Kitchen · domestic · fixed price

Job 4026

Complete
Kitchen worktop replacement
For Lucy and Jonathan Urch, Downend. Chris Moss (small works) with Kate Lyons. On site 28 Sep to 30 Sep, handed over 9 Oct 2026.
Agreed price
£8,100
ex VAT
Final margin
30.3%
quoted 30.1%
100% of the work done8 cabinets
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Quoted margin30.1%£2,442 on £8,100
Final margin30.3%£2,455 profit
Invoiced so far£8,100of £8,100, £6,075 paid
Where the money went
PersonHoursLabour costDifference
CM
Chris Moss
Small works and snagging fitter, £30/h at cost
24 h
of 25.5 h estimated
£720
of £765
-£45
SK
Sam Kerridge
Labourer and driver, £22/h at cost
8 h
of 6.5 h estimated
£176
of £143
+£33
Rule of thumb: 4 h per cabinet.
Cost week by week
£5,645 spent over 1 week, against a £5,658 estimate
LabourMaterialsSubcontract
Extras and variations · 0
Variations →
No extras on this job.
Timesheets · 32 h, £896 at cost
Timesheets →
Week ofPersonHoursCostStatus
28 Sep
Tap for the days
CMChris Moss24 h
3 days
£720.00
at £30/h
approved
28 Sep
Tap for the days
SKSam Kerridge8 h
1 day
£176.00
at £22/h
approved
Purchases · 3, £4,149
Purchases →
OrderWhatStatusNet
PO-5494
Avonmere Builders Merchants, raised 25 Sep
SundriesDelivered 28 Sep, billed£216.10
PO-5481
Halbrook Worktops, raised 18 Sep
Worktops, templated and fittedDelivered 30 Sep, billed£2,271.97
PO-5475
Wrenfold Kitchen Supply, raised 12 Sep
Replacement doors and panelsDelivered 28 Sep, billed£1,660.89
Subcontractor invoices · 2, £600
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3756
Jon Haskins Plumbing and Heating, 30 Sep
Plumbing, second fixApproved, in Xero£300.00
SC-3752
Jon Haskins Plumbing and Heating, 28 Sep
Plumbing, first fixApproved, in Xero£300.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2432
issued 14 Sep
Deposit
1 line
Paid 29 Sep£2,025.00£2,430.00posted
INV-2440
issued 29 Sep
Progress
1 line
Paid 4 Oct£4,050.00£4,860.00posted
INV-2449
issued 12 Oct
Completion
1 line
Sent, due 26 Oct£2,025.00£2,430.00posted
Stages £8,100 + billed extras £0 = £8,100 on invoices. £8,100 sent, £6,075 paid.
LJ
Lucy and Jonathan Urch
Lucy Urch · client since 30 Jul 2026
Site62 Belmont Avenue, Downend
Phone07700 900662
PortalLive: progress, extras, invoices
See what Lucy sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewChris Moss, small works
Booked11 Sep 2026
StartedMon 28 Sep
Handed over9 Oct 2026
Timeline
Handed over and closed
Kate · Fri 9 Oct 15:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £300.00
Jon Haskins · 30 Sep 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £300.00
Jon Haskins · 28 Sep 17:00
First day on site: Chris, Sam
Site app · 28 Sep 07:30
Booked: £8,100 ex VAT
Owen · 11 Sep 11:00