Kitchen · domestic · fixed price
Job 3975
CompleteKitchen and utility fit-out
For Hannah and Adam Merrick, Cotham. Crew A with Kate Lyons. On site 13 May to 27 May, handed over 31 May 2026.
Agreed price
£25,550
ex VAT
Final margin
20.1%
quoted 24.8%
100% of the work done17 cabinets
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
CostEstimateActual so farFinalDifference
Labour216 h logged against 195.5 h estimated, at each person's true cost rate£5,506£5,952£5,952+£4468.1% overMaterials6 purchases received£10,550£11,317£11,317+£7677.3% overSubcontract5 invoices from the electrician, plumber and plasterer£3,150£3,150£3,150On budgetTotal cost£19,206£20,419£20,419+£1,2136.3% overQuoted margin24.8%£6,344 on £25,550
Final margin20.1%£5,131 profit
Invoiced so far£25,550of £25,550, £25,550 paid
Where the money went
| Person | Hours | Labour cost | Difference |
|---|---|---|---|
SR Steve Rowe Lead fitter, crew A, £34/h at cost | 72 h of 68.5 h estimated | £2,448 of £2,329 | +£119 |
LD Liam Doyle Joiner, crew A, £30/h at cost | 72 h of 68.5 h estimated | £2,160 of £2,055 | +£105 |
JP Josh Penrose Apprentice joiner, crew A, £16/h at cost | 56 h of 43 h estimated | £896 of £688 | +£208 |
RF Rob Finch Decorator, £28/h at cost | 16 h of 15.5 h estimated | £448 of £434 | +£14 |
True labour cost. The 15 kitchens finished this year really took 12.95 h per cabinet, against the old rule of 11.5. This job: 17 cabinets, priced on 195.5 h. Rule of thumb: 11.5 h per cabinet. New quotes now use the true rate →
| Estimate line | Estimate | Ordered | Received | Difference |
|---|---|---|---|---|
Kitchen units and doors Wrenfold Kitchen Supply, PO-5269 | £6,120 | £6,426 | £6,426 | +£306 |
Worktops, templated and fitted Halbrook Worktops, PO-5294 | £2,850 | £3,172 | £3,172 | +£322 |
Plaster, board and sundries Avonmere Builders Merchants, PO-5299 | £420 | £460 | £460 | +£40 |
Timber, panels and fixings Kestle Timber, PO-5295 | £320 | £354 | £354 | +£34 |
Lighting and electrical fittings Voltmere Electrical Wholesale, PO-5300 | £420 | £444 | £444 | +£24 |
Splashback tiles and adhesive Brackwell Tiles, PO-5301 | £420 | £462 | £462 | +£42 |
Materials count when they are delivered and signed for on site. Nothing is on order and not received. Supplier bills post to Xero from here.
| Trade | Agreed | Invoiced | Difference |
|---|---|---|---|
Electrics Gary Pullen Electrical, 2 invoices | £1,420 | £1,420 | on the agreed price |
Plumbing Jon Haskins Plumbing and Heating, 2 invoices | £1,040 | £1,040 | on the agreed price |
Plastering Mark Dent Plastering, 1 invoice | £690 | £690 | on the agreed price |
The forecast counts each trade at its agreed price until it invoices more.
Agreed price
stage invoices at 25%, 50% and 25%
£25,550.00
Revenue
£25,550.00
Labour
final
- £5,952.00
Materials
final
- £11,316.92
Subcontract
final
- £3,150.00
Profit
20.1% margin, quoted at 24.8% (£6,344)
£5,131.08
Cost week by week
£20,419 spent over 3 weeks, against a £19,206 estimate
LabourMaterialsSubcontract
| Week of | Hours | Labour | Materials | Subcontract | Total |
|---|---|---|---|---|---|
| 11 May | 64 h | £1,792 | £7,683 | £1,230 | £10,705 |
| 18 May | 112 h | £3,072 | £3,634 | £690 | £7,396 |
| 25 May | 40 h | £1,088 | £0 | £1,230 | £2,318 |
Extras and variations · 0
Variations →No extras on this job.
