LIVE DEMO
Kitchen · domestic · fixed price

Job 4015

Complete
Kitchen worktop replacement
For Beth Iles, Henleaze. Chris Moss (small works) with Kate Lyons. On site 19 Aug to 25 Aug, handed over 3 Sep 2026.
Agreed price
£10,550
ex VAT
Final margin
24.5%
quoted 28.5%
100% of the work done11 cabinets
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Quoted margin28.5%£3,002 on £10,550
Final margin24.5%£2,582 profit
Invoiced so far£10,550of £10,550, £10,550 paid
Where the money went
PersonHoursLabour costDifference
CM
Chris Moss
Small works and snagging fitter, £30/h at cost
40 h
of 35 h estimated
£1,200
of £1,050
+£150
SK
Sam Kerridge
Labourer and driver, £22/h at cost
8 h
of 9 h estimated
£176
of £198
-£22
Rule of thumb: 4 h per cabinet.
Cost week by week
£7,968 spent over 2 weeks, against a £7,548 estimate
LabourMaterialsSubcontract
Extras and variations · 0
Variations →
No extras on this job.
Timesheets · 48 h, £1,376 at cost
Timesheets →
Week ofPersonHoursCostStatus
24 Aug
Tap for the days
CMChris Moss16 h
2 days
£480.00
at £30/h
approved
17 Aug
Tap for the days
CMChris Moss24 h
3 days
£720.00
at £30/h
approved
17 Aug
Tap for the days
SKSam Kerridge8 h
1 day
£176.00
at £22/h
approved
Purchases · 3, £5,992
Purchases →
OrderWhatStatusNet
PO-5445
Avonmere Builders Merchants, raised 16 Aug
SundriesDelivered 19 Aug, billed£291.53
PO-5438
Halbrook Worktops, raised 12 Aug
Worktops, templated and fittedDelivered 24 Aug, billed£3,332.93
PO-5424
Wrenfold Kitchen Supply, raised 1 Aug
Replacement doors and panelsDelivered 19 Aug, billed£2,367.06
Subcontractor invoices · 2, £600
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3719
Jon Haskins Plumbing and Heating, 25 Aug
Plumbing, second fixPaid£300.00
SC-3713
Jon Haskins Plumbing and Heating, 20 Aug
Plumbing, first fixPaid£300.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2398
issued 3 Aug
Deposit
1 line
Paid 18 Aug£2,637.50£3,165.00posted
INV-2414
issued 24 Aug
Progress
1 line
Paid 31 Aug£5,275.00£6,330.00posted
INV-2424
issued 4 Sep
Completion
1 line
Paid 9 Sep£2,637.50£3,165.00posted
Stages £10,550 + billed extras £0 = £10,550 on invoices. £10,550 sent, £10,550 paid.
BI
Beth Iles
Beth Iles · client since 20 Jun 2026
Site9 Orchard Rise, Henleaze
Phone07700 900676
PortalLive: progress, extras, invoices
See what Beth sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewChris Moss, small works
Booked31 Jul 2026
StartedWed 19 Aug
Handed over3 Sep 2026
Timeline
Handed over and closed
Kate · 3 Sep 15:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £300.00
Jon Haskins · 25 Aug 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £300.00
Jon Haskins · 20 Aug 17:00
First day on site: Chris, Sam
Site app · 19 Aug 07:30
Booked: £10,550 ex VAT
Owen · 31 Jul 11:00