanner
Lead fitter and tiler, crew B, £34/h at cost
32 h
of 37 h estimated
£1,088
of £1,258
-£170
RH
Ryan Hale
Fitter, crew B, £30/h at cost
32 h
of 32.5 h estimated
£960
of £975
-£15
CW
Callum Webb
Apprentice fitter, crew B, £16/h at cost
24 h
of 23 h estimated
£384
of £368
+£16
True labour cost. The 25 bathrooms finished this year really took 4.5 h per m² tiled, against the old rule of 4.2. This job: 22 m² tiled, priced on 92.5 h. Rule of thumb: 4.2 h per m² tiled. New quotes now use the true rate →
Cost week by week
£8,614 spent over 2 weeks, against a £8,801 estimate
LabourMaterialsSubcontract
Extras and variations · 1
Variations →
Timesheets · 88 h, £2,432 at cost
Timesheets →
Week ofPersonHoursCostStatus
31 Aug
Tap for the days
CWCallum Webb24 h
3 days
£384.00
at £16/h
approved
31 Aug
Tap for the days
MTMike Tanner32 h
4 days
£1,088.00
at £34/h
approved
31 Aug
Tap for the days
RHRyan Hale32 h
4 days
£960.00
at £30/h
approved
Purchases · 5, £4,032
Purchases →
OrderWhatStatusNet
PO-5460
Avonmere Builders Merchants, raised 29 Aug
Board, tanking and sundriesDelivered 1 Sep, billed£512.96
PO-5461
Voltmere Electrical Wholesale, raised 29 Aug
Lighting and extractorDelivered 1 Sep, billed£201.12
PO-5458
Brackwell Tiles, raised 28 Aug
Wall and floor tiles, adhesive, groutDelivered 2 Sep, billed£1,095.53
PO-5459
Kestle Timber, raised 28 Aug
Timber and fixingsDelivered 1 Sep, billed£282.13
PO-5448
Linmouth Bathroom Supply, raised 19 Aug
Sanitaryware and brasswareDelivered 28 Aug, billed£1,940.54
Subcontractor invoices · 5, £2,150
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3729
Jon Haskins Plumbing and Heating, 4 Sep
Plumbing, second fixPaid£665.00
SC-3730
Gary Pullen Electrical, 4 Sep
Electrics, second fixPaid£195.00
SC-3724
Mark Dent Plastering, 2 Sep
Plastering, skim and making goodPaid£430.00
SC-3722
Jon Haskins Plumbing and Heating, 1 Sep
Plumbing, first fixPaid£665.00
SC-3723
Gary Pullen Electrical, 1 Sep
Electrics, first fixPaid£195.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2394
issued 27 Jul
Deposit
1 line
Paid 8 Aug£2,912.50£3,495.00posted
INV-2421
issued 2 Sep
Progress
1 line
Paid 17 Sep£5,825.00£6,990.00posted
INV-2430
issued 14 Sep
Completion
2 lines, with V-4013-1
Overdue since 28 Sep£3,572.50£4,287.00posted
Stages £11,650 + billed extras £660 = £12,310 on invoices. £12,310 sent, £8,738 paid.
KH
Karen and Henry Winter
Karen Winter · client since 3 Jul 2026
Site95 Hollybush Lane, Totterdown
Phone07700 900390
PortalLive: progress, extras, invoices
See what Karen sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewCrew B: Mike, Ryan, Callum
Booked25 Jul 2026
StartedTue 1 Sep
Handed over11 Sep 2026
Timeline
Handed over and closed
Kate · 11 Sep 15:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £665.00
Jon Haskins · 4 Sep 17:00
Gary Pullen Electrical: Electrics, second fix, £195.00
Gary Pullen · 4 Sep 17:00
Mark Dent Plastering: Plastering, skim and making good, £430.00
Mark Dent · 2 Sep 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £665.00
Jon Haskins · 1 Sep 17:00
Gary Pullen Electrical: Electrics, first fix, £195.00
Gary Pullen · 1 Sep 17:00
First day on site: Callum, Mike, Ryan
Site app · 1 Sep 07:30
Booked: £11,650 ex VAT
Owen · 25 Jul 11:00