Timesheets · 216 h, £5,952 at cost
Timesheets →| Week of | Person | Hours | Cost | Status |
|---|---|---|---|---|
| 25 May Tap for the days Tue 26 May8 hTS-00657 | JPJosh Penrose | 8 h 1 day | £128.00 at £16/h | approved from the paper sheets |
| 25 May Tap for the days Tue 26 May8 hTS-00658 | LDLiam Doyle | 8 h 1 day | £240.00 at £30/h | approved from the paper sheets |
| 25 May Tap for the days Tue 26 May8 hTS-00660 Wed 27 May8 hTS-00664 | RFRob Finch | 16 h 2 days | £448.00 at £28/h | approved from the paper sheets |
| 25 May Tap for the days Tue 26 May8 hTS-00662 | SRSteve Rowe | 8 h 1 day | £272.00 at £34/h | approved from the paper sheets |
| 18 May Tap for the days Mon 18 May8 hTS-00619 Tue 19 May8 hTS-00630 Thu 21 May8 hTS-00645 Fri 22 May8 hTS-00651 | JPJosh Penrose | 32 h 4 days | £512.00 at £16/h | approved from the paper sheets |
| 18 May Tap for the days Mon 18 May8 hTS-00620 Tue 19 May8 hTS-00631 Wed 20 May8 hTS-00639 Thu 21 May8 hTS-00646 Fri 22 May8 hTS-00652 | LDLiam Doyle | 40 h 5 days | £1,200.00 at £30/h | approved from the paper sheets |
| 18 May Tap for the days Mon 18 May8 hTS-00624 Tue 19 May8 hTS-00636 Wed 20 May8 hTS-00642 Thu 21 May8 hTS-00649 Fri 22 May8 hTS-00655 | SRSteve Rowe | 40 h 5 days | £1,360.00 at £34/h | approved from the paper sheets |
| 11 May Tap for the days Thu 14 May8 hTS-00601 Fri 15 May8 hTS-00610 | JPJosh Penrose | 16 h 2 days | £256.00 at £16/h | approved from the paper sheets |
| 11 May Tap for the days Wed 13 May8 hTS-00595 Thu 14 May8 hTS-00602 Fri 15 May8 hTS-00611 | LDLiam Doyle | 24 h 3 days | £720.00 at £30/h | approved from the paper sheets |
| 11 May Tap for the days Wed 13 May8 hTS-00596 Thu 14 May8 hTS-00605 Fri 15 May8 hTS-00614 | SRSteve Rowe | 24 h 3 days | £816.00 at £34/h | approved from the paper sheets |
Purchases · 6, £11,317
Purchases →| Order | What | Status | Net |
|---|---|---|---|
| PO-5301 Brackwell Tiles, raised 14 May | Splashback tiles and adhesive | Delivered 19 May, billed | £461.55 |
| PO-5299 Avonmere Builders Merchants, raised 11 May | Plaster, board and sundries | Delivered 14 May, billed | £460.24 |
| PO-5300 Voltmere Electrical Wholesale, raised 11 May | Lighting and electrical fittings | Delivered 14 May, billed | £443.61 |
| PO-5294 Halbrook Worktops, raised 10 May | Worktops, templated and fitted | Delivered 22 May, billed | £3,172.13 |
| PO-5295 Kestle Timber, raised 10 May | Timber, panels and fixings | Delivered 14 May, billed | £353.83 |
| PO-5269 Wrenfold Kitchen Supply, raised 20 Apr | Kitchen units and doors | Delivered 12 May, billed | £6,425.56 |
Subcontractor invoices · 5, £3,150
Tap one for the subcontractor| Invoice | Work | Status | Amount |
|---|---|---|---|
| SC-3589 Gary Pullen Electrical, 27 May | Electrics, second fix | Paid | £710.00 |
Gary Pullen ElectricalElectrician, Kingswood. Day rate £260. Insured to Mar 2027. Domestic jobs. Part P registered. | |||
| SC-3590 Jon Haskins Plumbing and Heating, 27 May | Plumbing, second fix | Paid | £520.00 |
Jon Haskins Plumbing and HeatingPlumber, Bedminster. Day rate £250. Insured to May 2027. Gas Safe registered. | |||
| SC-3579 Mark Dent Plastering, 19 May | Plastering, skim and making good | Paid | £690.00 |
Mark Dent PlasteringPlasterer, Brislington. Day rate £220. Insured to Feb 2027. Skim and dry-lining. | |||
| SC-3575 Jon Haskins Plumbing and Heating, 15 May | Plumbing, first fix | Paid | £520.00 |
Jon Haskins Plumbing and HeatingPlumber, Bedminster. Day rate £250. Insured to May 2027. Gas Safe registered. | |||
| SC-3573 Gary Pullen Electrical, 14 May | Electrics, first fix | Paid | £710.00 |
Gary Pullen ElectricalElectrician, Kingswood. Day rate £260. Insured to Mar 2027. Domestic jobs. Part P registered. | |||
Invoices · posted to Xero when sent
Billing →| Invoice | Stage | Status | Net | Gross | Xero |
|---|---|---|---|---|---|
| INV-2283 issued 26 Mar | Deposit 1 line | Paid 2 Apr | £6,387.50 | £7,665.00 | posted |
| INV-2326 issued 20 May | Progress 1 line | Paid 3 Jun | £12,775.00 | £15,330.00 | posted |
| INV-2334 issued 1 Jun | Completion 1 line | Paid 17 Jun | £6,387.50 | £7,665.00 | posted |
Stages £25,550 + billed extras £0 = £25,550 on invoices. £25,550 sent, £25,550 paid.
Client
Client page →Hannah and Adam Merrick
Hannah Merrick · client since 14 Mar 2026
Site96 Belmont Avenue, Cotham
Phone07700 900166
PortalLive: progress, extras, invoices
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewCrew A: Steve, Liam, Josh
Booked24 Mar 2026
StartedWed 13 May
Handed over31 May 2026
Timeline
Handed over and closed
Kate · 31 May 15:00
Gary Pullen Electrical: Electrics, second fix, £710.00
Gary Pullen · 27 May 17:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £520.00
Jon Haskins · 27 May 17:00
Delivered: Worktops, templated and fitted from Halbrook Worktops (PO-5294, £3,172.13)
Steve Rowe · 22 May 08:15
Mark Dent Plastering: Plastering, skim and making good, £690.00
Mark Dent · 19 May 17:00
Delivered: Splashback tiles and adhesive from Brackwell Tiles (PO-5301, £461.55)
Steve Rowe · 19 May 08:15
Jon Haskins Plumbing and Heating: Plumbing, first fix, £520.00
Jon Haskins · 15 May 17:00
Gary Pullen Electrical: Electrics, first fix, £710.00
Gary Pullen · 14 May 17:00
Delivered: Timber, panels and fixings from Kestle Timber (PO-5295, £353.83)
Steve Rowe · 14 May 08:15
Delivered: Plaster, board and sundries from Avonmere Builders Merchants (PO-5299, £460.24)
Steve Rowe · 14 May 08:15
Delivered: Lighting and electrical fittings from Voltmere Electrical Wholesale (PO-5300, £443.61)
Steve Rowe · 14 May 08:15
First day on site: Liam, Steve
Site app · 13 May 07:30
Delivered: Kitchen units and doors from Wrenfold Kitchen Supply (PO-5269, £6,425.56)
Steve Rowe · 12 May 08:15
Booked: £25,550 ex VAT
Owen · 24 Mar 11:00